How the California and Maui Wildfires Will Affect Future Construction Projects
October 30, 2023 —
Susan Doering - Construction ExecutiveJust like any kind of fire, wildfires are caused by the presence of fuel and a spark. In the case of the
2017 fires in the wine country of California, along with the state's 2018
Camp Fire, the fuel was dry leaf litter, branches and downed trees. And the spark, in some cases, resulted from electric utility lines and, in other cases, due to contractor’s work.
More recently, this summer's Maui fires have taken hundreds of lives—deceased and missing—and burned more than 2,500 acres. Lahaina’s historic sites cannot be replaced, and estimates of the rebuild costs are near $5 billion. In Hawaii, the fuel was the same as in California: dried forest debris. It is alleged that the spark was from a powerline downed by extreme winds from Hurricane Dora. While sparks were present, it is the increased volume of fuel that has been the true source of the disastrous recent wildfires.
The increased presence of fuel is the result of recent changes in forestry-management practices, coupled with accelerated climatic shifts in recent years toward hotter, drier weather from 2011 to 2020 in California and 2022 to 2023 in Maui, increasing both frequency and severity.
Reprinted courtesy of
Susan Doering, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
South Carolina Clarifies the Accrual Date for Its Statute of Repose
March 18, 2019 —
William L. Doerler - The Subrogation StrategistIn Lawrence v. General Panel Corp., 2019 S.C. LEXIS 1, No. 27856 (S.C. Jan. 1, 2019), the Supreme Court of South Carolina answered a certified question related to South Carolina’s statute of repose, S.C. Code § 15-3-640,[1] to wit, whether the date of “substantial completion of the improvement” is always measured from the date on which the certificate of occupancy is issued. The court held that a 2005 amendment to § 15-3-640 did not change South Carolina law with respect to the date of substantial completion. Thus, under the revised version of § 15-3-640, “the statute of repose begins to run at the latest on the date of the certificate of occupancy, even if there is ongoing work on any particular part of the project.” A brief review of prior case law may assist with understanding the court’s ruling in Lawrence.
In Ocean Winds Corp. of Johns Island v. Lane, 556 S.E.2d 377 (S.C. 2001), the Supreme Court of South Carolina addressed the question of whether § 15-3-640 ran from substantial completion of the installation of the windows at issue or on substantial completion of the building as a whole. Citing § 15-3-630(b),[2] the court found that the windows “were ‘a specified area or portion’ of the larger condominium project” and, upon their incorporation into the larger project they could be used for the purpose for which they were intended. Thus, the court held that “the statute of repose began running when installation of the windows was complete.”
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and WilliamsMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Wilke Fleury Secures Bid Protest Denial
March 16, 2020 —
Wilke Fleury LLPAfter the City of Vacaville, following a sealed bid process, awarded a significant well drilling contract to Roadrunner Drilling & Pump Company, second-place bidder Nor-Cal Pump and Well Drilling filed a protest with the City on January 30, claiming that Roadrunner’s bid failed to meet certain requirements of the proposed contract. Roadrunner hired Wilke Fleury to defend the bid protest. After Wilke Fleury partner Dan Baxter transmitted a letter to the City explaining why the disgruntled bidder’s protest was factually and legally unsupported, the City—a mere nine days after receiving Dan’s letter—rejected the bid protest, and maintained its award of the project to Roadrunner as the lowest responsive and responsible bidder.
Wilke Fleury LLP
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
DoD Issues Guidance on Inflation Adjustments for Contractors
August 15, 2022 —
Jennifer Harris & Abby Salinas - ConsensusDocsThe Department of Defense (“DoD”) recently issued a memorandum to contracting officers (“COs”) guiding the use of economic price adjustment (“EPA”) clauses to address inflation-related cost increases. The memorandum, entitled Guidance on Inflation and Economic Price Adjustments, comes as the year-over-year inflation rate rose to 8.6% in May, and contractors with fixed-price contracts seek ways to recover their rising costs. EPA clauses allow the parties to mitigate cost risks that present themselves as a result of circumstances beyond the contractor’s control, e.g., inflation and supply chain price fluctuations. Generally, an EPA clause will dictate that the Government bear the cost risk up to a mutually agreed-upon ceiling. EPA clauses apply to the cost portion of a contract, but do not normally apply to the profit. DFARS PGI 216.203-4.
Memorandum: No CO Authority to Grant Contractual Relief Absent an EPA Clause
The memorandum states that absent an existing EPA clause, COs do not have the authority to provide contractual relief for unanticipated inflation under a firm-fixed-price contract.
Reprinted courtesy of
Jennifer Harris, Peckar & Abramson, P.C. (ConsensusDocs) and
Abby Salinas, Peckar & Abramson, P.C. (ConsensusDocs)
Ms. Harris may be contacted at jharris@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Client Alert: Stipulated Judgment For Full Amount Of Underlying Claim As Security For Compromise Settlement Void As Unenforceable Penalty
March 26, 2014 —
David W. Evans, Krsto Mijanovic, and Gregory M. Smith-Haight Brown & Bonesteel LLPIn Purcell v. Schweitzer (No. D063435 - filed February 24, 2014, certified for publication March 17, 2014), the Fourth District Court of Appeal upheld an order setting aside a stipulated default judgment for the full amount of plaintiff’s claim which had been agreed to by the parties to a settlement agreement, finding that it constituted an unenforceable penalty because the amount bore no reasonable relationship to the settling party’s actual damages resulting from a breach of the settlement agreement.
In an agreement settling a breach of contract action seeking $85,000 in damages based on an unpaid debt, the plaintiff agreed to settle the claim and to accept $38,000 in 24 monthly installments, including interest on the unpaid principal at 8.5 percent. The agreement provided that payments were due on the first day of each month and to be considered “timely,” had to be received by the fifth day of each month. If any payment was not made on time, it was to be considered a breach of the entire settlement agreement, making the entire $85,000 original liability due pursuant to a stipulation for entry of judgment for such amount. The stipulation included language to the effect that the $85,000 figure accounted for the “economics” of further proceedings. The agreement also specified that the foregoing provision did not constitute an unlawful “penalty” or “forfeiture” and that defendant waived any right to an appeal and any right to contest or seek to set aside such a judgment.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
David W. Evans,
Krsto Mijanovic, and
Gregory M. Smith
Mr. Evans may be contacted at devans@hbblaw.com; Mr. Mijanovic may be contacted at kmijanovic@hbblaw.com, and Mr. Smith may be contacted at gsmith@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Drafting or Negotiating A Subcontract–Questions To Consider
June 21, 2021 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to drafting and negotiating a subcontract, there are provisions that should be important to you from a risk assessment standpoint. From the subcontractor’s standpoint, below are questions you should ask, or issues you should consider, as you go through the subcontract. These are the same questions and issues that are also important to a contractor as the contractor will want to ensure these issues are included in the subcontract. By asking yourself these questions, you can check to see how the subcontract addresses these issues, and how the risk should be negotiated. Hopefully, you are working with counsel to make sure you understand what risk you are assuming and those provisions you want to try to push back on. Asking yourself these questions, or considering these questions, will help you go through the subcontract with a purpose based on the risk profile of the project and certain risk you don’t want to assume.
- Prime Contract –> Does the subcontract incorporate the prime contract? Make sure to request the prime contract since the subcontract will identify the prime contract as part of the Subcontract Documents and will require you to assume towards the contractor the same obligations the contractor is required to assume towards the owner.
- Scope of Work –> What is the scope of work? Is it clear. Make sure the scope is clear and you understand the scope.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
California Superior Court Overrules Insurer's Demurrer on COVID-19 Claim
February 15, 2021 —
Tred R. Eyerly - Insurance Law HawaiiA Superior Court in California overruled the insurer's demurrer to the policy holder's complaint seeking business interruption coverage after government shutdown orders were issued because of the coronavirus pandemic. Goodwill Industries of Orange County, California v. Philadelphia Indemnity Ins. Co., Cal. Superior Ct., Civil No. 30-2020-01169032-CU-IC-CXC (Minute Order Jan. 28,, 2021). The minute order is here [Goodwill Decision].
The insurer demurred on the ground that the insured had not alleged sufficient facts to show "direct physical loss" under the business income, extra expenses and civil authority provisions in the policy because coronavirus and COVID-19 did not physically alter the structure.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Power & Energy - Emerging Insurance Coverage Cases of Interest
November 30, 2020 —
David G. Jordan & Tiffany Casanova - Saxe Doernberger & Vita, P.C.The Power & Energy sector faces a multitude of risks that impact output and profitability, requiring sound risk management and robust insurance programs. As of recent, like most industries, there have been significant challenges facing the industry in light of COVID-19. These issues, including decreased product demand as well as supply- side issues, have been well documented. However, other issues continue to impact Power & Energy providers, with significant insurance coverage implications that are worthy of note. Below is a summary of three open cases of interest, where declaratory relief has been sought by energy providers’ insurance carriers, seeking an avoidance of coverage.
1. Fracking Dispute and “Intentional Acts”
In the Texas case of The James River Insurance Co. v. Clearpoint Chemicals LLC et al., No. 4:20-cv-0076 (N.D.Tex), James River Insurance Company (“James River”) is asking a federal district court to declare that it does not owe defense or indemnity to its insured for acts it defines as both intentional and/or malicious acts.
Reprinted courtesy of
David G. Jordan, Saxe Doernberger & Vita, P.C. and
Tiffany Casanova, Saxe Doernberger & Vita, P.C.
Mr. Jordan may be contacted at DJordan@sdvlaw.com
Ms. Casanova may be contacted at TCasanova@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of