Court Provides Guidance on ‘Pay-When-Paid’ Provisions in Construction Subcontracts
July 13, 2020 —
Ted R. Gropman & Cindy J. Lee - ConsensusDocsOn April 17, the California Court of Appeal decided Crosno Construction, Inc. v. Travelers Casualty & Surety Company of America,1 effectively narrowing the scope of enforceable “pay-when-paid” provisions in construction subcontracts to the extent the subcontractor seeks recovery against a general contractor’s payment bond surety. Although the Crosno case involved a public works project, the rationale and holding should apply with equal force to private works projects. Basing the bulk of its decision on the Wm. R. Clarke Corp. v. Safeco Insurance Co.2 case, the court found that an open-ended “pay-when-paid” provision in a subcontract is not enforceable against a subcontractor that seeks to recover on a public works payment bond claim. This article discusses the Crosno decision and the implications for contractors on both sides of the contract moving forward.
Brief Case Summary
In Crosno, general contractor Clark Bros., Inc. contracted with the North Edwards Water District (the District) to build an arsenic removal water treatment plant. Clark hired steel storage tank subcontractor Crosno Construction, Inc. to build and coat two steel reservoir tanks. Clark and Crosno’s subcontract included a “pay-when-paid” provision, which stated that Clark would pay Crosno within a “reasonable time” of receiving payments from the owner, but “in no event less than the time Contractor and Subcontractor require to pursue to conclusion their legal remedies against Owner or other responsible party to obtain payment.” After Crosno completed its work, a dispute arose between Clark and the District, and the District withheld payment from Clark (including the monies earmarked for Clark’s subcontractors). Clark sued the District for payment, and Crosno filed its own action against Travelers Casualty and Surety Company of America, the surety on Clark’s statutory public works payment bond, for recovery of the unpaid subcontract balance. Travelers rejected Crosno’s bond claim as premature, invoking the “pay-when-paid” subcontract language and pointing to Clark’s pending payment action against the District. The issue on appeal was whether the “pay-when-paid” provision in the subcontract blocked Crosno from recovering under the payment bond from Travelers while Clark’s lawsuit against the District was still pending.
Reprinted courtesy of
Ted R. Gropman, Pepper Hamilton LLP and
Cindy J. Lee, Pepper Hamilton LLP
Mr. Gropman may be contacted at ted.gropman@troutman.com
Ms. Lee may be contacted at cindy.lee@troutman.com
Read the court decisionRead the full story...Reprinted courtesy of
Arbitration—No Opportunity for Appeal
October 22, 2014 —
Craig Martin – Construction Contractor AdvisorLast week I presented to the Great Plains Chapter of the American Society of Professional Estimators on arbitration and litigation. Some of the questions related to the difficulty of appealing an arbitrator’s decision. A Florida appellate court recently confirmed this difficulty.
In Village at Dolphin Commerce Center, LLC v. Construction Service Solutions, LLC, a contractor filed an arbitration claim against the owner to get paid for its work. The owner claimed that the contractor could not maintain the claim to get paid because the contractor was not licensed. Apparently, there is a law in Florida that a contractor unlicensed at the time of the contract cannot maintain an action in Florida for unpaid work.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Invest In America Act Offers 494 Billion In Funding to U.S. Infrastructure and Millions of New Jobs
July 20, 2020 —
Stefanie A. Salomon - Peckar & AbramsonThe Investing in a New Vision for the Environment and Surface Transportation in America (INVEST in America) Act was approved by the House Transportation and Infrastructure Committee on June 18, 2020 and is making its way up to Congress. The bill will create millions of jobs and provide substantial investment in the nation’s deteriorating highways, bridges and public transit systems. The bill also endeavors to leave behind a smaller carbon footprint, a major improvement for the nation’s biggest source of carbon pollution.
Investing in a New Vision for the Environment and Surface Transportation in America Act
According to the American Society of Civil Engineers, the current condition of the nation’s infrastructure earns a grade of D+, and there exists an estimated $2 trillion funding gap to bring it into a state of good repair by 2025. While Americans have benefited from a century of infrastructure building, neglect has befallen our once greatest achievements – the roadways and arteries that led to the explosive growth of our nation. In the 1930s, 4.2 percent of the country’s GDP was spent on infrastructure investment. Unfortunately, by 2016 that number fell to 1.5 percent resulting in the substandard conditions that now confront us. Stated more bluntly, our nation’s infrastructure is crumbling and immediate investment in required to bring it up to par. The INVEST in America Act is our “immediate” opportunity to start replacing the outdated systems of the past with smarter, safer, and more resilient infrastructure.
Read the court decisionRead the full story...Reprinted courtesy of
Stefanie A. Salomon, Peckar & AbramsonMs. Salomon may be contacted at
ssalomon@pecklaw.com
U.S. Tornadoes, Hail Cost Insurers $1 Billion in June
July 09, 2014 —
Kelly Gilblom – BloombergTornadoes, hail and windstorms that pounded the U.S. from the Rocky Mountains to the Tennessee Valley last month will probably cost insurers more than $1 billion, Aon Plc said in a report.
Hailstorms and winds greater than 90 miles an hour (145 kilometers) in June caused billions of dollars of economic losses, led by a full week of storms early in the month, the London-based insurance broker said today.
More than 300 tornadoes hit the U.S. last month, compared with 125 a year earlier and 111 in June 2012, according to preliminary data from the National Weather Service’s Storm Prediction Center. May, June and July tend to be the worst months for twisters, it said.
Severe weather from June 3 to June 9 this year killed three people and led to more than 100,000 claims, Aon said. Later in the month, “hail and winds gusting to hurricane strength tracked eastward,” the broker said in its report. The storm “shattered windows, punctured roofs and downed trees onto homes, structures and vehicles.”
Read the court decisionRead the full story...Reprinted courtesy of
Kelly Gilblom, BloombergMs. Gilblom may be contacted at
kgilblom@bloomberg.net
America’s Infrastructure Gets a D+
March 16, 2017 —
Garret Murai – California Construction Law BlogThe American Society of Civil Engineers (ASCE) has issued their 2017 Infrastructure Report Card, which assigns a letter grade to the nation’s infrastructure.
Our country’s grade in 2017? A disappointing D+.
Although, if you’re a glass half full kind of person (bless your soul) at least our grade didn’t fall since the last report card was issued in 2013, when our grade was a D+ as well.
In short, we suck. Although, apparently, we don’t suck evenly across the board.
ASCE has divided its cumulative GPA into grades for specific courses, if you will. Our transit systems received a grade of D-; our airports, dams, drinking water and waste water plants, inland waterways, levees and roads received a grade of D; our power plants, hazardous waste plants, public parks and schools received a grade of D+; our bridges, ports and solid waste plants a grade of C+, and our rail systems received a grade of B.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Be Sure to Bring Up Any Mechanic’s Lien Defenses Early and Often
November 27, 2023 —
Christopher G. Hill - Construction Law MusingsAs those of you who regularly read Musings are aware, mechanic’s liens are a big part of my law practice and a big issue here at this construction law blog. I’ve discussed the picky requirements of the mechanic’s lien statutes in Virginia and how the 90 and 150-day rules are strictly enforced. However, a recent case out of the City of Norfolk Virginia Circuit Court cautions that while failure to meet these strict requirements may invalidate a lien, it only does so if the owner or general contractor seeking to invalidate the lien argues the invalidity and/or presents evidence of that invalidity either pretrial or during trial.
In Premier Restoration LLC v. Barnes, the Court considered the following facts. The defendant homeowners had a house fire and the resulting damage was the subject of an insurance claim that was paid and checks sent to the homeowners. Premier filed a mechanic’s lien in response to Barnes’s failure to pay for Premier’s restoration construction services after Barnes’s home was destroyed by fire. Premier seeks a decree to enforce the lien, asking the court to order the sale of Barnes’s property to recover its damages or, alternatively, a judgment in its favor. With the Complaint seeking enforcement of the lien and damages for breach of contract, and this is a key point, Premier provided a copy of the mechanic’s lien along with the affidavit that is part of the statutory form swearing that the Owner was justly indebted to Premiere. The homeowners filed a counterclaim for unfinished work, including unfinished punch list work. After a trial during which no evidence regarding either the timeliness of the lien recording or whether any of the work sought to be encompassed in the lien was performed outside of the statutory 150-day window was presented by either side, the defendants filed a post-trial motion seeking to invalidate the lien as including sums for work outside of the 150-day window.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
EPA and the Corps of Engineers Repeal the 2015 “Waters of the United States” Rule
January 13, 2020 —
Anthony B. Cavender - Gravel2GavelThe pre-publication version of the final rule to be promulgated by EPA and the U.S. Army Corps of Engineers (ACOE) to repeal the 2015 redefinition of the Clean Water Act’s term “Waters of the United States” which is the linchpin of these agencies’ regulatory power under the CWA, was made available on September 12, 2019. The rule should be published in the Federal Register in the next few weeks, and it will be effective 60 days thereafter. Many challenges are expected to be filed in the federal courts.
The 2015 rule was very controversial, and petitions challenging the rule were filed in many federal district courts, several courts of appeal, and finally in the Supreme Court (see NAM v. Department of Defense), which held that all initial challenges must be filed in the federal district courts. The upshot of these challenges is that, at this time, the 2015 rule has been enjoined in more than half the states while the other states are bound by the 2015 rule, a situation which is frustrating for everyone.
In addition to repealing the 2015 rule, the agencies also restored the pre-2015 definition had had been in place since 1986. As a result, the pre-2015 definition of waters of the U.S. will again govern the application of the following rules: (a) the ACOE’s definition of “waters of the U.S.” at 33 CFR Section 328.3; (b) EPA’s general Oil Discharge rule at 40 CFR Section 110; (c) the SPCC rules at 40 CFR Part 112; (d) EPA’s designation of hazardous substances at 40 CFR Part 116; (e) EPA’s hazardous substance reportable quantity rule at 40 CFR Part 117; (f) the NPDES permitting rules at 40 CFR Part 122; (g) the guidelines for dredged or fill disposal sites at 40 CFR Part 230; (g) Exempt activities not requiring a CWA 404 permit (guidelines for 404 disposal sites at 40 CFR Part 232); (h) the National Contingency Plan rules at 40 CFR Part 300; (i) the designation of reportable quantities of hazardous substances at 40 CFR Part 302; and (j) EPA’s Effluent Guidelines standards at 40 CFR Part 401.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Ninth Circuit Issues Pro-Contractor Licensing Ruling
July 18, 2018 —
Amy L. Pierce – Gravel2Gavel Construction & Real Estate Law BlogOn July 10, the U.S. Court of Appeals for the Ninth Circuit issued its much anticipated and a pro-contractor ruling in MP Nexlevel of California, Inc. v. CVIN LLC. The appeal arose from a dispute over the scope of a California specialty contractor’s license and, more particular, involved whether the subcontractor’s performance of certain work was outside the scope of its license constituting a breach of contract and resulting in the contractor not being entitled to payment for its work (Cal. Bus. & Prof. Code § 7031(a)). In an unpublished opinion, the Ninth Circuit reversed and remanded the matter, finding that “Nexlevel’s work here was ‘incidental and supplemental’ to the installation of these fiberoptic systems,” as contemplated by Cal. Code Regs. Tit. 16, § 831.
Read the court decisionRead the full story...Reprinted courtesy of
Amy L. Pierce, Pillsbury Winthrop Shaw Pittman LLPMs. Pierce may be contacted at
amy.pierce@pillsburylaw.com