Insurer's Motion to Dismiss Complaint for Failure to Cover Collapse Fails
April 13, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe insurer was unsuccessful in moving to dismiss the property owner's complaint that was filed after coverage for collapse of basement walls was denied. Cyr v. CCAA Fire & Cas. Ins. Co., 2017 U.S. Dist. LEXIS 39387 (D. Conn. March 20, 2017).
The Cyrs began observing cracking patterns in the basement wall of their home. A structural engineer inspected the wall and determined that the cracks were due to a chemical reaction in the concrete that would ultimately render the walls unstable. The Cyrs made a claim with CCAA under their homeowner's policy. The insureds contended that the progressive deterioration of the concrete in the basement walls was a collapse under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
No Coverage for Faulty Workmanship Causing Property Damage to Insured's Product Only
October 07, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Nebraska court found there was no coverage for rebar that did not meet specifications and did not cause property damage to other portions of the construction project. Drake-Williams Steel, Inc. v. Cont'l Cas. Co., 2016 Neb. LEXIS 116 (Neb. Aug. 5, 2016).
The general contractor was hired by the city to build an arena. Drake-Williams Steel, Inc. (DWS) was hired to supply rebar for the arena. The rebar was improperly bent when it was fabricated by DWS and did not conform to the terms of the contract. The rebar was incorporated into three components of the arena: the columns, the grade beams, and the pile caps. The pile caps were made of concrete with reinforcing rebar and were installed below ground level on top of the concrete piles that extended to the bedrock. The grade beams were also made of concrete and rebar. The beams formed an oval around the arena and connected different pile caps together and were also installed below ground level. No corrections were made to the grade beams.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Las Vegas Sphere Lawsuits Roll On in Nevada Courtrooms
October 02, 2023 —
Richard Korman - Engineering News-RecordBig concerts have yet to start at Las Vegas’ distinctive new ball-shaped entertainment venue, but the legal noise over its construction has been heard in Clark County courtrooms for more than two years.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
DE Confirms Robust D&O Protection Despite Company Demise
February 18, 2015 —
James Yoder, Michael Onufrak and Siobhan Cole – White and Williams LLPOn Feb. 5, 2015, the United States Bankruptcy Court for the District of Delaware, per Judge Brendan L. Shannon, entered proposed findings of fact and conclusions of law in favor of the former president and CEO of Ultimate Escapes Inc., James M. Tousignant, and its chairman, Richard Keith, after determining that Tousignant’s actions in negotiating and executing a controversial asset purchase agreement were protected by the business judgment rule, despite the demise of the company a short time later. The failure of a business strategy, in and of itself, does not create liability on the part of the former directors and officers of a bankrupt company.
Background
Ultimate Escapes was a luxury destination club that provided its members with access to high-end vacation residences around the world. Unfortunately, Ultimate Escapes’ business suffered greatly from the economic downturn that began in 2008, and on Sept. 20, 2010, Ultimate Escapes filed voluntary petitions for relief pursuant to Chapter 11 of the Bankruptcy Code.
Reprinted courtesy of White and Williams LLP attorneys
James Yoder,
Michael Onufrak and
Siobhan Cole
Mr. Yoder may be contacted at yoderj@whiteandwilliams.com
Mr. Onufrak may be contacted at onufrakm@whiteandwilliams.com
Ms. Cole may be contacted at coles@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Ambush Elections are Here—Are You Ready?
May 07, 2015 —
Craig Martin – Construction Contractor AdvisorOn April 14, 2015, the National Labor Relations Board’s new election rule went into effect. The new rule, which shortens the time frame for union elections, will make it easier for unions to organize. Employers must get prepared now, not when they hear about an election. As the NLRB Members who dissented from the final rule noted:
"The Final Rule has become the Mount Everest of regulations: Massive in scale and unforgiving in its effect. Very few people will have the endurance to read the Final Rule in its entirety."
Here are some highlights of the new rule:
- Within 2 business days after service of the Notice of the Pre-Election Hearing, the employer must post a Notice of Petition for Election. The employer must also distribute the notice via e-mail if the employer customarily communicates with employees via e-mail.
- A Pre-Election hearing will be scheduled within 8 days from the Notice.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
OSHA’s Multi-Employer Citation Policy: What Employers on Construction Sites Need to Know
September 09, 2019 —
Phillip C. Bauknight - Construction ExecutiveMulti-employer worksites are a frequent occurrence in the construction industry as employees from various companies often occupy the same site while a project is being completed. While the need for employees from different companies may be necessary to perform the various tasks required by a project, the presence of multiple employers, and their employees, on the same worksite can result in an increased risk of safety hazards.
Companies performing construction work should be, and generally are, aware of OSHA’s ability to issue citations for workplace safety violations. What many companies may not know, however, is that OSHA’s ability to cite employers is not limited to workplace conditions that are unsafe only to that employer’s direct employees. Rather, OSHA also has the ability to cite an employer, and often does issue such citations, for conditions that could result in injury or death to another company’s employees.
The policy which provides OSHA with this citation ability is CPL 02-00-124 and is called the Multi-Employer Citation Policy (the “Policy”). Under the language of the Policy, OSHA has the ability to cite multiple employers for violations of the Occupational Safety and Health Act for the same hazardous workplace condition. Critically, responsibilities under the Policy do not depend on the employer’s job title but are determined by the employer’s role.
Reprinted courtesy of
Phillip C. Bauknight, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Bauknight may be contacted at
pbauknight@fisherphillips.com
Insureds Survive Motion to Dismiss Civil Authority Claim
September 29, 2021 —
Tred R. Eyerly - Insurance Law HawaiiAfter suffering business losses due to a hurricane, the insured's Civil Authority claim survived the insurer's motion to dismiss. Pathology Lab. v. Mt. Hawley Ins. Co., 2021 U.S. Dist. LEXIS 145129 (W.D. La. Aug. 3, 2021).
Hurricane Laura devastated Lake Charles, Louisiana causing severe damage to the insured property as well as other properties within a mile of the insured property. All seven electrical transmission line corridors feeding Lake Charles were catastrophically damaged causing an extensive power outage. Government shutdown Orders prohibited the insureds' access to the Lab. The Orders were issued by the respective civil authorities both in anticipation of and as a result of damage and dangerous physical conditions expected from and actually resulting from Hurricane Laura and the continuation thereof. When the hurricane arrived, all businesses that were not essential to the recovery were ordered closed until electricity, water and sewer services were restored. As a result, the Lab was closed from August 27, 2020 toSeptember 8, 2020.
The Lab sued for business income under the policy's Civil Authority provisions. Mt. Hawley moved to dismiss. Mt. Hawley argued that the Orders did not by their explicit terms close the Lab's business because closure was entirely dependent on the conditions of the described premises itself and whether it was safe to occupy. Mt. Hawley further argued that the mandatory Evacuation Order was issued in anticipation of property damage and therefore did not trigger coverage under the Civil Authority provision.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Public Contract Code 9204 – A New Mandatory Claims Process for Contractors and Subcontractors – and a Possible Trap for the Unwary
March 22, 2017 —
Alex R. Baghdassarian & Joseph S. Sestay – Peckar & Abramson, P.C.New California legislation affecting public works contractors was adopted pursuant to Assembly Bill 626, sponsored by the Union Trade Contractors Association of California and endorsed by various trade and contractor associations including the AGC. AB 626, which was intended to assist contractors in presenting claims against public agencies, affords new opportunities, and some potential pitfalls, to contractors and subcontractors submitting claims to public owners.
The legislation, codified at California Public Contract Code (PCC) section 9204, is effective for public works contracts entered into after January 1, 2017. All public entities (including the CSUS and the UC system), other than certain Departments of the State (CalTrans, High-Speed Rail Authority, Water Resources, Parks and Recreation, Corrections and Rehabilitation, General Services and the Military) are bound by the provisions of PCC Section 9204. PCC 9204 establishes a mandatory pre-litigation process for all claims by contractors on a public works project. It is an attempt to address the reluctance of public owners to promptly and fairly negotiate change orders on projects, putting some teeth to the mandate of existing law under PCC Section 7104, which precludes public owners from shifting to the contractor the risk of addressing differing subsurface and/or concealed hazardous site conditions.
Reprinted courtesy of
Alex R. Baghdassarian, Peckar & Abramson, P.C. and
Joseph S. Sestay, Peckar & Abramson, P.C.
Mr. Baghdassarian may be contacted at abaghdassarian@pecklaw.com
Mr. Sestay may be contacted at jsestay@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of