Courtney Arbucci, Peter A. Dubrawski & Austin F. Smith - Haight Brown & BonesteelIn Horne v. Ahern Rentals, Inc. (No. B299605, filed 6/10/2020 ord. publ. 6/10/2020), Plaintiffs filed a wrongful death action against Defendant Ahern Rentals, Inc. (“Ahern”) arising out of the fatal incident involving Ruben Dickerson (“decedent”), while employed by independent contractor 24-Hour Tire Service, Inc. Decedent was ultimately crushed on Ahern Rentals, Inc.’s property when a forklift that was improperly placed on uneven ground collapsed as decedent laid under the raised forklift as he performed tire maintenance.
Plaintiffs’ suit would normally be barred by the Privette line of decisions which arise out of the foundational principle that an independent contractor’s hirer presumptively delegates to the contractor its tort law duty to provide a safe workplace for the contractor’s employees. (Privette v. Superior Court (1993) 5 Cal.4th 689 (Privette).) The Privette rule is subject to a number of exceptions including the “peculiar risk” exception, the “nondelegable duty” exception and the “affirmative contribution” exception. (See Privette, supra.) Here, Plaintiffs’ claimed that their suit against Ahern arose out of the “affirmative contribution” exception to Privette as defined by Hooker v. Department of Transportation (2002) 27 Cal.4th 198, 202 (Hooker). Hooker allows suits otherwise barred by Privette to go forward if the hirer of the independent contractor “exercised control over safety conditions at the worksite in a way that affirmatively contributed to the employee’s injuries.”
Reprinted courtesy of Haight Brown & Bonesteel attorneys
Courtney Arbucci,
Peter A. Dubrawski and
Austin F. Smith
Ms. Arbucci may be contacted at carbucci@hbblaw.com
Mr. Dubrawski may be contacted at pdubrawski@hbblaw.com
Mr. Smith may be contacted at asmith@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Law Alert: Concrete Supplier Botches Concrete Mix, Gets Thrashed By Court of Appeal for Trying to Blame Third Party
January 21, 2015 —
Steven M. Cvitanovic and Whitney L. Stefko – Haight Brown & Bonesteel LLPOn January 8, 2015, the Second Appellate district affirmed judgment of the lower court in State Ready Mix Inc. v. Moffatt & Nichol, and barred a concrete supplier from blaming a third party consultant for the concrete supplier's failure to deliver concrete that met project specifications.
In 2012, Major Engineering Marine, Inc. was hired by a project manager to construct a harbor pier in the Channel Islands Harbor. Major hired State Ready Mix, Inc. to supply the concrete for the project. State wrote and submitted a concrete mix design and, at the request of Major, civil engineer Moffatt & Nichol reviewed and approved State's mix design at no charge.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Editorial: Qatar Is Champion of Safety Hypocrisy in Migrant Worker Deaths
December 26, 2022 —
ENR Editorial Board - Engineering News-RecordOnce the World Cup soccer tournament concludes, decency dictates that someone should put a wrecking ball to Qatar’s Al Bayt and Lusail stadiums, where the opening ceremonies and matches were held. There’s no polite way to say it: bulldozing the World Cup sports facilities is the only way to amplify to the world the cost in migrant construction workers lives in all that was constructed.
Reprinted courtesy of
ENR Editorial Board, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
No Coverage Where Cracks in Basement Walls Do Not Amount to Sudden Collapse
January 10, 2018 —
Tred Eyerly - Insurance Law HawaiiIn another of a series of collapse cases arising out of Connecticut, the federal district court found there was no coverage for the homeowner's cracked basement wall caused by defective concrete. Liston-Smith v. CSAA Fire & Cas. Ins. Co., 2017 U.S. Dist. LEXIS 206211 (D. Conn. Dec. 15, 2017).
Read the court decisionRead the full story...Reprinted courtesy of
Tred Eyerly, Insurance Law HawaiiTred Eyerly may be contacted at
te@hawaiilawyer.com
2019 Legislative Session
June 03, 2019 —
Steve Heisdorffer – Colorado Construction LitigationTwo bills under consideration as the end of the session nears contain significant changes to Colorado’s Consumer Protection Act (“CCPA”). The bills broaden remedies, make more conduct a breach of the CCPA, and include purely private transactions in the type of conduct that falls within the scope of the CCPA. The bills are House Bill 19-1289 (“House Bill”) and Senate Bill 19-237 (“Senate Bill”). As of April 29, 2019, the House Bill has passed the House. The Senate Bill has not progressed past introduction. It is unclear if both houses of the legislature will have an opportunity to vote on either or both bills before the session ends.
The House Bill makes a person liable for CCPA violations based on conduct engaged in “recklessly,” not just knowing conduct. No definition of the term “recklessly” is provided in the House Bill, but Colorado’s attorney general testified “recklessly” “means a company or person acted with reckless disregard for the truth.” (Page 2). No explanation was given of what the word “reckless” in the definition of “recklessly” meant in this context.
Another provision of the House Bill adds a “catch all” prohibition that labels as a deceptive trade practice knowingly or recklessly engaging in any unfair, unconscionable, deceptive, deliberately misleading, false or fraudulent act or practice. There is no indication how a person could “recklessly” engage in “deliberately misleading” acts or practices.
Read the court decisionRead the full story...Reprinted courtesy of
Steve Heisdorffer, Higgins, Hopkins, McLain & RoswellMr. Heisdorffer may be contacted at
heisdorffer@hhmrlaw.com
Insurance Policies and Indemnity Provisions Are Not the Same
October 19, 2020 —
Garret Murai - California Construction Law BlogJust because you own a pair of Air Jordans doesn’t make you Michael Jordan. In the next case, Carter v. Pulte Home Corporation, Case No. A154757 (July 23, 2020), the 1st District Court of Appeal denied an insurance carrier’s equitable subrogation claim explaining that an insurer’s obligations under its insurance policy are not the same as an idemnitee’s obligations under an indemnity provision. Or, as aptly put by the Court of Appeal, while a “subrogated insurer is said to ‘stand in the shoes’ of its insured, because it has no greater rights than the insured. Here . . . [the insurer] is seeking to stand in a different, more advantageous set of shoes.”
Carter v. Pulte Home Corporation
Pulte Home Corporation was sued for construction defects by 38 homeowners in two housing developments. Various subcontractors had worked on the projects, but under their subcontracts, each subcontractor agreed to indemnify Pulte from and against “all liability, claims, judgments, suits, or demands for damages to persons or property arising out of, resulting from, or relating to Contractor’s performance of work under the Agreement (‘Claims’) unless such Claims have been specifically determined by the trier of fact to be the sole negligence of Pulte . . . ”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Why Are Developers Still Pouring Billions Into Waterlogged Miami?
November 30, 2016 —
James Tarmy – BloombergOn Sunday, an ebullient procession of artists, performers, and city residents filled Collins Avenue between Miami Beach’s 32nd and 36th streets to inaugurate the Faena Forum, a 43,000--square-foot, $150 million, performing- and visual-arts space that’s the cultural centerpiece of the Faena District, a $1 billion development comprising luxury hotels, restaurants, and real estate. The complex is the brainchild of Alan Faena, an Argentinian fashion designer-cum-developer known for his all-white outfits, and Len Blavatnik, a Ukrainian born, New York-based billionaire whose net worth is estimated by Bloomberg Billionaires to be $18.6 billion.
The parade/carnival/performance was was titled “Side by Tide,” which might be an overly optimistic assessment of Miami Beach's sea level. With "king tides" flooding parking garages and a University of Miami study reporting that Miami Beach has seen a 200 percent increase in flooding in the last decade, the tide isn’t on anyone’s side. It’s already beneath the city, seeping upward, often as not, through the ground’s porous limestone and into buildings’ backlogged storm drains. Aside from ruining the undercarriages of residents’ Porsches, this ground-up flooding has a second, perhaps more deleterious effect on the long-term feasibility of Miami Beach: Normal defenses against a rising ocean—such as sea walls or dykes—are useless.
Read the court decisionRead the full story...Reprinted courtesy of
James Tarmy, BloombergMr. Tarmy may be followed on Twitter @jstarmy
The Increasing Trend of Caps in Construction Contracts and Negotiating Them
November 27, 2023 —
Jarred Trauth - ConsensusDocsRisks are inherent in every construction project and all parties involved face them: owners, designers, general contractors/builders, subcontractors, suppliers…. Equitably allocating such risks is one of the most important and most negotiated areas of any construction related contract. Limitations of liability provisions are key to risk allocation. These provisions include no damage for delay provisions and caps on delay damages, warranty limitations and exclusions, indemnity limitations, and consequential damage waivers. Another, and the focus of this article, is a liability cap fixing the total amount of damages for which a party may be liable under the contract (the “Liability Cap”). Liability Caps have become more and more common in construction and construction related contracts, including major component supply agreements and design agreements.
This article will discuss Liability Caps generally and considerations of an owner or contractor negotiating them, including carve-outs (i.e. exceptions) to them.
Read the court decisionRead the full story...Reprinted courtesy of
Jarred Trauth, Jones Walker LLPMr. Trauth may be contacted at
jtrauth@joneswalker.com