Five Issues to Consider in Government Contracting (Or Any Contracting!)
September 02, 2024 —
David Adelstein - Florida Construction Legal UpdatesThe appeal of Appeals of – Konecranes Nuclear Equipment & Services, LLC, ASBCA 62797, 2024 WL 2698011 (May 7, 2024) raises interesting, but important, issues that should be considered. In this case, the government (in a supply contract) procured four portal cranes from the claimant. After an initial test of one of the cranes failed, the government refused to accept delivery even after the issue was addressed by the claimant. The government did not accept the manner in which the claimant addressed the issue and would only accept cranes if the claimant employed “an unnecessary alternative solution [that] caused further delay and increased [claimant’s] costs.” On appeal, it was determined the government’s decision to delay delivery based on its demand for the alternative solution was not justified, i.e., constituted a breach of contract. Below are five issues of consideration in government contracting, or, for that matter, any contracting.
Issue #1- Patently Ambiguous Specifications
The government argued that the specifications were patently ambiguous and because the claimant failed to inquire regarding the ambiguous specifications prior to performance, its interpretation of the ambiguous specifications should govern. The contractor countered that the specifications were unambiguous and it met the specifications.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Contract Not So Clear in South Carolina Construction Defect Case
November 07, 2012 —
CDJ STAFFThe South Carolina Court of Appeals has reversed a partial summary judgment issued by one of the lower courts in the case of The Retreat at Edisto Co-Owners Association v. The Retreat at Edisto. The underlying issues of the case deal with a construction defect complaint.
The lower court had concluded “Developer’s ‘First Amendment’ to the Master Deed required the Developer to satisfy the provision in the paragraph labeled ‘Master Deed Amendment or Phase II’ as a condition precedent to its election to proceed with the development of Phase II.”
The appeals court found that “the language of the First Amendment to the Master Deed is susceptible to more than one interpretation.” The court additionally concluded that the “Developer presented the requisite scintilla of evidence on the question of its intent in order to establish a genuine issue of material fact. As the material facts were in dispute, the appeals court reversed the summary judgment and remanded the case to the circuit court for further proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
Congress Relaxes Several PPP Loan Requirements
June 15, 2020 —
Greg Tross & Michael Krueger – Newmeyer DillionOn June 3, 2020, Congress passed the Paycheck Protection Program Flexibility Act ("Act") which does exactly what it means to do: provide flexibility for PPP loan recipients. President Trump is expected to sign the bill into law within the week.
The Act extends the "covered period" for Paycheck Protection Program ("PPP") loans from the original eight weeks to 24 weeks or December 31, 2020, whichever is earlier. This extension provides much needed reprieve to small businesses who can utilize these funds to weather the economic effects of the Coronavirus Pandemic through 2020.
The Act also revises the limitations on how small businesses utilize their PPP loans. While the CARES Act originally required 75% of the PPP loan to be used for payroll costs, this number has now been reduced to 60%. This means that up to 40% of the PPP loan can be used to cover mortgage obligations, rent, and other covered utility payments.
The PPP loan payment deferral period has also been extended to align with the date on which the PPP loan's forgiveness amount is remitted to the lender. This should provide more certainty to small businesses on their payback obligations, if any.
Recently, the Small Business Administration also released loan forgiveness applications to assist a business in calculating their loan forgiveness. While the SBA will likely revise it with the Act's passing, small businesses should look at the application's framework to prepare for submitting their loan forgiveness requests in the future.
Newmeyer Dillion continues to follow COVID-19 and its impact on your business and our communities. Feel free to reach out to us at NDcovid19response@ndlf.com or visit us at www.newmeyerdillion.com/covid-19-multidisciplinary-task-force/.
Reprinted courtesy of
Greg Tross, Newmeyer Dillion and
Michael Krueger, Newmeyer Dillion
Mr. Tross may be contacted at greg.tross@ndlf.com
Mr. Krueger may be contacted at michael.krueger@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Court Holds That Trimming of Neighbor’s Trees is Not an Insured Accident or Occurrence
June 10, 2015 —
Christopher Kendrick and Valerie A. Moore – Haight Brown & Bonesteel LLPIn Albert v. Mid-Century Insurance Co. (No. B257792, filed 4/28/15, ord. pub. 5/20/15), a California Court of Appeal held that an insured’s trimming of a neighbor’s trees which allegedly damaged the trees was not an accident or occurrence covered by her homeowners insurance, despite a mistaken and good faith belief as to where the property line lay.
Ms. Albert was sued by her adjoining neighbor, who alleged damage to his property when she erected an encroaching fence and pruned nine mature olive trees on his property. The two parcels shared a reciprocal roadway easement providing for access to the main public road. At some point, Ms. Albert erected a fence that was subsequently determined to be on the neighbor’s land, and which enclosed a grove of nine mature olive trees. Ms. Albert claimed that the trees straddled the property line and were mutually owned. She pointed out that she had regularly been notified by the Los Angeles Fire Department to clear the area, and that she had been trimming the trees for years. Thus, she claimed a good faith belief that the trees were hers and that she was required to trim them.
Contending that her trimming had caused severe damage by reducing the aesthetic and monetary value of the trees, the neighbor sued alleging causes of action for trespass to real property and trees; abatement of private nuisance; declaratory relief; and for quiet title. He sought treble damages under Civil Code sections 733 and 3346, for injury to timber or trees.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com; Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Home Prices Climbed 0.1% in July as Gains Slowed
September 24, 2014 —
Prashant Gopal – BloombergU.S. home prices rose less than economists estimated in July as investors pull back from the property market.
Prices climbed 0.1 percent on a seasonally adjusted basis from June, the Federal Housing Finance Agency said today in a report from Washington. The average economist estimate was for a 0.5 percent increase, according to data compiled by Bloomberg.
Investors who helped drive up prices are retreating as fewer foreclosures and other discounted homes become available. All-cash purchases in August fell to about 23 percent of the market from the usual 33 percent, the National Association of Realtors reported yesterday. Investors accounted for 12 percent, the least since late 2009.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net
California Complex Civil Litigation Superior Court Panels
December 31, 2014 —
Richard H. Glucksman, Esq., Jon A. Turigliatto, Esq., and David A. Napper, Esq. – Chapman Glucksman Dean Roeb & Barger BulletinThe Complex Civil Litigation Program is relatively new as it has only existed in California
since 2000. Complex divisions dedicate courtrooms solely for litigation of complex civil
cases that require exceptional judicial management including construction defects, antitrust,
securities, toxic torts, mass torts, and class actions. Complex civil courtrooms help the trial
court operate in a more efficient, expeditious, and effective manner. A complex court
reduces costs for litigants by streamlining motion practice and expeditiously resolving
discovery disputes.
Not all counties have dedicated complex civil divisions. For those that do, each county has
its own local rules, and some complex divisions have their own particular set of rules. The
Judicial management of complex cases begins early, and is applied continuously and actively
with the idea that final resolution be expedited as much as possible. In focusing on
cooperation amongst the parties to achieve these goals, often requiring joint statements to
the court and a prohibition on discovery motions until after the parties have formally metand-
conferred on the issues. Moreover, complex cases are centralized and are assigned to
one highly skilled Judge for all purposes.
The first six California counties to create a Complex Civil division include Alameda, Contra
Costa, Los Angeles, Orange, San Francisco, and Santa Clara. Riverside County Superior
Court is the most recent California County to add a Complex division, effective January 2015.
Riverside county Superior Court’s Complex department consists of ten civil judges, seven of
which are in the main courthouse with Riverside. Riverside county expects to consolidate all
complex civil litigation into one courtroom by January 2015. Riverside county Judge Sharon
Waters state that "[i]t's been something that I personally have felt has been long overdue"
and that "[t]he idea is that put it with one judge and let him or her develop the expertise."
Judge Waters believes "[t]he potential value of establishing a complex litigation courtroom
[is that] it allows the judge to focus on the cases full time."1
As of October 2014, Riverside county had about 450 to 500 pending cases designated as
complex, over fifty percent (50%) of which involved construction defect matters. The sole
Judge who will preside over the complex cases has not yet been named.
1 Jolly, Vik. "Riverside to Shift Complex Civil Cases to 1 Courtroom." Los Angeles Daily Journal (October 13,
2014)
Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys
Richard H. Glucksman,
Jon A. Turigliatto and
David A. Napper
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com;
Mr. Turigliatto may be contacted at jturigliatto@cgdrblaw.com;
and Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Sometimes You Get Away with Unwritten Contracts. . .
January 20, 2020 —
Christopher G. Hill - Construction Law MusingsI have spoken often regarding the need for a well written construction contract that sets out the “terms of engagement” for your construction project. A written construction contract sets expectations and allows the parties to the contract to determine the “law” of their project. An unwritten “gentleman’s agreement” can lead to confusion, faulty memories, and more money paid to construction counsel than you would like as we lawyers play around in the grey areas.
One other area where the written versus unwritten distinction makes a difference is in the calculation of the statute of limitations. In Virginia, a 5 year statute of limitations applies to written contracts while a 3 year statute of limitations applies to unwritten contracts. This distinction came into stark relief in the case of M&C Hauling & Constr. Inc. v. Wilbur Hale in the Fairfax, Virginia Circuit Court. In M&C Hauling, M&C provided hauling services to the defendant through a subcontract with Hauling Unlimited in 2014, the last of which was in July. M&C provided over 2000 hours of hauling and provided time tickets (that were passed to Mr. Hale on Hauling Unlimited letterhead and signed by Mr. Hale or his agent) and an invoice stating the price term of $75.00 per hour. No separate written contract between M&C and Hauling Unlimited or Mr. Hale existed.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Additional Insured is Loss Payee after Hurricane Damage
October 01, 2024 —
Tred R. Eyerly - Insurance Law HawaiiConstruing the policy language, the federal district court found that the policy's additional insured was the loss payee for damage caused by Hurricanes Laura and Delta. TCP Ryan St. LLC v. Weschester Surplus Lines Ins. Co., 2024 U.S. Dist. LEXIS 125529 (W.D. La. July 16, 2024).
Hurricanes Laura and Delta caused damage to TCP Ryan Street, LLC's (TCP) property. Westchester had issued a policy to MRI Heritage Brand, Inc. (MRI). MRI, as lessee, was obligated pursuant to the lease terms to "purchase and maintain . . . a policy of fire, extended coverage, vandalism and malicious mischief (or 'all risk') insurance coverage on all real property situated at the Lease Premises." The lease also required MRI to obtain coverage under a policy naming only the landlord as the sole insured and provided that the proceeds would be payable to the landlord.
The policy provided that no entity was covered unless Westchester had received identifying information for the entity during the application process or the entity was added by endorsement.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com