History of Defects Leads to Punitive Damages for Bankrupt Developer
March 01, 2012 —
CDJ STAFFThe South Carolina Court of Appeals has ruled that evidence of construction defects at a developer’s other projects were admissible in a construction defect lawsuit. They issued their ruling on Magnolia North Property Owners’ Association v. Heritage Communities, Inc. on February 15, 2012.
Magnolia North is a condominium complex in South Carolina. The initial builder, Heritage Communities, had not completed construction when they filed for bankruptcy protection under Chapter 11. The remaining four buildings were completed by another contractor. The Property Owners’ Association subsequently sued Heritage Communities, Inc. (HCI) alleging defects. The POA also sued Heritage Magnolia North, and the general contractor, BuildStar.
The trial court ruled that all three entities were in fact one. On appeal, the defendants claimed that the trial court improperly amalgamated the defendants. The appeals court noted, however, that “all these corporations share officers, directors, office space, and a phone number with HCI.” Until Heritage Communities turned over control of the POA to the actual homeowners, all of the POA’s officers were officers of HCI. The appeals court concluded that “the trial court’s ruling that Appellants’ entities were amalgamated is supported by the law and the evidence.”
Heritage also claimed that the trial court should not have allowed the plaintiffs to produce evidence of construction defects at other Heritage properties. Heritage argued that the evidence was a violation of the South Carolina Rules of Evidence. The court cited a South Carolina Supreme Court case which made an exception for “facts showing the other acts were substantially similar to the event at issue.” The court noted that the defects introduced by the plaintiffs were “virtually identical across all developments.” This included identical use of the same products from project to project. Further, these were used to demonstrate that “HCI was aware of water issues in the other projects as early as 1998, before construction on Magnolia North had begun.”
The trial case ended with a directed verdict. Heritage charged that the jury should have determined whether the alleged defects existed. The appeals court noted that there was “overwhelming evidence” that Heritage failed “to meet the industry standard of care.” Heritage did not dispute the existence of the damages during the trial, they “merely contested the extent.”
Further, Heritage claimed in its appeal that the case should have been rejected due to the three-year statute of limitations. They note that the first meeting of the POA was on March 8, 2000, yet the suit was not filed until May 28, 2003, just over three years. The court noted that here the statute of limitation must be tolled, as Heritage controlled the POA until September 9, 2002. The owner-controlled POA filed suit “approximately eight months after assuming control.”
The court also applied equitable estoppel to the statute of limitations. During the time in which Heritage controlled the board, Heritage “assured the unit owners the construction defects would be repaired, and, as a result, the owners were justified in relying on those assurances.” Since “a reasonable owner could have believed that it would be counter-productive to file suit,” the court found that also prevented Heritage from invoking the statute of limitations. In the end, the appeals court concluded that the even apart from equitable tolling and equitable estoppel, the statute of limitations could not have started until the unit owners took control of the board in September, 2002.
Heritage also contested the jury’s awarding of damages, asserting that “the POA failed to establish its damages as to any of its claims.” Noting that damages are determined “with reasonable certainty or accuracy,” and that “proof with mathematical certainty of the amount of loss or damage is not required,” the appeals court found a “sufficiently reasonable basis of computation of damages to support the trial court’s submission of damages to the jury.” Heritage also claimed that the POA did not show that the damage existed at the time of the transfer of control. The court rejected this claim as well.
Finally, Heritage argued that punitive damages were improperly applied for two reasons: that “the award of punitive damages has no deterrent effect because Appellants went out of business prior to the commencement of the litigation” and that Heritages has “no ability to pay punitive damages.” The punitive damages were upheld, as the relevant earlier decision includes “defendant’s degree of culpability,” “defendants awareness or concealment,” “existence of similar past conduct,” and “likelihood of deterring the defendant or others from similar conduct.”
The appeals court rejected all of the claims made by Heritage, fully upholding the decision of the trial court.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Impact of Lis Pendens on Unrecorded Interests / Liens
September 15, 2016 —
David Adelstein – Florida Construction Legal UpdatesIn a previous article, I discussed the importance of recording a lis pendens in a construction lien foreclosure action.
There is another noteworthy point relating to the impact of lis pendens that can provide quite a bit of consternation.
Florida Statute 48.23(1)(d) provides:
Except for the interest of persons in possession or easements of use, the recording of such notice of lis pendens, provided that during the pendency of the proceeding it has not expired pursuant to subsection (2) or been withdrawn or discharged, constitutes a bar to the enforcement against the property described in the notice of all interests and liens, including, but not limited to, federal tax liens and levies, unrecorded at the time of recording the notice unless the holder of any such unrecorded interest or lien intervenes in such proceedings within 30 days after the recording of the notice. If the holder of any such unrecorded interest or lien does not intervene in the proceedings and if such proceedings are prosecuted to a judicial sale of the property described in the notice, the property shall be forever discharged from all such unrecorded interests and liens. If the notice of lis pendens expires or is withdrawn or discharged, the expiration, withdrawal, or discharge of the notice does not affect the validity of any unrecorded interest or lien.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Illinois Legislature Passes Bill Allowing Punitive Damages In Most Wrongful Death Actions
June 05, 2023 —
John Hackett & Jarred Reed - Lewis BrisboisMadison County, Ill. (May 19, 2023) – On May 18, 2023, the Illinois legislature passed House Bill 0219, amending the Illinois Wrongful Death Act to allow for the recovery of punitive damages in wrongful death actions. The bill will soon be sent to the Governor’s desk for signature. If signed into law, the statutory change will allow heirs of decedents to recover punitive damages in wrongful death actions.
The proposed amendment to the Illinois Wrongful Death Act is underlined below:
Whenever the death of a person shall be caused by wrongful act, neglect or default, and the act, neglect or default is such as would, if death had not ensued, have entitled the party injured to maintain an action and recover damages including punitive damages when applicable, in respect thereof, then and in every such case the person who or company or corporation which would have been liable if death had not ensued, shall be liable to an action for damages, including punitive damages when applicable, notwithstanding the death of the person injured, and although the death shall have been caused under such circumstances as amount in law to felony. Nothing in this Section affects the applicability of Section 2-1115 of the Code of Civil Procedure or Section 2-102 or 2-213 of the Local Governmental and Governmental Employees Tort Immunity Act. Punitive damages are not available in action for healing art malpractice or legal practice or in an action against the State or unit of local government or an employee of a unit of local government in his or her official capacity. The changes made to this Section by this amendatory Act of the 103rd general Assembly apply to actions filed on or after the effective date of this amendatory Act.
Reprinted courtesy of
John Hackett, Lewis Brisbois and
Jarred Reed, Lewis Brisbois
Mr. Hackett may be contacted at John.Hackett@lewisbrisbois.com
Mr. Reed may be contacted at Jarred.Reed@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Contrasting Expert Opinions Result in Denial of Cross Motions for Summary Judgment
February 27, 2023 —
Tred R. Eyerly - Insurance Law HawaiiGiven the opposing experts' contradictory reports, the court denied both the insured and insurer's motions for summary judgment regarding coverage for a pipe leak. Pronti v. Hanover Ins. Co., 2022 U.S. Dist. LEXIS 222306 (W.D. N. Y. Dec. 9, 2022).
The insured had a swimming poll and spa, which functioned using a subsurface plumbing system, covered with concrete decking. A subsurface pipe began to leak, preventing the pool from properly functioning. The insureds gave notice under their homeowners' policy and contended that significant portions of the pool, spa, concrete decking and other landscaping had to be torn out to do repairs. The insurer retained an expert, Sarah G. Byer, a structural engineer, to investigate. The parties agreed that the pipe had a leak, but disputed if the location of the leak was specifically identified.
The parties also disputed the cause of the leak. Byer found that the most likely cause was deterioration incurred over the pipe's lifetime based on the age of the plumbing system and Byer's personal observation of the pipe. Byer further stated that the physical qualities of flexible PVC piping made it susceptible to damage from chlorine and water over time.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
“Unwinnable”: Newark Trial Team Obtains Unanimous “No Cause” Verdict in Challenging Matter on Behalf of NYC Mutual Housing Association
May 15, 2023 —
Lewis BrisboisNewark, N.J. (May 8, 2023) – Newark Partner Afsha Noran and New Jersey Managing Partner Colin P. Hackett recently obtained a “no cause” verdict on behalf of multi-unit apartment owners and managers, notwithstanding that the trial judge initially deemed the matter an “unwinnable case” for the defense.
In this matter, Lewis Brisbois represented a large New York City mutual housing association that owned and managed a single multi-unit apartment building in Paterson, New Jersey. The plaintiffs – a mother and her two children – alleged that the housing association failed to maintain the property, which led to defective conditions and mold throughout their apartment. They further contended that the mold caused multiple pulmonary, nasal, and skin injuries. Despite
the shortage of trial judges in New Jersey, this case proceeded to trial, with the plaintiffs’ significant six-figure demand in place.
Over the course of the four-day trial, the plaintiffs presented five witnesses: the plaintiff mother, the plaintiff 18-year-old child, the liability expert, and two medical experts. The client chose not to retain either liability or damages experts to counter those of the plaintiffs. As such, Lewis Brisbois’ trial team was left to defend the matter with an opening statement, a cross-examination of the plaintiffs and their experts, the testimony of the client’s property manager, and a closing argument.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
No Coverage for Property Damage That is Limited to Work Completed by Subcontractor
April 25, 2012 —
Tred R. Eyerly - Insurance Law HawaiiThe issue before the 11th Circuit was whether, under Florida law, a general contractor had coverage for a property damage claim limited to the defective work performed by a subcontractor, and not affecting any other portion of the project. The court found no coverage in Amerisure Mut. Ins. Co. v. Auchter Co., 2012 U.S. App. LEXIS 5412 (11th Cir. March 15, 2012).
Amelia Island Company contracted with Auchter Company, a general contractor, for construction of an inn and conference room. Auchter subcontracted with Register Contracting Company to install the Inn’s roof. Pursuant to the Florida Building Code, installation of the roof required that it be able to withstand 110 m.p.h. winds.
Register completed installing the roof tiles in January 1998. Beginning in 2002, the tiles began dislodging from the roof. During the 2004 hurricane season, three hurricanes caused more tiles to come off the roof. Some of these tiles hit other tiles, cracking them.
In 2006, the parties went to arbitration over the costs of repairs for the roof.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
KONE is Shaking Up the Industry with BIM
January 20, 2020 —
Aarni Heiskanen - AEC BusinessKONE supplies elevators, escalators, autowalks and maintenance and modernization solutions. I sat down with Kenneth Flannigan to discuss how BIM is changing KONE and what it means to the industry.
KONE operates in over 60 countries, has around 1.3 million units in service, and moves over one billion people per day. The company’s mission is “to improve the flow of urban life.” Kenneth Flannigan is the BIM Solution Owner for the company. He acknowledges that even though KONE provides equipment and software innovation, in this day and age that’s not enough.
“We’re a critical path item. How innovative are we if we’re not working on every single project in a shared 3D environment, like our customers?” Flannigan asks.
KONE serves both indirect and paying customers. It works with influencers like architects and with general contractors, builders, and construction managers. It also has a life-cycle relationship with building owners, which is evidenced by the fact that over 30% of the company’s sales come from maintenance.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
AI Systems and the Real Estate Industry
April 03, 2023 —
Robert G. Howard & Craig A. de Ridder - Gravel2Gavel Construction & Real Estate Law BlogArtificial intelligence (AI) systems captured considerable attention with the release of a large language chatbot, ChatGPT, by OpenAI, in November of last year. On March 14, OpenAI unveiled GPT-4, a more powerful “multimodal” chatbot responding to both text and images. And, on March 21, Google launched its conversational computer program, Bard, to compete with GPT-4. These chatbots allow users to initiate detailed queries or requests and receive prompt responses in complete sentences. Users are not forced to scroll through a list of results like those produced by search engines and follow-up questions can be asked.
AI systems have been touted for many years and these new breakthroughs may drastically change the way that we create content.
Notwithstanding their unprecedented capabilities, AI systems can produce imperfect results. New chatbots, for example, can generate plausible-sounding but nonsensical, biased or false responses. Accordingly, heavy fact-checking is necessary. OpenAI has warned that ChatGPT is prone to filling in replies with incorrect data if there is not enough information available on the topic on the internet. Bard includes a website disclaimer that it “may display inaccurate or offensive information that doesn’t represent Google’s views.” On March 20, a breach at OpenAI allowed users to see other people’s chat histories before the service was shut down. Further, there is a real risk that courts will rule that certain content generated by these systems infringes the copyright or database rights of the owner of the materials and data that the technologies relied on. When entering into agreements with AI software providers, companies should also be concerned about
other risks, including misappropriation of data, security, confidentiality, privacy and third-party claims.
Reprinted courtesy of
Robert G. Howard, Pillsbury and
Craig A. de Ridder, Pillsbury
Mr. Howard may be contacted at robert.howard@pillsburylaw.com
Mr. de Ridder may be contacted at craig.deridder@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of