Tred R. Eyerly - Insurance Law HawaiiFaced with an issue of first impression in California, the Court of Appeals held that a broker was not liable for failing to reveal the insurer's insolvency occurring after issuance of the policy. Pacific Rim Mechanical Contractors, Inc. v. Aon Risk Ins. Serv. West, Inc., 2012 Cal. App. LEXIS 232 (Cal. Ct. App. Feb. 28, 2012).
The developer for a construction project in downtown San Diego retained Aon as its broker to secure coverage. Aon procured a general liability policy for the project with Legion Indemnity Company. Legion was solvent when it issued the policy.
The developer hired Pacific Rim (“PacRim”) as one of several subcontractors on the project. The parties entered into a contract in which the developer agreed to provide PacRim with liability insurance through an Owner Controlled Insurance Program (“OCIP”). Aon was not a party to the contract and PacRim was never its client. PacRim, however, enrolled in the OCIP by contacting Aon and providing all necessary paperwork.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
The Business of Engineering: An Interview with Matthew Loos
July 15, 2019 —
Aarni Heiskanen - AEC BusinessMatthew Loos is an experienced project manager in the civil engineering industry. He works as a project engineer at Jones|Carter in Fort Worth, Texas. In this interview, we discuss Matt’s new book, The Business of Engineering.
It is not very common that an engineer writes a non-technical book. What inspired you to do so?
Have you ever gotten an idea stuck in your head that you just couldn’t let go of? A time when you couldn’t go to sleep because the idea was consistently begging for your attention?
That’s what happened to me. The idea for this book hits me right before bed, as most good ideas do. I couldn’t go to sleep after the idea struck me. I spent half of the night writing the chapters of this book in my mind. I had been thinking about the idea of engineering and how it relates to other career fields, even the non-technical ones. I was disenchanted with the trifling number of classes I took that prepared me for the business world. These were the initial thoughts that eventually led me down the road into thinking about engineering as a profession going forward.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Defeating the Ten-Year Statute of Repose For Latent Construction Defects
January 28, 2015 —
The Porter Law GroupIt is an all-too-common scenario in California construction: Nine and a half years after completion of a major California construction project, immediately before the 10-year “statute of repose” for suing on “latent” construction defects expires, a lawsuit claiming damages for “recently discovered” latent construction defects is filed. The property owner sues the contractor for the alleged defects. The direct contractor sues all its subcontractors for indemnity and defense. The attorneys spontaneously generate. Experts proliferate. Claimed defects are extrapolated. Four or five years later, after a few dozen attorneys earn a small fortune in fees, the insurance companies make payments. Attorneys collect more fees. The owners take what remains. They repair nothing... and buy vacation homes.
Perhaps a cynical view, but there are many in the construction defect world who would reach a similar conclusion. The question is: How can you defeat this seemingly inevitable chain of events? Under a case known as Brisbane Lodging L.P. v. Webcor Builders, Inc. 216 Cal.App 4th 1249 (2013) there may be hope. California Code of Civil Procedure sections 337.1 and 337.15 grant a 10-year “statute of repose” for bringing claims for “latent” construction defects. These statutes allow a lawsuit for such claimed defects to be filed in court up until ten years after the project has been completed. Latent defects are generally defined as those which are “not apparent by reasonable inspection” (CCP §337.15(b)). It is extremely common for such claims to be filed immediately before this 10-year deadline expires. When the lawsuit is brought, the cash register begins to ring.
Read the court decisionRead the full story...Reprinted courtesy of
The Porter Law Group
The Importance of the Subcontractor Exception to the “Your Work” Exclusion
May 16, 2018 —
John J. Kozak, Esq. - Florida Construction Law NewsCommercial General Liability (CGL) policies typically include a “your work” exclusion, excluding coverage for “’property damage’ to ‘your work’ arising out of it or any part of it and included in the ‘products-completed operations hazard.’” These CGL policies define “your work,” in pertinent part, as “work or operations performed by you or on your behalf.” (emphasis added). As the recent case of Mid-Continent Cas. Co. v. JWN Construction, Inc., 2018 U.S. Dist. LEXIS 20529 (S.D. Fla. 2018) reminds us, the “your work” exclusion can serve to eliminate coverage for a general contractor, even when property damage is caused by a subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
John J. Kozak, Esq., Cole, Scott & Kissane, P.A.Mr. Kozak may be contacted at
john.kozak@csklegal.com
Foreclosing Junior Lienholders and Recording A Lis Pendens
July 13, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen you foreclose on a construction lien, there are a couple of pointers to remember.
First, you want to make sure you include junior lienholders or interests you are looking to foreclose (or you want to be in a position to amend the foreclosure lawsuit to identify later). The reason being is you want to foreclose their interests to the property. “[J]unior interest holders are a narrow class of mortgagees whose interest in the underlying property is recorded after the foreclosing contractor’s claim of lien is filed. This class is routinely joined to the construction lien enforcement action under section 713.26 to allow the construction lienor to foreclose out the junior lienholder’s interest in the property encumbered by the construction lien.” See Decks N Sunch Marine, infra.
Second, you want to record a lis pendens with the lien foreclosure lawsuit. Failure to do so could be problematic because Florida Statute s. 713.22(1) provides in part, “A lien that has been continued beyond the 1-year period by the commencement of an action is not enforceable against creditors or subsequent purchasers for a valuable consideration and without notice, unless a notice of lis pendens is recorded.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Client Alert: Stipulated Judgment For Full Amount Of Underlying Claim As Security For Compromise Settlement Void As Unenforceable Penalty
March 26, 2014 —
David W. Evans, Krsto Mijanovic, and Gregory M. Smith-Haight Brown & Bonesteel LLPIn Purcell v. Schweitzer (No. D063435 - filed February 24, 2014, certified for publication March 17, 2014), the Fourth District Court of Appeal upheld an order setting aside a stipulated default judgment for the full amount of plaintiff’s claim which had been agreed to by the parties to a settlement agreement, finding that it constituted an unenforceable penalty because the amount bore no reasonable relationship to the settling party’s actual damages resulting from a breach of the settlement agreement.
In an agreement settling a breach of contract action seeking $85,000 in damages based on an unpaid debt, the plaintiff agreed to settle the claim and to accept $38,000 in 24 monthly installments, including interest on the unpaid principal at 8.5 percent. The agreement provided that payments were due on the first day of each month and to be considered “timely,” had to be received by the fifth day of each month. If any payment was not made on time, it was to be considered a breach of the entire settlement agreement, making the entire $85,000 original liability due pursuant to a stipulation for entry of judgment for such amount. The stipulation included language to the effect that the $85,000 figure accounted for the “economics” of further proceedings. The agreement also specified that the foregoing provision did not constitute an unlawful “penalty” or “forfeiture” and that defendant waived any right to an appeal and any right to contest or seek to set aside such a judgment.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
David W. Evans,
Krsto Mijanovic, and
Gregory M. Smith
Mr. Evans may be contacted at devans@hbblaw.com; Mr. Mijanovic may be contacted at kmijanovic@hbblaw.com, and Mr. Smith may be contacted at gsmith@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Are Defense Costs In Addition to Policy Limits?
December 02, 2015 —
Craig Martin – Construction Contractor AdvisorI recently had a discussion with an insurer about whether defense costs were included within the policy limits of a client’s coverage or in addition to policy limits. This was an important discussion because if costs of defense were included in the policy limits, my client was going to exceed those policy limits in a hurry. How would this situation play out with your insurance?
Fortunately, the majority of insurance policies, such as Commercial General Liability (CGL) policies, provide that defense costs are “in addition” to the policy limits. But some policies, often times referred to as “burning limits” policies, provide that cost of defense is included in the policy limits. This means that if you have $1,000,000.00 policy limits, your costs of defense will reduce that limit throughout the course of litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
ASCE Statement on Calls to Suspend the Federal Gas Tax
June 27, 2022 —
Tom Smith, Executive Director, American Society of Civil Engineers (ASCE)WASHINGTON, D.C. –
ASCE strongly opposes the recent announcement from the Biden Administration to suspend the current 18.4 cents-per-gallon federal gasoline tax for three months. Even at the same modest figure of 18 cents per gallon for over 25 years since 1993, the motor fuel tax has represented a reliable federal revenue source for communities to fix and modernize their network of roads, bridges, and transit systems.
Suspending the gas tax would result in the loss of billions in revenue from the Highway Trust Fund (HTF), significantly diminishing much of the progress made in the Bipartisan Infrastructure Law at a time when Americans expect improvements to the nation's roads, bridges, and transit systems. Replacing this lost revenue with funds from other sources is not a viable long-term solution and sets a damaging precedent. Encouraging states to follow suit will compound this bad idea and further exacerbate our nation's infrastructure funding challenges. Our transportation system, including roadways, bridge spans, and transit networks, can't rely on novel, unpredictable funding.
Further, there is little guarantee that motorists will see any real relief at the pump. Gas holidays aren't price controls; the manager at the gas station still gets to set their price. Oil producers have benefited significantly in the past from previous state-level gas tax holidays. There is no mechanism to ensure that these "savings" are passed on to consumers, but there is a virtual guarantee of disrupting transportation dollars and the HTF. While it sounds like an enticing solution when pocketbooks are strained, Congress knows that a variety of factors, including plain supply and demand, affect the prices that people see at fuel stations.
Now is the time to build on the momentum of the Bipartisan Infrastructure Law which, for the first time in decades, takes significant steps to revitalize our nation's aging infrastructure, improve public safety, strengthen our economy, and deliver well-paying jobs.
Read the court decisionRead the full story...Reprinted courtesy of