State And Local Bid Protests: Sunk Costs and the Meaning of a “Win”
July 11, 2022 —
Amy Anderson - ConsensusDocsAcross the United States, state and local agencies often use competitive bidding to award contracts for various types of work. Generally speaking, a bid protest is when an unsuccessful bidder challenges the award by the state or local agency to another competitive bidder. Procurement at this level is entirely distinct from federal procurement.
The details of any bid protest will be specific to the locality. However, a question that very often comes up when a state or local agency uses competitive bidding: what happens when I lose the bid? More specifically, if I should not have lost because my bid was the lowest or best value, can I make the state or local agency award the bid to me?
Read the court decisionRead the full story...Reprinted courtesy of
Amy Anderson, Jones Walker LLP (ConsensusDocs)Ms. Anderson may be contacted at
aanderson@joneswalker.com
Angela Cooner Appointed Vice-Chair of Arizona’s Inaugural Board of Legal Specialization Construction Defect Law Advisory Commission
June 20, 2022 —
Angela Cooner - Lewis BrisboisPhoenix, Ariz. (May 17, 2022) - Phoenix Partner Angela Cooner has been appointed as the vice-chair of the State Bar of Arizona’s inaugural Board of Legal Specialization Construction Defect Law Advisory Commission. The commission was created pursuant to the Arizona Supreme Court’s recent administrative order recognizing construction defect law as a new area of specialization.
The commission will, among other things, create the application, examination, and interview process that Arizona attorneys will be required to complete to earn the construction defect law specialized certification. Ms. Cooner will serve a two-year term that will end on January 31, 2024.
Read the court decisionRead the full story...Reprinted courtesy of
Angela Cooner, Lewis BrisboisMs. Cooner may be contacted at
Angela.Cooner@lewisbrisbois.com
Not So Fast, My Friend: Pacing and Concurrent Delay
April 25, 2022 —
William E. Underwood - ConsensusDocsWhen critical path activities are delayed by the owner (or another party), contractors will sometimes “pace,” or slow down, other activities to match the owner-caused delay. After all, why should the contractor hurry up and wait? But paced activities can often appear as concurrent delays on a project’s overall schedule. And all too often, contractors fail to contemporaneously document their efforts to pace work. Not only can this create avoidable disputes with owners and other contractors, but it can also create future roadblocks to the recovery of delay damages. This article examines the interplay between pacing and concurrent delay[1] and what contractors should do to minimize risk and preserve their rights to obtain more than a simple time extension for project delays.
Pacing versus Concurrent Delay
As a basic matter, most contracts allocate responsibility/liability for a schedule delay to the party that caused the delay. For example, if an owner is contractually required to provide equipment for a contractor to install, then the owner likely bears responsibility for any delays caused if the equipment is delivered late. If, however, the contractor was also behind schedule on other activities during this time and the project would have been delayed regardless of the owner’s late deliveries, then the delay is probably concurrent. And the contractor will generally be entitled to only an extension of time, and no other monetary relief.
Read the court decisionRead the full story...Reprinted courtesy of
William E. Underwood, Jones Walker LLP (ConsensusDocs)Mr. Underwood may be contacted at
wunderwood@joneswalker.com
Court Requires Adherence to “Good Faith and Fair Dealing” in Construction Defect Coverage
September 30, 2011 —
CDJ STAFFThe California Court of Appeals has ruled in the case of Allied Framers, Inc. v. Golden Bear Insurance Company. Allied had been sued in a construction defect case and its primary insurer had become insolvent. Coverage for Allied’s defense was paid for by the California Insurance Guarantee Association through June 8, 2006. When warned that CIGA’s involvement was ending, Allied notified Golden Bear, which declined to provide coverage.
In the matters that followed, Golden Bear claimed that Allied had not exhausted its $1 million in primary insurance. Allied then showed that $1 million had already been paid out in the case. A few months thereafter, Golden Bear offered a $500,000 settlement on behalf of Allied which was rejected. Thereafter, Golden Bear hired new counsel to defend Allied. Golden Bear received, but allegedly did not pay, invoices Allied sent from their former counsel. Golden Bear finally settled the construction defect case for $2 million.
Allied’s original counsel sued Allied for payment. Golden Bear declined coverage. Allied then claimed that Golden Bear liable on several counts, arising from its failure to settle the construction defect action earlier than it did and its failure to pay Allied’s counsel. Golden Bear demurred, arguing that Allied had now exhausted is coverage with the $2 million settlement. The lower court sustained Golden Bear’s demurrer, dismissing Allied’s complaints.
The appeal court reviewed Allied’s seven complaints and sustained most of them. However, the court did reverse the trial court’s order in regard to Allied’s complaint that Golden Bear breached an implied covenant of good faith and fair dealing. The appeals court was not convinced that Golden Bear properly evaluated the settlement demand in the underlying construction defect case. The court found three other ways in which Golden Bear’s actions might show bad faith, in refusing to pay defense fees “after promising [Allied] such costs would be paid in full,” “failing to advise Allied about ‘actual or potential negative consequences of agreeing to the proposed settlement,’” and that their choice of counsel “failed to protect [Allied’s] interests in the negotiation.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Court of Federal Claims: Upstream Hurricane Harvey Case Will Proceed to Trial
July 02, 2018 —
Anthony B. Cavender - Gravel2Gavel Construction & Real Estate Law Blog On May 24, the U.S. Court of Federal Claims decided one of what may be many cases involving the terrible flooding wrought by Hurricane Harvey in the Houston, TX region. The Court of Federal Claims has divided thousands of pending claims into “upstream” and “downstream” categories, depending on whether the flooded properties were located upstream or downstream of two U.S. Army Corps of Engineers (Corps) flood control reservoirs that were constructed in the 1940s and 1950s. The case is In re Upstream Addicks and Barker (Texas) Flood-Control Reservoirs; however, the Court of Federal Claims’ order in this case applies to “all upstream cases.”
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, Pillsbury Winthrop Shaw Pittman LLPMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
The Law Clinic Paves Way to the Digitalization of Built Environment Processes
February 11, 2019 —
Aarni Heiskanen - AEC BusinessThe Law Clinic offers legal advice on digitalization to built environment innovators and experimenters and in the process helps lawmakers find the pain points in legislation.
In April 2018 the Finnish Ministry of the Environment launched an experimental legal service for real estate and construction professionals, municipalities, and lawmakers.
The cost-free service is like a helpdesk for anyone who has questions about real estate and construction laws and regulations and their interpretation as it applies to new digital processes. The Law Clinic is part of the national KIRA-digi project, which includes 138 experiments, many of which need legal advice for their execution.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
A Look Back at the Ollies
May 03, 2018 —
Beverley BevenFlorez-CDJ STAFFThe Jerrold S. Oliver Award of Excellence, also known as the “Ollie” award, is presented to “an individual who is outstanding or has contributed to the betterment of the construction defect community.” West Coast Casualty asks members of the construction defect community to nominate those they feel are deserving of the award, and then members vote for one of four nominees. The award is presented at the West Coast Casualty Seminar. Those recognized receive a plaque and a donation in the winner’s name to Habitat for Humanity as well as a local California and Nevada charity.
Jerrold S. Oliver was a “’founding father’ in the alternate resolution process in construction defect claims and litigation. His loyalty and commitment to this community were beyond mere words as he was a true believer in the process of resolution.”
Past Award Winners:
1996 - Awarded to Ross R. Hart, Esq. (Mediator - American Arbitration Assoc.)
1997 - Awarded to Merv Thompson, Esq. (Mediator in private practice)
1999 - Awarded to Tom Craigo, (Adjuster - C.N.A. Insurance Company)
2000 - Awarded to Kristi Cole, (Adjuster - Safeco Insurance Company)
2001 - Awarded to Karen Rice, (Claims Manager - ACE / USA)
2002 - Awarded to Stephen Henning, Esq. (Wood, Smith, Henning and Berman, LLP)
2003 - Awarded to Ross Feinberg, Esq. (Feldscott, Lee, Feinberg, Grant and Mayfield LLP)
2004 - Awarded to Janet Shipes (Adjuster – C.N.A. Insurance Company)
2005 - Awarded to Edward Martinet (Expert – MC Consultants)
2006 - Awarded to Hon. Victoria V. Chaney (Judge – Los Angeles Superior Court)
2007 - Awarded to Bruce Edwards, Esq. (Mediator) JAMS
2008 - Awarded to Gerald Kurland, Esq. (Mediator) JAMS
2009 - Awarded to Keith Koeller, Esq. (Koeller, Nebecker, Carlson and Haluck, LLP)
2010 - Awarded to Terry Wolcott – (Construction Defect Manager – Travelers Ins. Co.)
2011 - Awarded to George Calkins, Esq. (Mediator) JAMS
2012 - Awarded to Joyia Greenfield, Esq. (Lorber, Greenfield and Polito, LLP)
2013 - Awarded to Margee Luper (Claim Manager – XL Insurance Group)
2014 - Awarded to Matt Liedle, Esq. (Liedle, Lounsbery, Larson & Lidl, LLP)
2015 - Awarded to Robert A. Bellagamba, Esq. (Special Master/Mediator, Castle & Dekker)
2016 - Awarded to Lisa Unger, (Senior Claims Examiner, Global Management Liability Markel)
2017 - Awarded to Caryn Siebert, (Vice President, Claims, Knight Insurance Group)
Read the court decisionRead the full story...Reprinted courtesy of
Corps of Engineers to Prepare EIS for Permit to Construct Power Lines Over Historic James River
May 01, 2019 —
Anthony B. Cavender - Gravel2GavelOn March 1, the U.S. Court of Appeals for the District of Columbia decided National Parks Conservation Assoc. v. Todd T. Simonite, Lieutenant General, et al. The case involves an application to the U.S. Army Corps of Engineers (Corps) for a construction permit to build electric power lines over the “historic James River, from whose waters Captain John Smith explored the New World.”
The Corps concluded after reviewing the thousands of comments submitted to it in connection with this application, and after considering the views of several government agencies and conservation groups, that an Environment Impact Statement (EIS) was not required, and that its Environmental Assessment assured the Corps that the project would not result is significant environmental impacts. The Court of Appeals has concluded that, based on this evidence, the Corps’ refusal to prepare an EIS thoroughly discussing all these points was arbitrary and capricious. The Corps has been ordered to prepare the EIS and to take special note of its obligations under the National Environmental Protection Act (NEPA), the Clean Water Act (CWA) and its obligations under the National Historic Preservation Act.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com