Richard W. Brown & Sarah J. Markham - Saxe Doernberger & Vita, P.C.The December 2021 First Department decision in Nouveau Elevator Indus. v. New York Marine & General Ins. Co. is pushing some buttons in the elevator industry, given the significant implications it may have on the adequacy of policy limits for elevator service companies operating in New York state.
The Court held in Nouveau that monthly elevator maintenance work performed under an ongoing service agreement is considered “completed operations” for purposes of applying policy limits. Specifically, the Court found that the per location policy limits are not implicated here, and instead held that the products-completed operations aggregate limit applies to completed work, which expressly includes “that part of the work done at a job site [that] has been put to its intended use.”
Facts of the Case
Nouveau provides elevator maintenance and service in the greater New York city region. Its work is done in multiple buildings and locations throughout the city. Nouveau purchased six commercial general liability (CGL) policies from New York Marine for consecutive one-year periods. Each of the CGL policies provides a liability limit of $1 million, with an aggregate limit of $2 million, per accident or occurrence.
Reprinted courtesy of
Richard W. Brown, Saxe Doernberger & Vita, P.C. and
Sarah J. Markham, Saxe Doernberger & Vita, P.C.
Mr. Brown may be contacted at RBrown@sdvlaw.com
Ms. Markham may be contacted at SMarkham@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Few Homes Available to Reno Buyers, Plenty of Commercial Properties
January 22, 2013 —
CDJ STAFFSaying that "new home inventory does not exist," Mark Krueger of ArchCrest Commercial Partners tells the Reno Gazette Journal that this had lead to a problem, in that there are no homes for prospective buyers in the Reno and Sparks area. Adding to the problem is that investors are buying up resale homes with the intent of selling them at a profit later, which adds to the scarcity of available homes.
While the residential market is suffering from not enough homes to satisfy buyers, there are ample commercial properties. As a result, there are no plans for any additional retail, office, or industrial projects in the Reno area for 2013. Vacancy rates are expected to fall only slightly to 12.3% for industrial properties and 17.7% for retail properties.
Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Attempt to Strike Experts in Collapse Case Fails
February 03, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's efforts to exclude two of the insured's experts in a collapse case were unsuccessful. Hudon Specialty Ins. Co. v. Talex Enterprises, LLC, 2019 U.S. Dist. LEXIS 150148 (S.D. Miss. Sept. 4, 2019).
The insureds' building collapsed. The remaining portions of the building required immediate stabilization. The insureds hired Mr. Laird, an engineer, to prevent further property destruction. The insured designated Mr. Laird as a non-retained expert for trial. Mr. Laird's report claimed that the collapse was caused because the building had been re-roofed many times without removal of the degraded underlying roofing materials, thereby adding additional weight to the roof structure.
The insureds also designated Steve Cox as a non-retained expert. Mr. Cox was an architect who owned property neighboring the building that collapsed. He opined that the building collapsed because of the condition of very old mortar and not because of water standing on the building roof or because of roof repairs.
Hudson sought to strike these two experts because their opinions were inconsistent with the admitted facts. A document produced by the insureds stated that a large amount of rainwater had collected on the roof and the weight of the rainfall was the proximate cause of the collapse. Hudson claimed that this statement qualified as a judicial admission, removing the question of causation from contention. The court disagreed that the statement was a judicial admission because it did not form any part of the pleadings. The statement may have been an evidentiary admission that could be controverted or explained by the parties.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Court Holds That Public Entity Can Unilaterally Replace Subcontractor Under California’s Subletting and Subcontracting Fair Practices Act
July 22, 2019 —
Garret Murai - California Construction Law BlogThe Subletting and Subcontracting Fair Practices Act (Public Contract Code section 4100 et seq.), also known as the Listing Law, is intended to prevent direct contractors on public works projects from “bid shopping” and “bid peddling.”
Bid Shopping: Bid shopping is when a direct contractor discloses a subcontractor’s bid to other subcontractors in an attempt to obtain a lower bid than the one in which it based its bid to the owner.
Bid Peddling: Bid peddling is the other side of the equation. It is when a subcontractor whose bid was not selected, lowers its bid in an attempt to induce the direct contractor to substitute it for another subcontractor after the prime contractor’s bid has been awarded.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Common Construction Contract Provisions: Indemnity Provisions
January 19, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLP BlogUpcoming blog posts will focus on common contract provisions found in construction contracts. Such provisions are not solely limited to construction contracts and can be found in many other types of business contracts as well. This post will highlight indemnity clauses.
An indemnity clause is a common contract provision used to allocate risk between parties to a contract. The clause obligates one party (the Indemnitor) to protect the other party (the Indemnitee) from certain losses, typically arising from claims of third parties. It may require the Indemnitor to reimburse the Indemnitee for losses or expenses, or satisfy judgments, or even defend the Indemnitee in a lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Hotel Owner Makes Construction Defect Claim
January 28, 2013 —
CDJ STAFFA lawsuit has been filed over the construction of the GrandStay Hotel & Conference Center in Apple Valley Minnesota. Apple Valley GSRS, LLC, who invested in the hotel, has sued Cole Group Architects and Cornerstone Construction, alleging that the architects design was not to industry standards and that the builder used inferior materials and techniques. The lawsuit makes claim of "significant damage."
The hotel hired an engineer who subsequently recommended that all the stucco and the roof should be be replaced. The stucco has shown signs of cracking and crumbling. The hotel states that the roof has problems with leaking.
Cornerstone has denied the hotel's claims. They have also counter-sued their subcontractors.
Read the court decisionRead the full story...Reprinted courtesy of
French Laundry Spices Up COVID-19 Business Interruption Debate
April 20, 2020 —
Jeffrey J. Vita & Melanie A. McDonald - Saxe Doernberger & VitaOn March 26, 2020, Michelin-rated Napa Valley restaurants, French Laundry and Bouchon Bistro, and their celebrity chef, Thomas Keller, filed the second known
coronavirus-related declaratory judgment (DJ) lawsuit by a restaurant. The restaurants filed their DJ against Hartford Fire Insurance Company just seven days after Napa County issued a Shelter at Home Order.1 Chef Keller’s suit comes on the heels of the first such suit by a restaurant seeking to recover business income losses, filed by iconic New Orleans French Quarter restaurant Oceana Grill2 on March 17, just four days after the Louisiana governor issued an order prohibiting gatherings of more than 250 people.
As local governments seek to protect their citizens and prevent an onslaught of cases in area hospitals, they are issuing various “stay home,” “shelter at home,” and similar orders to force social distancing and to help flatten the curve of the growth in COVID-19 cases. Restaurants nationwide are especially hard hit by these orders, as many of these orders contain size limitations on gatherings, which have required that restaurants and bars limit capacity (as in the March 13th Louisiana order). Other such orders require non-essential businesses to “cease all activities in the County” (as in the Napa County Shelter at Home order). The Napa County order does not exempt restaurants as “essential businesses,” except when providing food for take-out or delivery. Other orders, still, directly address restaurants and require them to cease allowing public consumption of food and beverages (as in the subsequent, March 17th Louisiana order).
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C. and
Melanie A. McDonald, Saxe Doernberger & Vita, P.C.
Mr. Vita may be contacted at jjv@sdvlaw.com
Ms. McDonald may be contacted at mam@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Chimney Collapses at South African Utility’s Unfinished $13 Billion Power Plant
November 21, 2022 —
Paul Burkhardt - BloombergSouth Africa’s newest coal-fired power plant, which has been under construction since 2008 and will cost an estimated 232 billion rand ($12.7 billion), shut one of its six generating units after a duct collapsed.
The unit at the Kusile plant could remain offline “for a few months” although a clearer estimate will be known over coming weeks, state-owned utility Eskom Holdings SOC Ltd. said in a statement late Wednesday. The outage comes as the country endures record blackouts -- locally known as loadshedding.
The duct appeared to have sheared off from the unit’s main structure, a photo posted on Twitter by Anton Eberhard, a professor at the University of Cape Town’s Graduate School of Business, showed.
Read the court decisionRead the full story...Reprinted courtesy of
Paul Burkhardt, Bloomberg