D.C. Decision Finding No “Direct Physical Loss” for COVID-19 Closures Is Not Without Severe Limitations
August 24, 2020 —
Michael S. Levine & Michael L. Huggins - Hunton Andrews KurthOn August 6, 2020, in Rose’s 1 LLC, et al. v. Erie Insurance Exchange, Civ. Case No. 2020 CA 002424 B, a District of Columbia trial court found in favor of an insurer on cross motions for summary judgment on the issue of whether COVID-19 closure orders constitute a “direct physical loss” under a commercial property policy.
At its core, the decision ignores key arguments raised in the summary judgment briefing and is narrowly premised on certain dictionary definitions of the terms, “direct,” “physical,” and “loss.” Relying almost entirely on those definitions – each supplied by the insureds in their opening brief – the court set the stage for its ultimate conclusion by finding “direct” to mean “without intervening persons, conditions, or agencies; immediate”; and “physical” to mean “of or pertaining to matter ….” The court then apparently accepted the policy’s circular definition of “loss” as meaning “direct and accidental loss of or damage to covered property.” Importantly, however, despite recognizing the fundamental rule of insurance policy construction that the court “must interpret the contract ‘as a whole, giving reasonable, lawful, and effective meaning to all its terms, and ascertaining the meaning in light of all the circumstances surrounding the parties at the time the contract was made,’” the court apparently ignored the insureds’ argument that the term “property damage” is specifically defined in the policy to include “loss of use” without any specific reference to physical or tangible damage.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Michael L. Huggins, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Huggins may be contacted at mhuggins@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Venture Sues LAX for Nonpayment
February 05, 2014 —
Beverley BevenFlorez-CDJ STAFFConstruction joint venture Walsh/Austin filed suit against the Los Angeles International Airport, claiming that “the airport failed to properly pay more than $2.4 million to an electrical subcontractor,” according to The Daily Breeze. Furthermore, SASCO, the electrical firm, alleged that they were “given inaccurate design documents that made it impossible for the company to carry out the work at the agreed-upon rate.”
The complaint, as reported by The Daily Breeze, cited “other lawsuits brought by an Orange County plastering firm and a Buena Park door company” and suggested that “eventually, all the litigation tied to nonpayment at LAX will end up in the same courtroom.”
Nancy Castles, a spokeswoman for Los Angeles World Airports, told The Daily Breeze that “the agency does not comment on pending litigation.”
Read the court decisionRead the full story...Reprinted courtesy of
Tightest Credit Market in 16 Years Rejects Bernanke’s Bid
October 08, 2014 —
Prashant Gopal – BloombergJames Bregenzer, a 31-year-old marketing strategist in Chicago, was rejected for a mortgage in May after successfully financing two previous home purchases. The hitch this time: his monthly payment would have been $100 more than the lender was willing to approve.
Bregenzer is in good company. Standards in the U.S. are so high and inflexible that former Federal Reserve Chairman Ben S. Bernanke, now a Brookings Institute fellow-in-residence with a net worth of at least $1.1 million, said at a conference last week that he couldn’t refinance his house in Washington. Even some doctors struggle to get home loans if they’re self-employed.
“We asked if we could go over by $100 and were told that’s just not going to work,” said Bregenzer, who bought his first home before getting married in 2008. “The process of buying a home used to be stupid easy. Now, my wife and I were buying a home with two salaries, we make a heck of a lot more than I used to, and I have to go into great and terrible detail to show documentation.”
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net
Construction Defects could become Issue in Governor’s Race
October 22, 2014 —
Jesse Howard Witt – Acerbic WittAccording to today’s Denver Business Journal, construction defects have emerged as a potential issue in Colorado’s gubernatorial race. During last night’s debate, Republican challenger Bob Beauprez criticized incumbent Democrat John Hickenlooper for failing to help senators with a last-minute push to enact a bill stripping away homeowner protections in construction disputes. Republicans had argued that the bill was needed to appease apartment developers who claim that quality control and insurance costs are too high on condominium projects.
Read the court decisionRead the full story...Reprinted courtesy of
Jesse Howard Witt, The Witt Law FirmMr. Witt welcomes comments at www.wittlawfirm.net
Traub Lieberman Attorneys Lisa M. Rolle and Vito John Marzano Secure Dismissal of Indemnification and Breach of Contract Claims Asserted against Subcontractor
November 24, 2019 —
Lisa M. Rolle & Vito John Marzano - Traub Lieberman PerspectivesOn August 7, 2019, TLSS Partner Lisa M. Rolle and associate Vito John Marzano obtained a dismissal of all claims on behalf of their client, the subfloor subcontractor at the worksite, in a severed action filed in the Supreme Court of the State of New York, County of Kings.
In April 2014, plaintiff commenced suit against several defendants, including the general contractor, after he sustained an injury when he fell through temporary plywood while installing a staircase at a worksite in Brooklyn. In May 2018, plaintiff filed a note of issue and certified the matter as ready for trial. Immediately thereafter, the general contractor initiated a second third-party action against the subcontractor seeking common-law and contractual indemnification and breach of contract. The Court subsequently granted Traub Lieberman’s motion to sever the second third-party action and instructed the general contractor to file a new action.
After the general contractor recommenced suit, Traub Lieberman, on behalf of its client, the subcontractor, immediately moved to dismiss for failure to state a cause of action. In relevant part, Traub Lieberman pointed to the deposition testimony of the general contractor’s principal to establish that the subcontractor had finished its work on the permanent subfloor no less ten months to over a year prior to plaintiff’s accident, and that the subfloor required no alteration, repair or maintenance prior to or as a result of plaintiff’s accident. Further, the general contractor’s testimony pointed to work performed by another subcontractor that directly resulted in plaintiff’s injuries. It was also brought to the Court’s attention that plaintiff had testified that he fell through a temporary plywood floor, and that the subcontractor had only installed a permanent subfloor.
Reprinted courtesy of
Lisa Rolle, Traub Lieberman and
Vito John Marzano, Traub Lieberman
Ms. Rolle may be contacted at lrolle@tlsslaw.com
Mr. Marzano may be contacted at vmarzano@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Value in Recording Lien within Effective Notice of Commencement
August 03, 2020 —
David Adelstein - Florida Construction Legal UpdatesConstruction lien priority is no joke! This is why a lienor wants to record its construction lien within an effective notice of commencement. A lien recorded within an effective notice of commencement relates back in time from a priority standpoint to the date the notice of commencement was recorded. A lienor that records a lien wants to ensure its lien is superior, and not inferior, to other encumbrances. An inferior lien or encumbrance may not provide much value if there is not sufficient equity in the property. Plus, an inferior lien or encumbrance can be foreclosed.
An example of the importance of lien priority can be found in the recent decision of Edward Taylor Corp. v. Mortgage Electronic Registration Systems, Inc., 45 Fla.L.Weekly D1447b (Fla. 2d DCA 2020). In this case, a contractor recorded a notice of commencement for an owner. While an owner is required to sign the notice of commencement that the contractor usually records, in this case, the owner did not sign the notice of commencement. Shortly after, the owner’s lender recorded a mortgage and then had the owner sign a notice of commencement and this notice of commencement was also recorded. When there is a construction lender, the lender always wants to make sure its mortgage is recorded first—before any notice of commencement—for purposes of priority and has the responsibility to ensure the notice of commencement is recorded. Here, the lender apparently did not realize the contractor had already recorded a notice of commencement at the time it recorded its mortgage.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Plaintiffs Not Barred from Proving Causation in Slip and Fall Case, Even With No Witnesses and No Memory of Fall Itself
February 01, 2022 —
David Hoynacki, Arezoo Jamshidi & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPOn January 19, 2022, the California Court of Appeal, Second Appellate District (Los Angeles), held that a plaintiff is not barred as a matter of law from proving causation in a slip and fall case if there were no witnesses to the fall, and the plaintiff does not remember the fall itself. The Court of Appeal stated specifically that circumstantial evidence would permit a jury to make a “reasonable and probable inference” regarding contributing factors to a fall, even with no eye-witness evidence.
In
Kaney v. Mazza (BC619247, Jan. 19, 2022), plaintiff and appellant Lydia Kaney (Kaney), was visiting her sister in her rented home in September of 2014. At some point during the visit, the light in the bathroom at the top of the stairs stopped working—Kaney used the stairs, and fell. Kaney filed suit against her sister and the owner of the home alleging premises liability, negligence, and violation of the Americans with Disabilities Act (ADA). In her deposition, Kaney testified that she remembered going up to the bathroom, and then waking up on the floor in pain. She could not remember how she fell; she did not know if she had missed a step, or if she had slipped and fallen backwards. She speculated that a worn-out bath mat may have been the cause of the slip and fall because the rubber traction on the bath mat was worn away.
Reprinted courtesy of
David Hoynacki, Haight Brown & Bonesteel LLP,
Arezoo Jamshidi, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Mr. Hoynacki may be contacted at dhoynacki@hbblaw.com
Ms. Jamshidi may be contacted at ajamshidi@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Edison Utility Accused of Igniting LA Fire in Lawsuits
January 21, 2025 —
Jef Feeley, Mark Chediak & Malathi Nayak - BloombergEdison International Inc.’s southern California utility faces lawsuits blaming the energy provider’s equipment for igniting one of the wildfires still raging in the second-largest US metropolis.
The first of several suits filed Monday was brought on behalf of a group of homeowners, renters, business owners and others with properties destroyed by the deadly Eaton Fire in the Pasadena area. The complaints allege that Southern California Edison power lines were the cause of the blaze that leveled the community of Altadena. The initial suits are expected to be followed by thousands more legal claims.
Reprinted courtesy of
Jef Feeley, Bloomberg,
Mark Chediak, Bloomberg and
Malathi Nayak, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of