Court Upholds Plan to Eliminate Vehicles from Balboa Park Complex
June 10, 2015 —
Kristen Lee Price and Lawrence S. Zucker II – Haight Brown & Bonesteel LLPIn Save Our Heritage Organisation v. City of San Diego, et al. (No. D063992, filed 5/28/15), the California Court of Appeal for the Fourth Appellate District upheld a controversial plan to eliminate vehicles from various plazas in historic Balboa Park. In reaching its decision, the Court of Appeal considered a question of first impression involving the interpretation of San Diego Municipal Code section 126.0504.
Balboa Park, designated a National Historic Landmark in 1940, is a large urban park in the center of San Diego. The City of San Diego (“City”) recently approved a proposed plan (“Project”) to eliminate vehicles from the plazas within the Balboa Park complex and to return the plazas to purely pedestrian zones. Subsequently, a community group named Save Our Heritage Organisation (“SOHO”) filed a petition for a writ of mandate alleging, among other things, the City erroneously approved the Project. SOHO contended Municipal Code section 126.0504 mandated two key findings be made before the Project could be approved: (1) that the intended purpose of the property would not be adversely affected; and (2) without the proposed project, the property would not be put to a “reasonable beneficial use.” SOHO argued that although the City made the requisite findings, those findings lacked substantial evidentiary support. The trial court agreed with SOHO and directed the City to rescind the site development permit.
The City argued on appeal that Municipal Code section 126.0504 vested it with “discretion to make a qualitative determination of whether an existing use of the property, even if deemed beneficial, is also a reasonable use of that property under all of the facts and circumstances applicable to the particular property in question.” The Court of Appeal agreed and reversed.
Reprinted courtesy of
Kristen Lee Price, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Ms. Price may be contacted at kprice@hbblaw.com; Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Illinois Attorney General Warns of Home Repair Scams
November 27, 2013 —
CDJ STAFFAfter storms damaged homes in Illinois, Lisa Madigan, the state’s Attorney General, warned consumers “to be cautious and on alert for scammers trying to take advantage of people in need of assistance.” Ms. Madigan noted that home repair scammers go into areas with storm damage convince homeowners to pay more than they should to repair storm damage.
Read the court decisionRead the full story...Reprinted courtesy of
Where-Forum Art Thou? Is the Chosen Forum Akin to No Forum at All?
May 30, 2022 —
William Doerler - The Subrogation StrategistMany courts enforce forum selection clauses in contracts between parties. In W. Bay Plaza Condo. Ass’n v. Sika Corp., No. 3D21-1834, 2022 Fla. App. LEXIS 1637 (W. Bay Plaza), the Court of Appeal of Florida, Third District (Court of Appeal) answered the question of whether a mandatory forum selection clause in a manufacturer’s warranty was enforceable as to a condominium association, who was a non-signatory. The trial court enforced the forum selection clause – calling for litigation in New Jersey rather than Florida – and the Court of Appeal affirmed the ruling.
As stated in W. Bay Plaza, in late 2013 and early 2014, West Bay Plaza Condominium Association (W.B. Plaza Condo. Ass’n) contracted with Built Right Installers International Corporation, R.J. Miranda Consultants, Inc. and UCI Engineering Inc. (collectively, the Construction Defendants) to have repairs done to the exterior of the property. In 2016, Sika Corporation (Sika), a New Jersey corporation, gave a five-year warranty to W.B. Plaza Condo. Ass’n for three sealant products used to repair the garage at the property. In 2019, W.B. Plaza Condo. Ass’n sued the Construction Defendants for breach of contract and professional negligence. Subsequently, W.B. Plaza Condo. Ass’n amended its complaint and filed a claim against Sika, alleging that Sika breached its warranty because its products failed to provide a watertight barrier. Sika filed a motion to dismiss the action, alleging that Florida was an improper venue because its’ warranty contained a mandatory forum selection clause. W.B. Plaza Condo. Ass’n argued that it was not bound by the forum selection clause because it was a non-signatory to the warranty and, even if it was bound by the clause, there were compelling reasons not to enforce it.
Read the court decisionRead the full story...Reprinted courtesy of
William Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
A Court-Side Seat: NWP 12 and the Dakota Access Pipeline Easement Get Forced Vacations, while a Potential Violation of the Eighth Amendment Isn’t Going Anywhere
August 10, 2020 —
Anthony B. Cavender - Gravel2GavelHere’s a report on several new decisions made over the past few days.
U.S. SUPREME COURT
U.S. Army Corps of Engineers v. Northern Plains Resources Council
On July 8, 2020, the Court has issued a partial stay of the decision of the U.S. District Court for Montana, which had held that the nationwide use by the Corps of Engineers of its Nationwide Permit 12 to permit oil and gas pipelines must be vacated because the Corps, when it reissued these permits in 2012, failed to follow the requirements of the Endangered Species Act. The breadth of this ruling seems to have surprised and alarmed many past and perspective permittees of the Corps. The stay will not apply to the ongoing Ninth Circuit litigation.
FEDERAL COURTS OF APPEAL
Vega, et al. v. Semple (The U.S. Court of Appeals for the Second Circuit)
On June 29, 2020, the court refused to dismiss a putative class action by past and present inmates of Connecticut’s Garner Correctional Institution who alleged that state correctional officials exposed them to excessive amounts of radon gas in violation of the Eighth Amendment. These officials are alleged to have been “deliberately indifferent” to inmate safety. A 1993 Supreme Court decision, Helling v. McKiney, clearly established the law in this area, and the Garner facility opened in 1992. The defense clams of limited immunity as to federal law violations were rejected.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Georgia Supreme Court Addresses Anti-Indemnity Statute
October 21, 2019 —
David R. Cook - AHC Construction and Procurement BlogIn prior blog posts, we addressed Georgia’s anti-indemnity statute. One of the posts addressed the statute in the context of an electric utility easement near an airport. That case made its way to the Supreme Court Georgia, which provided some additional clarity to the statute. Milliken & Co. v. Georgia Power Co., — Ga. –, 829 S.E.2d 111 (2019).
When a plane crashed and several passengers and crew died or were injured, their representatives sued several defendants, including a nearby plant owner, Milliken & Company (“Milliken”), based on claims that transmission lines on Milliken’s property were too close to the runways, were too high, and encroached on the airport easements. Milliken cross claimed against Georgia Power Company (“GPC”). Milliken’s claim was based on an easement it granted to GPC, which required GPC to indemnify it for any claims arising out of GPC’s construction or maintenance of the transmission lines.
On appeal, the Supreme Court considered whether the clause was unenforceable under O.C.G.A. § 13-8-2(b). In general, “a party may contract away liability to the other party for the consequences of his own negligence without contravening public policy, except when such agreement it prohibited by statute.” Id. at 113 citing Lanier at McEver v. Planners & Eng’rs Collaborative, 284 Ga. 204, 205 (2008). As one such statute, O.C.G.A. § 13-8-2(b) applies when an indemnification provision (i) “relates in some way to a contract for construction, alteration, repair, or maintenance of certain property” and (ii) “promises to indemnify a party for damages arising from that own party’s sole negligence.” Id. at 114 (internal punctuation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Winners Announced in Seattle’s Office-to-Residential Call for Ideas Contest
July 10, 2023 —
Ryanne Mathisen - Ahlers Cressman & Sleight PLLCOn June 7, 2023, the City of Seattle announced three winners of its Office to Residential: Call for Ideas contest for which it received a total of 13 submissions. Hybrid Architecture, LLC, took first place; Gensler, Seattle Office Project Team took second; and the Miller Hull Partnership took third. Seattle’s Department of Construction and Inspections will study the submissions and determine what legislative and regulatory modifications would be necessary to support and further these proposals and other future office-to-residential conversion projects.
Seattle will also be holding a series of exhibitions over the coming weeks where project submissions will be available to the public. On June 14, 2023, from 5:30 PM to 7:30 PM, a reception will be hosted by the Seattle Architecture Foundation and the City at the American Institute of Architects. The gallery will also be open to the public from 10:00 AM to 5:00 PM on June 21, 28, and July 5. After June 14, 2023, those interested can access contest submissions at the
project website.
Seattle’s primary goal with this contest was to provide a vision for the future of downtown and begin charting a concrete path to getting there. Since working from home has become more common following the COVID-19 pandemic, vacancy rates in many office buildings have risen sharply, while housing availability and affordability remain ongoing issues. If Seattle can show a realistic—and profitable—path to converting commercial office spaces into residences, it would be addressing both problems, killing two birds with one stone.
Read the court decisionRead the full story...Reprinted courtesy of
Ryanne Mathisen, Ahlers Cressman & Sleight PLLCMs. Mathisen may be contacted at
ryanne.mathisen@acslawyers.com
No Damage for Delay? No Problem: Exceptions to the Enforceability of No Damage for Delay Clauses
October 18, 2021 —
Chris Broughton, Jones Walker LLP - ConsensusDocsIntroduction:
Under a no-damage-for-delay clause, the owner is not liable for any monetary damages resulting from delays on the project. In lieu of monetary recovery, the contractor’s remaining remedy is a non-compensatory time extension. These clauses are common at the contractor-subcontractor interface as well.
While no-damage-for-delay clauses are enforced in most jurisdictions, some states, either by statute or case law, have limited the enforceability of no-damage-for-delay clauses. Other states have also limited the enforceability of these clauses on state government contracts, and a select few have outlawed them on all projects regardless if they are publicly or privately owned. Additionally, for subcontractors on federal projects, the Miller Act may provide a way to avoid no-damage-for-delay and recover against the general contractor’s payment bond.
This article provides an overview of no-damage-for-delay clauses and the exceptions to enforcement of these clauses. However, due to the consequences of a no-damage-for-delay clause, it is important to know the terms of your contract and the law that governs your project.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Broughton, Jones Walker LLPMr. Broughton may be contacted at
cbroughton@joneswalker.com
Private Statutory Cause of Action Under Florida’s Underground Facility Damage Prevention and Safety Act
July 11, 2021 —
David Adelstein - Florida Construction Legal UpdatesFlorida’s Underground Facility Damage Prevention and Safety Act is set forth in Florida Statutes Chapter 556. Any owner or operator of underground infrastructure as well as contractors that perform underground excavation and demolition operations are familiar (or, need to be familiar) with this Act and the requirements it imposes on them.
In a nutshell, this Act requires excavators to notify operators of underground facilities (e.g., pipelines, cables, sewers) through a notification system before excavating or demolishing an underground location. Then notification system gives the operator of the underground facility two days’ advance notice that an excavation will be taking place. After receiving this notice, the operator of the underground facility must mark the area where its infrastructure is located which could be affected by the underground excavation or demolition operations. The Act further imposes duties on excavators to use increased caution, supervise mechanized equipment, perform excavation and demolition operations in a careful an prudent manner, and to re-notify the notification system if the operator’s marking is no longer visible so the location of the operator’s underground facility can be re-marked.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com