Res Judicata Not Apply to Bar Overlapping Damages in Separate Suits Against Contractor and Subcontractor
November 06, 2023 —
David Adelstein - Florida Construction Legal UpdatesCan the doctrine of res judicata bar an owner’s claim against the general contractor after the owner also sued and obtained a satisfied judgment against the subcontractor when there are identical, overlapping damages pursued in separate lawsuits. A recent case says, not really.
In Pickell v. Lennar Homes, LLC, 48 Fla.L.Weekly D2037a (Fla. 6th DCA 2023), a homeowner sued a homebuilder and the homebuilder’s mechanical subcontractor in separate lawsuits. The claims and damages asserted in the separate lawsuits were substantially identical. The homeowner obtained a judgment against the mechanical subcontractor which was satisfied (i.e., paid). The homebuilder tried to use this as a get-out-jail-free card and claimed the homeowner was barred from suing it under the doctrine of res judicata based on overlapping claims and damages.
“To successfully assert a defense of res judicata, a party must prove four “identities”: “(1) identity of the thing sued for; (2) identity of the cause of action; (3) identity of persons and parties to the action; and (4) identity of the quality of the persons for or against whom the claim is made.” Pickell, supra (citation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Changes to Arkansas Construction and Home Repair Laws
September 30, 2011 —
CDJ STAFFA new law, set to take effect in 2012, lowers the ceiling on when work must be done by a licensed contractor. Through the end of the year, projects costing $20,000 or more had to be done by an Arkansas licensed contractor. As of January 1, 2012, that new limit will be $2,000.
This will apply to all single-family residences and according to Lovely County Citizen, covers “construction, alteration, renovation, repair, modification, improvement, removal, demotion, or addition to a pre-existing structure.” Residential building contractors will be required to have workers compensation insurance, as will home improvement contactors if they take jobs worth more than $20,000.
Morris Dillow, a building inspector in Holiday Island, said, “It will get these scammers out of here who are ripping people off.” He cited the example of a contractor who after getting paid for roof repairs and painting, left the job unfinished.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 and Mutual Responsibility Clauses
June 01, 2020 —
Joseph M. Leone - ConsensusDocsAs everyone knows, there is a tremendous amount of uncertainty in the construction industry due to the COVID-19 pandemic. Schedules, productivity, safety processes, and seemingly everything else are being affected. In these difficult times, most contractors are making every effort to work together to solve the problems caused by COVID-19. But what happens when differences arise between project owners, contractors, and subcontractors as to the effect of COVID-19 on a project? One party may want to continue pushing the schedule, others may want to slow down, or, more likely, not be able to keep up with the original schedule because of some reason related to COVID-19. As between a prime contractor and a subcontractor, a mutual responsibility clause can provide some clarity or, unfortunately, depending on how the subcontract is written, confusion.
Almost all subcontracts have a clause which flows down the prime contractor’s obligations on a project to the subcontractor as applicable to the subcontractor’s work. Known as “flow-down” clauses, this clause works in one direction; obligations of the prime contractor “flow-down” to the Subcontractor. A mutual responsibility clause, in essence, works in both directions. The subcontractor is required to perform its obligations consistent with the prime contractor’s obligations to the owner and the subcontractor is granted the same rights against the prime contractor which the prime contractor has against the owner. Obligations flow down and rights flow up. The rights and obligations flowing through the prime contractor include, the obligation to perform the work in accordance with the plans and specifications, the obligation to meet the schedule constraints in the prime agreement, and the right to extensions of time and change orders to the extent the prime contractor obtains the same.
Read the court decisionRead the full story...Reprinted courtesy of
Joseph M. Leone, Drewry Simmons Vornehm, LLP Mr. Leone may be contacted at
jleone@dsvlaw.com
Nevada Assembly Bill Proposes Changes to Construction Defect Litigation
April 14, 2011 —
Beverley BevenFlorez CDJ STAFFAssemblyman John Oceguera has written a bill that would redefine the term Construction Defect, set statutory limitations, and force the prevailing party to pay for attorney’s fees. Assembly Bill 401 has been referred to the Committee on Judiciary.
Currently, the law in Nevada states that “a defect in the design, construction, manufacture, repair or landscaping of a new residence, of an alteration of or addition to an existing residence, or of an appurtenance, which is done in violation of law, including in violation of local codes or ordinances, is a constructional defect.” However, AB401 “provides that there is a rebuttable presumption that workmanship which exceeds the standards set forth in the applicable law, including any applicable local codes or ordinances, is not a constructional defect.”
The Nevada courts may award attorney fees to the prevailing party today. However, AB401 mandates that attorney fees must be awarded, and the exact award is to be determined by the Court. “(1) The court shall award to the prevailing party reasonable attorney’s fees, which must be an element of costs and awarded as costs; and (2) the amount of any attorney’s fees awarded must be determined by and approved by the court.”
AB401 also sets a three year statutory limit “for an action for damages for certain deficiencies, injury or wrongful death caused by a defect in construction if the defect is a result of willful misconduct or was fraudulently concealed.”
This Nevada bill is in the early stages of development.
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Whose Employee is it Anyway?: Federal Court Finds No Coverage for Injured Subcontractor's Claim Based on Modified Employer's Liability Exclusion
September 28, 2020 —
Jeffrey J. Vita & Kerianne E. Kane - Saxe Doernberger & VitaIn Nagog Real Estate Consulting Corp. v. Nautilus Insurance Co.,1 the United States District Court for the District of Massachusetts held that an insurer had no duty to defend its insureds against claims brought by an injured subcontractor, based on an overbroad employer’s liability exclusion in the policy.
Nautilus Insurance Company issued a commercial general liability policy to developer Nagog Homes LLC and its related construction company, Nagog Real Estate. The policy was endorsed with an Employer’s Liability Exclusion (the L205 Endorsement) that expanded the scope of the standard exclusion in the coverage form to include bodily injury claims of employees of “any” insured and their contractors or subcontractors, as opposed to simply the employees of the named insured.
Nagog Homes was the developer, and Nagog Real Estate was the general contractor for a residential construction project. An employee of the framing subcontractor hired by Nagog Real Estate was injured while working on the project and sued both Nagog entities for his injuries. Nautilus, relying on the modified employer’s liability exclusion, denied coverage for the lawsuit based on allegations that the Nagog entities hired the framing subcontractor to perform work, which effectively made the plaintiff an employee of one or both of the Nagog entities.
Reprinted courtesy of
Jeffrey J. Vita , Saxe Doernberger & Vita and
Kerianne E. Kane, Saxe Doernberger & Vita
Mr. Vita may be contacted at jjv@sdvlaw.com
Ms. Kane may be contacted at kek@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
How Concrete Mistakes Added Cost to the Recent Frederick Douglass Memorial Bridge Project
December 16, 2023 —
Richard Korman - Engineering News-RecordA disputed insurance claim heading for trial next year over construction of Washington, D.C.'s two-year-old Frederick Douglass Memorial Bridge revolves around the design-build joint venture's problems in 2019 with concrete voids and honeycombing. The flaws required demolition and rebuilding costing millions of dollars.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Summary Judgment for Insurer Reversed Based on Expert Opinion
May 30, 2022 —
Tred R. Eyerly - Insurance Law HawaiiAfter the trial court discounted the insured's expert witness and granted summary judgment to the insurer, the Florida District Court of Appeal reversed. Morales v. Citizens Prop. Ins. Corp., 2022 Fla. App. LEXIS 1831 (Fla. Ct. App. March 15, 2022).
The insureds' property was allegedly damaged by Hurricane Irma in 2017. They filed a claim with Citizens. Citizens sent its adjuster and eventually denied the claim because the policy did not cover damages caused by wear and tear. Further, there was no coverage for loss caused by "rain . . . unless a covered peril first damages the building causing an opening in a roof or wall and the rain . . . enters through this opening."
The insureds sued and Citizens moved for summary judgment. At the hearing, Citizens' expert, a civil engineer, concluded that there were no storm-created openings in the roof. The insureds engaged a licensed contractor, Steven Delgado, who stated that he found significant damage to the roofing system and water intrusion through the roof. He observed loose shingles which were most likely damaged during Hurricane Irma, allowing for high winds and airborne debris to create small openings permitting water intrusion.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Washington Supreme Court Expands Contractor Notice Obligations
November 28, 2018 —
Brett M. Hill - Ahlers Cressman & Sleight BlogThe Washington State Supreme Court dealt another blow to public works contractors in Washington State. In a case recently issued by the court, Nova Contracting, Inc. v. City of Olympia, [1] the court expanded contractors’ obligations when providing notice on public works construction projects. The Nova Contracting case was the subject of a previous blog. The case involved Nova Contracting and the City of Olympia. Nova was the low bidder on the contract. Nova alleged that the City of Olympia did not want Nova to win the job and intentionally hindered Nova’s ability to perform the job. The facts alleged by Nova, which were covered in the previous blog, involved the City’s improper and apparently punitive rejection of submittals on the job and the City’s eventual wrongful termination of Nova. Of significance in the case is that Nova never actually began work on the job. All that Nova had done at the time of termination was begin mobilizing its equipment on site. The Court of Appeals found that Nova had alleged sufficient facts to establish that the City violated the duty of good faith and fair dealing by improperly rejecting Nova’s submissions and had breached the contract with Nova by improperly terminating.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers Cressman & Sleight PLLCMr. Hill may be contacted at