Contract Change #9: Owner’s Right to Carry Out the Work (law note)
March 28, 2018 —
Melissa Dewey Brumback - Construction Law in North CarolinaIn prior versions of the General Conditions, if a contractor defaulted and the Owner (after giving notice) opted to cure by carrying out the work itself, an appropriate Change Order would be issued. However,
a Change Order is a contract that requires an agreement by both the Owner and Contractor, and, obviously, Contractors were reluctant to agree that they were in default and responsible for a deductive change order.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North Carolina
Changes to the Federal Rules – 2024
November 18, 2024 —
William L. Doerler - The Subrogation StrategistUnless Congress moves quickly, several amendments to the Federal Rules of Civil Procedure and Evidence will take effect December 1, 2024. Below is a brief description of the amendments.
Rules of Evidence
Rule 107 is a new rule. This rule addresses illustrative aids, stating that, if such aid helps the trier of fact to understand the evidence or an argument, a party may use the aid if its utility is not substantially outweighed by the danger of, among other things, unfair prejudice. As noted under the discussion of Rule 1006, below, an illustrative aid - offered only to help the trier of fact understand the evidence - is generally not admissible into evidence.
Rule 613 currently states that extrinsic evidence of a witness’s prior inconsistent statement is admissible only if the witness is given an opportunity to explain or deny the statement and the adverse party is given an opportunity to examine the witness about it, or if justice so requires. As amended, the court has the discretion to forego this requirement.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Traub Lieberman Partner Katie Keller and Associate Steven Hollis Obtain Summary Judgment Based on Plaintiff’s Failure to Comply with Policy Conditions
June 12, 2023 —
Kathryn Keller & Steven A. Hollis - Traub LiebermanTraub Lieberman Partner Katie Keller and Associate Steven Hollis obtained summary judgment on behalf of a major homeowners’ insurer in a breach of contract action in the Circuit Court for the Ninth Judicial Circuit in and for Osceola County, Florida. The underlying claim involved a water loss in the kitchen of the Plaintiff’s property allegedly resulting in substantial damage to the home necessitating renovations throughout the residence. The claim was reported seventeen days after the reported date of loss by Plaintiff’s counsel. The Plaintiff had retained counsel and two vendors before giving notice to the insurer. In addition, the insurer’s field adjuster was not provided the opportunity to inspect the plumbing materials which had been allegedly damaged. Specifically, the bottom panel of the sink kitchen cabinet box had been removed. The insurer retained an engineer, who concluded that the removal of the damaged property hindered the ability of the engineer to determine their conditions prior to removal or whether exposure from waste arm leakage occurred. It was later learned that the damaged plumbing fixtures and the bottom of the cabinets had been thrown out by the contractors, which all happened before the claim was reported to the insurer. The insured also failed to provide a signed, sworn proof of loss within sixty days after the loss.
Reprinted courtesy of
Kathryn Keller, Traub Lieberman and
Steven A. Hollis, Traub Lieberman
Ms. Keller may be contacted at kkeller@tlsslaw.com
Mr. Hollis may be contacted at shollis@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Precedent-Setting ‘Green’ Apartments in Kansas City
September 17, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to the Kansas City Star, the Missouri riverfront apartment development, Second and Delaware, is being constructed with “greener-than-green technology” and features the following: “Sixteen-inch-thick concrete walls. Rooftop gardens. A 90 percent reduction in energy use compared to current building codes.”
The two buildings “will comprise the largest U.S. multifamily apartment project using Passive House Institute-certified construction, a system that’s more energy-efficient than the highest LEED (Leadership in Energy and Environmental Design) building standard.”
Read the court decisionRead the full story...Reprinted courtesy of
Federal Judge Dismisses Insurance Coverage Lawsuit In Construction Defect Case
December 09, 2011 —
CDJ STAFFA federal judge dismissed a coverage lawsuit brought by Mid Continent Casualty Company against its insured, Greater Midwest Builders Ltd.
Plaintiff brought this declaratory judgment action in response to a suit filed in Johnson County District Court, seeking a judicial determination that it had no coverage obligation for claims asserted against its insured. This case was stayed until the state court action entered judgment against the insured. The prevailing parties then commenced a garnishment action against the plaintiff, and another insurance company, in state court in Missouri. The court was asked whether it should lift the stay and proceed with the case, or decline jurisdiction in favor of resolution in the Missouri state court.
The court granted the motion to dismiss holding that proceeding with the case would lead to protracted, piecemeal litigation, while deferring to the Missouri state court would decide all the claims involved in the dispute.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Court of Appeals Finds Insured AOAO Not Liable for Securing Inadequate Insurance
March 04, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Hawaii Intermediate Court of Appeals (ICA) affirmed the trial court's finding that the insured Association of Apartment Owners (AOAO) was not liable for securing a policy with inadequate coverage. AOAO Queen Emma Gardens, et al v. Wa, 2023 Haw. App. LEXIS 400 (Haw. Ct. App. Dec. 19, 2023).
In October 2002, the Was purchased a condominium located in the Queen Emma Gardens Condominium. The AOAO's bylaws provided that it would procure and maintain insurance "to insure the Board, the Association, and each apartment owner against claims for personal injury, death, and property damage arising out of the condition of the property or activities thereon . . ." The AOAO secured a CGL policy from Insurance Association, Inc., with coverage limits for bodily injury at $1,000,000 and an umbrella policy providing an additional $5,000,000 of coverage. Each of the policies "insured each individual insurance owner of the insured condominium, but only with respect to liability arising out of the ownership, maintenance or repair of that portion of the premises which is not reserved for that unit owner's exclusive use or occupancy."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
California Appeals Court Remands Fine in Late Completion Case
November 18, 2011 —
CDJ STAFFThe California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.
The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”
Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”
Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”
The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”
The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.
The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Round-Up (02/08/23) – The Build America, Buy America Act, ESG Feasibility, and University Partnerships
February 27, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThis week’s round-up explores President Joe Biden’s recent State of the Union address and plans for the Build America, Buy America Act, the feasibility of real estate companies achieving their ESG goals, and how developers, lenders, and tenants are partnering with universities to solve real estate challenges.
- During his annual State of the Union address, President Joe Biden detailed his Build America, Buy America plans and standard to require all construction materials on federal infrastructure projects to be made in the United States. (Jennifer Goodman & Zachary Phillips, Construction Dive)
- Speculation surrounding the economic environment and real estate stability is testing the feasibility and resilience of the environmental, social and corporate governance (ESG) framework used by corporations to measure their societal impact. (Anna Staropoli, Commercial Observer)
- Adopting Web3 and decentralization in the real estate industry is projected to bring about significant changes and improvements. (David Bitton, Forbes)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team