Property Damage, Occurrences, Delays, Offsets and Fees. California Decision is a Smorgasbord of Construction Insurance Issues
November 21, 2017 —
Garret Murai - California Construction Law BlogOriginally published by CDJ on November 15, 2017
I read once that 97 percent of cases never go to trial. However, there are still the ones that do. And, then, there are the ones that do both. The following case, Global Modular, Inc. v. Kadena Pacific, Inc., California Court of Appeals for the Fourth District, Case No. E063551 (September 8, 2017), highlights some of the issues that can arise when portions of cases settle and other portions go to trial, the recovery of delay damages on a construction project through insurance, and the recovery of attorneys’ fees.
Global Modular, Inc. v. Kadena Pacific, Inc.
The U.S. Department of Veterans Affairs contracted with general contractor Kadena Pacific, Inc. (Kadena) to oversee construction of its Center for Blind Rehabilitation in Menlo Park, California. Kadena, in turn, contracted with subcontractor Global Modular, Inc. (Global) to construct, deliver and install 53 modular units totaling more than 37,000 square feet for a contract price of approximately $3.5 million.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Georgia Court of Appeals Upholds Denial of Coverage Because Insurance Broker Lacked Agency to Accept Premium Payment
December 07, 2020 —
Lawrence J. Bracken II, Michael S. Levine & Rachel E. Hudgins - Hunton Insurance Recovery BlogIn American Reliable Insurance Company v. Lancaster, the Georgia Court of Appeals reversed the denial of a property insurer’s summary judgment motion concerning the insurer’s denial of a fire loss claim. The basis of the denial was that the policyholders had failed to pay the policy premium. The policyholders, Charlie and Wanda Lancaster, claimed that they had paid their policy premiums for several years to their insurance agent, Macie Yawn. In October 2014, American Reliable mailed a renewal notice to the Lancasters notifying them that premium payments had to be made directly to the insurer. After it did not receive payment from the Lancasters, American Reliable sent them a cancellation notice in December 2014, again notifying them that payments be made directly to the insurer. The Lancasters denied having received either notice from American Reliable, but the record included a receipt for certificate of mailing.
After the Lancaster’s home burned down in 2015, American Reliable denied coverage on the grounds that the policy had been cancelled for nonpayment of premium. In the subsequent coverage action, the trial court denied American Reliable’s motion for summary judgment, ruling that a factual issue existed as to the actual and apparent agency of the insurance agent, Yawn. On appeal, the Court of Appeals found that the trial court erred in deciding that there was a factual issue concerning Yawn’s agency. Specifically, the Court of Appeals ruled that the record showed American Reliable had terminated Yawn’s agency to accept policy premiums, and that the Lancaster’s received notice of that termination in the renewal and cancellation notices. In addition to determining that Yawn was not an actual agent, the Court held that Yawn did not have apparent agency, because the notices sent to the Lancasters stated that the premium payment was to be paid to American Reliable, not to the agent.
Reprinted courtesy of
Lawrence J. Bracken II, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and
Rachel E. Hudgins, Hunton Andrews Kurth
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Hudgins may be contacted at rhudgins@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Break out the Neon: ‘80s Era Davis-Bacon “Prevailing Wage” Definition Restored in DOL Final Rule
August 21, 2023 —
A. Scott Hecker & Ted North - The Construction SeytOn August 8, 2023, the U.S. Department of Labor (DOL)
announced its
final rule related to the Davis-Bacon Act (the “Act”), entitled “Updating the Davis-Bacon and Related Acts Regulations.” However, the official final rule must be published in the Federal Register – likely by week’s end – before going into effect 60 days after publication.
DOL issued its notice of proposed rulemaking (“NPRM”) in March 2022 and received more than 40,000 comments from interested stakeholders. Evaluating and addressing those comments took the better part of a year, as DOL did not send the rule to the Office of Information and Regulatory Affairs (“OIRA”) for White House approval until December 16, 2022. After languishing for months, OIRA has now concluded its review, allowing DOL to move forward with its final rule.
Reprinted courtesy of
A. Scott Hecker, Seyfarth and
Ted North, Seyfarth
Mr. Hecker may be contacted at shecker@seyfarth.com
Mr. North may be contacted at enorth@seyfarth.com
Read the court decisionRead the full story...Reprinted courtesy of
Nebraska Joins the Ranks—No CGL Coverage for Faulty Work
September 17, 2014 —
Craig Martin – Construction Contractor AdvisorThe Nebraska Court of Appeals has ruled that a home builder that fails to adequately compact the soil does not have insurance coverage to repair damages to the home caused by the settling soil. In “insurance speak”, there was no occurrence to trigger coverage.
In this case, Cizek Homes, Inc. v Columbia National Insurance Company, a home builder contracted with a buyer to build a house. A lot was selected and the home was built. After the buyer moved in, the house started to settle, causing damage to the house. The buyer told the builder about these problems and the builder agreed to fix the problems. The builder also contacted its insurance company and requested coverage for the buyer’s claim. The insurer rejected the claim, determining that the buyer’s claim was not covered by the builder’s Commercial General Liability (CGL) insurance.
The insurer then filed suit asking the court to interpret the insurance policy and to determine whether the CGL insurance covered the claim. The court looked to the buyer’s allegations that the builder failed to construct the home in accordance with accepted construction and industry standards and that the builder was negligent in designing and constructing the home. The builder admitted that it was obligated to pay for the costs of repairs, but denied that it was negligent in constructing the home.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Does the Miller Act Trump Subcontract Dispute Provisions?
May 16, 2018 —
Christopher M. Horton - Smith CurrieAll general contractors performing public building or public works contracts with the federal government must be familiar with the Miller Act. It is a requirement for doing business with the federal government. Pursuant to the Miller Act, a general contractor entering into a public building or public works contract with the federal government must furnish a payment bond in an amount equal to the contract price, unless the contracting officer determines that it is impractical to obtain a bond in that amount and specifies an alternative bond amount.
Miller Act payment bonds guarantee payment to certain subcontractors and suppliers supplying labor and materials to contractors or subcontractors engaged in the construction. As a result, subcontractors have an avenue of relief should they not get paid for work done on the project. Specifically, subcontractors have a right to bring an action against the surety within 90-days after the date on which the person did or performed the last labor or furnished or supplied the last of material for which the claim is made. Any such action must be brought no later than one year after the date on which the person did or performed the last labor or furnished or supplied the last of material. 40 United States Code § 3133.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher M. Horton, Smith CurrieMr. Horton may be contacted at
cmhorton@smithcurrie.com
Columbus, Ohio’s Tallest Building to be Inspected for Construction Defects
July 16, 2014 —
Beverley BevenFlorez-CDJ STAFFFox 28 news reported that “[t]he state of Ohio is going to spend more than $166,000 to inspect…the 40-year-old Rhodes Tower” in Columbus.
"They're going to look at the exterior of the building - [at] sealants between the joints, the condition of the panels, the window systems, how they're draining, how they're operating, and how they're sealed," Ned Thiell, of Ohio Facilities Construction Commission, told ABC 6/FOX 28 news.
A study completed last year declared there were “’deficiencies’ on the building’s stone covering” and there were “panels with severe fracture defects” that “will need to be replaced with new stone panels.”
Read the court decisionRead the full story...Reprinted courtesy of
Mississippi River Spends 40 Days At Flood Stage, Mayors Push for Infrastructure Funding
June 18, 2019 —
Jeff Yoders - Engineering News-RecordAs record flooding continues across the Midwest, the region’s mayors and the Army Corps of Engineers are looking for solutions to mitigate future floods.
Read the court decisionRead the full story...Reprinted courtesy of
Jeff Yoders, ENRMr. Yoders may be contacted at
yodersj@enr.com
Exponential Acceleration—Interview with Anders Hvid
December 01, 2017 —
Aarni Heiskanen - AEC BusinessAnders Hvid is a Danish consultant, speaker, and author. He talks about digital disruption, exponential acceleration, and paradigm shifts that are taking place in a world that is moving from local and linear into global and exponential.
“I have a background in social studies. My interest is in humans, and systems in which they work together. I’ve always had a deep fascination with technology and how it influences our society, our jobs, our democracies, and systems,” Anders says. He visited Singularity University back in 2010, and that experience made a lasting impression on him. “It freaked me out, to be honest, and it opened my eyes to how important technology is.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi