Burden Supporting Termination for Default
January 11, 2021 —
David Adelstein - Florida Construction Legal UpdatesTerminating a contractor for default is a “‘drastic sanction’ and ‘should be imposed (or sustained) only for good grounds and on solid evidence.’” Cherokee General Corp. v. U.S., 150 Fed.Cl. 270, 278 (Fed.Cl. 2020) (citation omitted). This is true with any termination for default because terminating a contract for default is the harshest recourse that can be taken under a contract. It is a caused-based termination. For this reason, the party terminating a contract for default needs to be in a position to carry its burden supporting the evidentiary basis in exercising the default-based (or caused-based) termination. Stated differently, the party terminating a contract for default needs to justify the reasonableness in terminating the contract for default.
A party looking to terminate a contract for default should smartly work with counsel to best position its justification in exercising the termination for default. Likewise, a contractor terminated for default should immediately work with counsel to best position the unreasonableness or the lack of justification for the default-based termination.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction Contracts and The Uniform Commercial Code: When Does it Apply and Understanding the Pre-Dominant Factor Test
November 01, 2022 —
Keith Sparks - Ahlers Cressman & Sleight PLLCThe Uniform Commercial Code (“UCC”) replaces the common law in many commercial transactions, providing provisions and a framework governing the conduct of business. The UCC attempts to develop uniformity among state laws on commercial matters as many of these contracts involve parties from different states. The UCC has been adopted in almost all states, including Washington, and substantially mirror each other throughout the country.
The question that is most commonly presented, in the Construction law context, is when does the UCC apply and control?
Read the court decisionRead the full story...Reprinted courtesy of
Keith Sparks, Ahlers Cressman & Sleight PLLCMr. Sparks may be contacted at
keith.sparks@acslawyers.com
A Year-End Review of the Environmental Regulatory Landscape
January 11, 2022 —
Anne Idsal Austin & Joel Simon - Gravel2Gavel Construction & Real Estate Law BlogOur guest today is Anne Idsal Austin, a nationally recognized environmental lawyer who has held several high-profile federal and state regulatory roles. As a partner who recently joined Pillsbury’s environmental and natural resources practice, she provides strategic consulting and policy advice, helping clients navigate the dynamic regulatory and legal waters in an era of energy transition, decarbonization and an emphasis on ESG principles. Prior to joining Pillsbury, Anne was the Principal Deputy Assistant Administrator for the U.S. Environmental Protection Agency’s Office of Air and Radiation, known as OAR or OAR, where she had primary oversight over United States clean air policy and regulation. Prior to that, she served as the EPA regional administrator for Region 6, overseeing all federal environmental programs in Texas, Louisiana, New Mexico, Oklahoma and Arkansas. Prior to joining EPA, Anne held several positions where she shaped environmental and energy policy at the highest levels of government in the state of Texas. Welcome to our podcast, Anne.
Anne Austin: Thanks so much. It’s great to be here today, Joel.
Joel Simon: Anne, I’m really excited for this chance to speak with you because there’s so much going on at the federal environmental policy level, and it would be great to have someone really knowledgeable present this to us in an organized fashion. So with that minor task ahead of you, could you start us off with a brief overview of the environmental regulatory landscape?
Reprinted courtesy of
Anne Idsal Austin, Pillsbury and
Joel Simon, Pillsbury
Ms. Austin may be contacted at anne.austin@pillsburylaw.com
Mr. Simon may be contacted at joel.simon@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Savannah Homeowners Win Sizable Judgment in Mold Case against HVAC Contractor
August 10, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPTwo Savannah homeowners filed a complaint against a local air conditioning contractor and its insurer, asserting claims of professional negligence and fraud. The couple alleged that in March 2009, the contractor replaced the duct system of their home’s air conditioning unit. The following June, the couple discovered mold growth on the vent covers. They hired an independent contractor who upon inspection concluded that the duct system, which contained holes, gaps, loose connections and insufficient mastic, had been defectively installed in violation of the applicable city ordinances, resulting in excessive moisture and mold contamination throughout the residence. The homeowners alleged that they grew ill with respiratory problems as a result and were subsequently forced to vacate the residence and abandon their personal belongings. Their complaint sought to recover repair costs, moving costs, expenses associated with rental property, costs of living, costs related to the replacement of personal property, medical expenses, punitive damages, attorney’s fees, and costs of litigation.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Oregon Courthouse Reopening after Four Years Repairing Defects
April 01, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Courthouse Square in Marion County, Oregon is due to reopen after four years and nearly $23 million of repair costs to fix structural defects, according to the Statesman Journal. The square includes a courthouse building and bus mall, and is jointly owned by the county and transit district.
Two years after the Courthouse Square had been built, cracks were observed “in the building’s walls” and “paving stones on the bus mall shifted and settled.” A construction defect suit was filed in 2006.
However, the situation worsened in July of 2010 when “engineers determined that the entire complex was dangerous,” according to the Statesman Journal. “Building safety officials gave Courthouse Square’s occupants 60 days to move out, forcing county and transit district operations into temporary leased space.”
Now that the structural repairs have been completed, Dave Clark, project manager with Structural Preservation Systems LLC (the company awarded the repair contract), stated that the building’s structure is now stronger than most buildings. “If there’s an earthquake, come to this building,” Clark said.
Read the court decisionRead the full story...Reprinted courtesy of
NY Pay-to-Play Charges Dropped Against LPCiminelli Executive As Another Pleads Guilty
June 06, 2018 —
Mary B. Powers & Debra K. Rubin - Engineerings News-RecordThe former president of New York contractor LPCiminelli—the firm that has been at the center of an alleged pay-to-play scheme playing out since 2016 when he and two other executives were indicted—got a reprieve as federal prosecutors said they were dropping all charges against him, including wire fraud, conspiracy to commit wire fraud and making false statements to federal agents, according to a June 1 court filing.
Reprinted courtesy of
Mary B. Powers, ENR and
Debra K. Rubin, ENR
Ms. Rubin may be contacted at rubind@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
Depreciating Labor Costs May be Factor in Actual Cash Value
April 20, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Minnesota Supreme Court considered a certified question from the the U.S. District Court regarding consideration of depreciating labor costs in determining the actual cash value of a loss. Wilcox v. State Farm Fire & Cas. Co., 2016 Min. LEXIS 50 (Minn. Feb. 10, 2016).
The insureds' home was damaged by hail. State Farm provided a written estimate that calculated the actual cash value of the loss. To estimate the actual cash value of the damaged property, State Farm first calculated the replacement costs of individual items, such as roof flashing, siding, fascia, gutters, and window screens. Next, State Farm subtracted the pre-loss depreciation of some, but not all, individual items. For example, State Farm depreciated the cost of removing and replacing certain materials, such as siding. State Farm did not depreciate the cost of the new siding separately from the cost of the labor required to install the new siding on the home. Instead, State Farm calculated the removal and replacement of the siding as a single cost, then depreciated the removal-and-replacement cost as a whole. The cost of labor to repair or replace the damaged property was referred to by the court as "embedded labor costs."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Keeping KeyArena's Landmark Lid Overhead at Climate Pledge Arena Redevelopment Is A 22,000-Ton Balancing Act
November 30, 2020 —
Nadine M. Post - Engineering News-RecordMost contractors would jump at the chance to have a roof overhead during a major rebuild. But for the team turning earthquake-prone Seattle’s 411,000-sq-ft KeyArena into the 932,000-sq-ft Climate Pledge Arena, the city-owned facility’s historic helmet has been a 44-million-lb design and construction headache.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of