Owner Can’t Pursue Statutory Show Cause Complaint to Cancel Lien… Fair Outcome?
June 10, 2024 —
David Adelstein - Florida Construction Legal UpdatesIf there is a payment dispute with a construction
lienor — could be a contractor, a subcontractor, or supplier – it is possible, and more than likely, a construction lien may get recorded against real property. This scenario is not uncommon as the lien is the mechanism for the lienor to collateralize their claimed nonpayment. Now, in reality, it does not take much money to record a lien. A lienor should utilize a lawyer to prepare their liens, but maybe they prepare liens in-house. Regardless, the recording of the lien is a nominal cost and the clerk that dockets and records the lien does NOT analyze the merits of the lien. That is not what the clerk is there to do; nor do you really want them the delve into the factual merits.
Well, what if a lien is facially invalid, meaning that the lien, on its face, includes information that demonstrates it is NOT properly perfected. Or what if the lienor failed to properly preserve or perfect its lien rights before recording the lien. This happens! Naturally, an owner of the real property wants the lien removed from the property. The owner does not want the encumbrance.
The owner could transfer the lien to a lien transfer bond under Florida’s Lien Law, but that is easier said than done. And this does not discharge the lien; it just removes the lien from the property to the security of the bond.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Hotel Owner Makes Construction Defect Claim
January 28, 2013 —
CDJ STAFFA lawsuit has been filed over the construction of the GrandStay Hotel & Conference Center in Apple Valley Minnesota. Apple Valley GSRS, LLC, who invested in the hotel, has sued Cole Group Architects and Cornerstone Construction, alleging that the architects design was not to industry standards and that the builder used inferior materials and techniques. The lawsuit makes claim of "significant damage."
The hotel hired an engineer who subsequently recommended that all the stucco and the roof should be be replaced. The stucco has shown signs of cracking and crumbling. The hotel states that the roof has problems with leaking.
Cornerstone has denied the hotel's claims. They have also counter-sued their subcontractors.
Read the court decisionRead the full story...Reprinted courtesy of
Illinois Appellate Court Finds That Damages in Excess of Policy Limits Do Not Trigger Right to Independent Counsel
June 22, 2020 —
Jason Taylor - Traub LiebermanUnder Illinois law, an insurer’s duty to defend includes the right to control the defense, which allows insurers to protect their financial interest in the outcome of the litigation. However, where a conflict of interest exists, the insured, rather than the insurer, is entitled to assume control of the defense of the underlying action. If this occurs, the insurer satisfies its obligation to defend by reimbursing the insured for the cost of defense provided by independent counsel selected by the insured. What circumstances and situations arise to the level of an actual conflict of interest between the insurer and insured are often grounds for dispute.
In Joseph T. Ryerson & Son, Inc. v. Travelers Indemnity Co. of America, 2020 IL App (1st) 182491 (Apr. 7, 2020), the Illinois Appellate Court addressed whether damages awarded by a jury in excess of the policy limits were sufficient to trigger a right to independent counsel for post-trial and appellate proceedings. According to the Illinois Appellate Court, at least under the facts of the Ryerson case, the answer is “no.”
In Ryerson, Nancy Hoffman sued Ryerson for injuries sustained in a tractor-trailer accident. Ryerson tendered the suit to its primary insurer, Travelers, and its umbrella insurer, Illinois National. The policy limits were $2 million and $25 million, respectively. A jury found in favor of Hoffman for over $27.6 million in damages, and Ryerson appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
U.S. Supreme Court Allows Climate Change Lawsuits to Proceed in State Court
May 01, 2023 —
George Leahy - Lewis BrisboisWashington, D.C. (April 25, 2023) - On Monday, April 24, the U.S. Supreme Court refused to hear appeals by several major energy companies that sought to remove lawsuits filed by state and local governments from state court into federal court. The Court’s
certiorari denials reject companies’ appeals in five separate cases, which involved claims brought by municipalities in Colorado, Maryland, California, Hawaii, and Rhode Island. Each municipality claims that it has been harmed by the effects of climate change, allegedly attributed to the companies’ carbon emissions.
The Court’s denials effectively allow the lawsuits to continue in state court, often seen as favorable for plaintiffs due to a greater potential for jury trials and associated damages awards than might be available in federal court. Following a
2021 Supreme Court ruling in a related case that granted the companies an additional chance to argue that their cases should be heard in federal court, the lower federal appeals courts in each of the five cases concluded that the companies had not established sufficient grounds to establish proper venue and jurisdiction in federal court. The Supreme Court’s April 24 denial leaves those decisions unaltered, allowing the lawsuits to continue in state court for further consideration.
Read the court decisionRead the full story...Reprinted courtesy of
George Leahy, Lewis Brisbois
Keller Group Fires Two Executives in Suspected Australia Profits Reporting Fraud
February 20, 2023 —
James Leggate - Engineering News-RecordLondon-based geotechnical contracting giant Keller Group's profits from its Australia business unit may have been fraudulently inflated by the U.S. equivalent of as much as $20 million in today’s dollars since 2019, the company has revealed.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Heads I Win, Tails You Lose. Court Finds Indemnity Provision Went Too Far
May 25, 2020 —
Garret Murai - California Construction Law BlogWe all love David and Goliath stories. The underdog winning against the far stronger (and dastardly) opponent. Think Rocky Balboa versus Ivan Drago, the Star Wars Rebellion versus the Galatic Empire, Indiana Jones versus a good chunk of the Third Reich. And now, we have Margaret Williams.
The Story of Margaret Williams and her LLC
The story, told in Long Beach Unified School District v. Margaret Williams, LLC, Case No. B290069 (December 9, 2019), is about Margaret Williams. Ms. Williams (we’ll just call her “Margaret” going forward because it just sounds better when telling a story) worked for nearly ten years full-time for the Long Beach Unified School District, toiling day in and day out doing construction management and environmental compliance work, including work involving the clean up of material at a school construction site contaminated with arsenic.
Although she worked full-time for the District for nearly ten years, she wasn’t an employee. Rather, she was a contractor. And, on top of it all, as a condition of working for the District, the District required that she form a company in order to contract with the District. According to Margaret, “In order to work with the District, I was directed . . . to form a corporation or partnership. This was the only way I could work for the District: I could not enter into a contract with the District as an individual.” So, in 2006, she formed a company, simply called Margaret Williams, LLC.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Construction Defect Specialist Joins Kansas City Firm
January 13, 2014 —
CDJ STAFFDavid Schatz, whose practice specializes in construction disputes and defects, has joined the Kansas City, Missouri firm Spencer Fane Britt & Brown LLP in their litigation practice group. Mr. Schatz’s expertise also includes banking and finance, banking litigation, commercial disputes, insurance, surety, employment, contract claims, and personal injury.
Pat Whalen, Chairman of Spencer Fane Britt & Brown, said that Schatz “brings great experience across a range of industries, but many of us in Kansas City are particularly pleased by his construction and general litigation credentials, which will fit will with the resources we’re building in those areas.”
Read the court decisionRead the full story...Reprinted courtesy of
Court Calls Lease-Leaseback Project What it is: A Design-Bid-Build Project
August 19, 2015 —
Garret Murai – California Construction Law BlogFirst there was “Prince.”
Then there was “The Artist Formerly Known as Prince.”
Then there was “The Artist Formerly Known as Prince (Because he Changed His Name to a Symbol), But Then Realized That No One Could Pronounce the Symbol (and What Good is a Symbol if Everyone Has to Wave Their Hands Wildly at You to Get Your Attention or Scream ‘Hey You!’), and So Changed His Name Back to Prince Again.”
Whatever name (or symbol) he was going by, everyone knew him as the guy who told us to party like it was 1999 (when 1999 still seemed like the distant future), who sang about a girl with a “pocket full of horses” (which totally flew past my junior high school brain at the time), and gave us such great metaphors as “if the elevator tries to bring you down, go crazy, punch a higher floor!”
Like Prince or his symbol, sometimes it doesn’t matter what label you put on something when everyone knows what that something is. In law, we call it looking at the “substance” rather than its “form.” And, in the next case, Davis v. Fresno Unified School District, the California Court of Appeals for the Fifth District made quick work of a purported “lease-leaseback” project – a project delivery method available to school districts whereby a school district leases property it owns to a developer for a minimum of $1, who in turns builds a school facility on the site and leases the facility and the site back to the school district, who in turn takes ownership of the facility and site at the end of the lease – and called it for what it was: a run-of-the-mill “design-bid-build” project.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at