Wait! Don’t Sign Yet: Reviewing Contract Protections During the COVID Pandemic
April 13, 2020 —
Danielle S. Ward - Balestreri Potocki & HolmesAs the circumstances of the COVID pandemic change day by day, and we all rush to keep business moving where and when we can, companies should consider hitting the “pause button” before renewing or executing any new contracts. Developing contracts often takes considerable time and expense, and companies are not in the habit of reworking them often. A change in law may prompt a company to revisit their contract terms, but otherwise business is often carried out with a standard form contract for a period of years. With the COVID pandemic affecting nearly every business and industry, life is not business as usual, and companies should make sure their contracts consider what previously seemed like an unforeseeable event.
Force Majeure clauses are included in many contracts to excuse contract performance when made impossible by some unforeseen circumstance. These clauses typically fall under two categories: general and specific. General force majeure clauses excuse performance if performance is prevented by circumstances outside the parties’ control. By contrast, specific force majeure clauses detail the exhaustive list of circumstances (acts of god, extreme weather, war, riot, terrorism, embargoes) which would excuse contract performance. Force majeure clauses are typically interpreted narrowly. If your contract has a specific clause and pandemic or virus is not one of the listed circumstances it may not apply. Whether a particular existing contract covers the ongoing COVID pandemic will vary depending on the language of the contract.
Force majeure clauses previously made headlines when the great economic recession hit in 2008. A number of courts held that simple economic hardship was not enough to invoke force majeure. The inability to pay or lack of desire to pay for the contracted goods or services did not qualify as force majeure. In California, impossibility turns on the nature of the contractual performance, and not in the inability of the obligor to do it. (Kennedy v. Reece (1964) 225 Cal. App. 2d 717, 725.) In other words, the task is objectively impossible not merely impossible or more burdensome to the specific contracting party.
California has codified “force majeure” protection where the parties haven’t included any language or the circumstances in the clause don’t apply to the situation at hand. Civil Code section 1511 excuses performance when “prevented or delayed by an irresistible, superhuman cause, or by the act of public enemies of this state or of the United States, unless the parties have expressly agreed to the contrary.” (Civ. Code § 1511.) What qualifies as a “superhuman cause”? In California, the test is whether under the particular circumstances there was such an insuperable interference occurring without the party's intervention as could not have been prevented by the exercise of prudence, diligence and care. (Pacific Vegetable Oil Corp. v. C. S. T., Ltd. (1946) 29 Cal.2d 228, 238.)
If you find yourself in an existing contract without a force majeure clause, or the statute does not apply, you may consider the doctrine of frustration of purpose. This doctrine is applied narrowly where performance remains possible, but the fundamental reason the parties entered into the contract has been severely or substantially frustrated by an unanticipated supervening circumstance, thus destroying substantially the value of the contract. (Cutter Laboratories, Inc. v. Twining (1963) 221 Cal. App. 2d 302, 314-15.) In other words, performance is still possible but valueless. Note this defense is not likely to apply where the contract has simply become less profitable for one party.
Now that COVID is no longer an unforeseeable event, but rather a current and grave reality, a party executing a contract today without adequate protections may have a difficult time proving unforeseeability. Scientists are not sure whether warm weather will suppress the spread of the virus, as it does with the seasonal flu, but to the extent we get a reprieve during the summer we may see a resurgence of cases this Fall or Winter. Companies should take care in reviewing force majeure clauses, and other clauses tied to timely performance such as delay and liquidated damages before renewing or executing new contracts.
Your contract scenario may vary from the summary provided above. Please contact legal counsel before making any decisions. During this critical time, BPH’s attorneys can be reached via email to answer your questions.
Read the court decisionRead the full story...Reprinted courtesy of
Danielle S. Ward, Balestreri Potocki & HolmesMs. Ward may be contacted at
dward@bph-law.com
Oregon to Add 258,000 Jobs by 2022, State Data Shows
March 26, 2014 —
Alison Vekshin – BloombergOregon expects to add 258,000 jobs by 2022, a 15 percent increase driven by the economic recovery in the construction industry and growth in health care, according to the Oregon Employment Department.
Construction industry employment is projected to rise 29 percent, the fastest of any industry, though short of pre-recessionary growth, the agency said March 12 in a statement.
The predictions “reflect several ongoing trends: continuing recovery from the Great Recession, particularly for the construction industry; a growing health-care sector, due in part to an aging population; continuing population growth; and the need for replacement workers due to baby-boomer retirements,” the agency said.
Read the court decisionRead the full story...Reprinted courtesy of
Alison Vekshin, BloombergMs. Vekshin may be contacted at
avekshin@bloomberg.net
CISA Guidance 3.1: Not Much Change for Construction
June 22, 2020 —
Laura Bourgeois LoBue - Gravel2Gavel Construction & Real Estate Law BlogThis week, the Cybersecurity & Infrastructure Security Agency (CISA) issued Version 3.1 of its Guidance on the Essential Critical Infrastructure Workforce. For the most part, CISA’s Guidance 3.1 did not change from Version 3.0 as it relates to construction. However, CISA added a few construction-related services to “Essential Critical Infrastructure”:
- “Workers who support the construction and maintenance of electric vehicle charging stations.”
- “Engineers performing or supporting safety inspections.”
Read the court decisionRead the full story...Reprinted courtesy of
Laura Bourgeois LoBue, PillsburyMs. LoBue may be contacted at
laura.lobue@pillsburylaw.com
Anti-Concurrent Causation Clause Preserves Possibility of Coverage
January 15, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe policy's anti-concurrent causation clause preserved the possibility of coverage when the insurer's motion for summary judgment to disclaim its indemnity obligation for damage caused by Hurricane Sandy was overturned by the Second Circuit. Madelaine Chocolate Novelties, Inc. v. Great Northern Ins. Co., 2018 U.S. App. LEXIS 29821 (Oct. 23, 2018 2nd Cir. )
In 2012, Madelaine Chocolate suffered significant damage to its business due to storm surges created by Hurricane Sandy. Madelaine Chocolate had an "all-risk" policy issued by Great Northern. Madelaine Chocolate filed a claim for property damage of approximately $40 million and business income loss and extra operation expenses of $13.5 million. Great Northern denied most of the claim, reasoning that the storm surge damage was excluded under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Condo Building Increasing in Washington D.C.
November 05, 2014 —
Beverley BevenFlorez-CDJ STAFFBuilder reported that in Washington D.C., "the condo pipeline has increased for the first time since 2005, according to Alexandria, Va.,-based research firm Delta Associates." Supply has grown with "3,100 units either being marketed or sold in around the nation's capital." Furthermore, "condo prices have jumped 12 percent year over year."
“The size of the projects are smaller than they were in the last boom cycle,” William Rich, senior vice president and multifamily practice director at Delta, told Builder.
Read the court decisionRead the full story...Reprinted courtesy of
Out of Eastern Europe, a Window Into the Post-Pandemic Office
September 28, 2020 —
Andra Timu & Irina Vilcu - BloombergSpecial quarantine rooms. Floor-to-ceiling walls in bathroom stalls. Touchless entrances that take your temperature. This is what telecommunications company Ericsson’s office building in Bucharest looks like after coronavirus. The space has become the pilot for a 100-prong coronavirus standard that a real estate investor in Eastern Europe is pitching as a new global “immune” building standard.
Liviu Tudor, president of the Brussels-based European Property Federation, hopes the standard will convince more employees to go back to work. He’s gathered a team of experts in construction, health care and engineering, such as such as Adrian Streinu-Cercel, the head of Bucharest's biggest infectious diseases hospital, to develop three tiers of “immune” building certifications that he says are intended to make indoor spaces “pandemic proof.”
Read the court decisionRead the full story...Reprinted courtesy of
Andra Timu & Irina Vilcu, Bloomberg
Precast Standards' Work Under Way as Brittle Fracture Warnings Aired
December 22, 2019 —
Nadine M. Post - Engineering News-RecordThe American Concrete Institute is gearing up to develop ACI’s first code requirements specifically for precast concrete. The recent announcement of the initiative comes on the heels of an article in the September issue of ACI’s monthly magazine, Concrete International, that sounds the alarm about the potential for brittle failures of precast, prestressed-concrete double-T parking decks, with flanges reinforced with a non-code-compliant polymer-coated carbon-fiber grid product, called C-Grid.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Details of Sealed Whistleblower Charges Over Cuomo Bridge Bolts Burst Into Public View
March 22, 2021 —
Richard Korman - Engineering News-RecordTappan Zee Constructors, the consortium that built the big New York Hudson River crossing that opened in 2018, is embroiled in another lawsuit related to the bridge.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of