Anthony B. Cavender - Gravel2GavelSeveral interesting decisions have recently been made by federal and state courts.
FEDERAL APPELLATE COURTS
The U.S. Seventh Circuit Court of Appeals – ARCO Shifts from State to Federal and No Vigor for VIM
On June 18, 2020, the court decided the case of Baker, et al. v. ARCO, holding that the revised federal removal statutes authorize the removal to federal court of a state-filed complaint against several defendants by the former residents of an Indiana housing complex who contended that the defendants were responsible for the industrial pollution attributed to the operations of a now-closed industrial plant. The housing complex was constructed at the site of the former U.S. Smelter and Lead Refinery. During the Second World War, the plant produced products for the use of the government war effort, thus triggering the applicability of the federal removal statutes.
On June 25, 2020, the court decided the case of Greene, et al. v. Westfield Insurance Company. As the court notes, this is a matter that “began as a case about environmental pollution and evolved into a joint garnishment action.” An Indiana wood recycling facility, VIM Recycling, was the subject of many complaints by nearby residents that its operations and waste disposal activities exposed then to dust and odors in violation of federal law and triggered state tort law claims. VIM was sued in state court, but neglected to notify its insurer, as required by its insurance policy with Westfield Insurance. One thing led to another, and a default judgment in the amount of $ 50 million was entered against VIM. Since VIM at that point had no assets, the plaintiffs and later VIM sought recovery from Westfield. When this dispute landed in federal court, the court, after reviewing the policy, concluded that there was a provision excluding coverage when the insured knew it had these liabilities when it purchased the insurance. As a result, the lower court dismissed the lawsuit, and this decision has been affirmed by the Seventh Circuit.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Want to Stay Up on Your Mechanic’s Lien Deadlines? Write a Letter or Two
March 22, 2017 —
Christopher G. Hill – Construction Law Musings90 days. 150 days. 6 months. 30 days. Do these numbers sound familiar? If you read Construction Law Musings regularly, they should be. These are various deadlines relating to the recording and enforcement of mechanic’s liens in Virginia.
90 days from your last work performed (or from the last date of the last month of work in the correct circumstances) sets the outside limit on when a construction company can record a lien on a construction project. 150 days is the “look back” period for what work’s value can be included in that lien. 6 months is the statute of limitations for the filing of an enforcement suit. Finally, 30 days amount of time after your start of work within which you, as a construction professional, must notify a mechanic’s lien agent of your presence on a residential project. Of course, there are always nuances to these rules that need to be taken into account, preferably with the help of your friendly neighborhood construction attorney, before deciding how to proceed in this very picky and “form over function” area of construction law.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Is the Construction Industry Actually a Technology Hotbed?
August 19, 2024 —
Andrew Silver - Construction ExecutiveTechnology has always been a driving force behind progress, and the construction industry is no exception. Over the years, technological advancements have revolutionized the way companies design, plan and build structures, leading to increased efficiency, safety and sustainability. From virtual-reality simulations to drones and 3D printing, technology has transformed every aspect of the construction process. However, the construction trades still lag behind other sectors in adoption of digital technologies. With a lack of skilled labor continuing to be an impediment to growth and profitability in the construction industry, technological developments could have significant implications for successful adopters.
Already, the industry is seeing a huge difference in valuation between traditional engineering and construction firms and construction software companies. As labor shortages continue to hinder growth in the industry, consolidation is likely, as is the probability that companies with the greatest tech capabilities will be the most highly valued. There are several areas of technology that are of the greatest interest in the current marketplace.
BIM
Building information modeling with computer-aided design software now allows architects and engineers to create detailed and accurate 3D models of buildings and infrastructure projects, integrating data about every aspect of the building, from materials and costs to energy efficiency and maintenance schedules. These models not only help in visualizing the final product; they also enable better communication and collaboration among project stakeholders.
Reprinted courtesy of
Andrew Silver, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
LAX Runway Lawsuit a Year Too Late?
January 17, 2014 —
Beverley BevenFlorez-CDJ STAFFThe City of Los Angeles filed a lawsuit against Tutor-Saliba Corp. and O&G Industries Inc., which had created a joint venture to rebuild Runway 25L at Los Angeles International Airport (LAX), according to Brian Sumers writing for the Daily Breeze. However, lawyers for the construction companies are alleging that the lawsuit was filed a year too late: “…the complaint’s first four causes of action against Joint Venture are indisputably barred under California Law,” lawyers from Castle & Associates claimed.
This news came soon after a plane blew a tire on the same runway involved in the lawsuit, as reported by the Los Angeles Times. The blown out tire may not be related to the alleged construction defects: “The runway is usable,” Nancy Castles, spokeswoman for Los Angeles World airports told the Los Angeles Times. Castles explained that “the lawsuit is about ‘deterioration’ and that at some point the runway will need to be rebuilt, but that time is not now.”
Read the full story at the Daily Breeze...
Read the full story at the Los Angeles Times...
Read the court decisionRead the full story...Reprinted courtesy of
Chicago Criticized for Not Maintaining Elevator Inspections
October 29, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Crain’s Chicago Business, “as few as a fifth of elevators get the required annual checkup,” Chicago Inspector General Joe Ferguson claimed.
Ferguson audited the roughly 5,100 buildings that city inspectors were assigned to inspect elevators, and found that only 965 were actually inspected, reported Crain’s Chicago Business. Furthermore, “when problems were found in inspections conducted by city personnel, they often were not fixed in a timely manner, again according to city records.”
Read the court decisionRead the full story...Reprinted courtesy of
Leonard Fadeeff v. State Farm General Insurance Company
September 21, 2020 —
Michael Velladao - Lewis BrisboisIn Fadeeff v. State Farm Gen. Ins. Co., 50 Cal.App.5th 94 (May 22, 2020), the California Court of Appeal reversed the entry of summary judgment in favor of State Farm General Insurance Company (“State Farm”) in connection with a smoke and soot damage claim made by Leonard and Patricia Fadeeff (the “Fadeeffs”) for damage sustained by their home due to the 2015 Valley Fire. The parties’ dispute arose out of the Valley Fire, which took place in Lake County, California. The Fadeeffs’ home was located in Hidden Valley Lake.
The Fadeeffs submitted a claim to State Farm under their homeowners policy. Initially, after an adjuster inspected the home and noted that it was “well maintained” with no apparent maintenance issues, State Farm made a series of payments and arranged for ServPro to clean the smoke and soot damage. Subsequently, the Fadeeffs retained an independent adjuster and submitted a supplemental claim in the amount of $75,000. State Farm retained a different unlicensed adjuster to investigate the claim and retained expert, Forensic Analytical Consulting Services (FACS) to inspect the Fadeeffs’ home, and another company referred to as HVACi, to inspect the Fadeeffs’ HVAC system.
The independent adjuster used to investigate the Fadeeffs’ supplemental claim failed to follow company guidelines in connection with using experts, which required specific questions to be addressed by the expert. In addition, FACS only took surface samples of the walls in the Fadeeffs’ home. Ultimately, the reports prepared by FACS and HVACi concluded that no additional work was required to remediate the damage sustained by the Fadeeffs’ home. Thereafter, State Farm denied the Fadeeffs’ supplemental claim.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Velladao, Lewis BrisboisMr. Velladao may be contacted at
Michael.Velladao@lewisbrisbois.com
First-Time Buyers Home Sales Stagnates
October 22, 2014 —
Beverley BevenFlorez-CDJ STAFFDespite a rise overall in home sales, “first-time buyer share remained unchanged from the previous two months at 29%, far behind the historical average first-time buyer share of about 40%,” reported National Association of Home Builders’ Eye on Housing. However, “[e]xisting home sales increased to the highest level of the year, having posted gains for five of the last six months, despite weakness among first-time buyers. Existing home sales increased 2.4% in September, but remain 1.7% below the same period a year ago.”
According to Eye on Housing, existing sales is expected to continue to increase throughout the year, though the first-time buyer segment is “the weak spot.”
Read the court decisionRead the full story...Reprinted courtesy of
South Africa Wants Payment From Colluding World Cup Builders
July 23, 2014 —
Kamlesh Bhuckory and Mike Cohen – BloombergSouth Africa’s government is putting pressure on construction companies to make further payments as punishment for rigging contracts to build stadiums for the 2010 FIFA Soccer World Cup and other projects.
Antitrust authorities fined 15 builders, including Murray & Roberts Holdings Ltd. (MUR) and Aveng Ltd., a total of 1.5 billion rand ($141 million) in June 2013, after a probe that spanned almost four years found they colluded to drive up prices.
“The 1.5 billion rand in penalties is not the end of the story with the construction industry,” Economic Development Minister Ebrahim Patel told lawmakers in Cape Town today. “We are now in discussion with the construction industry on a restitution package for their collusion and price fixing.”
Mr. Bhuckory may be contacted at kbhuckory@bloomberg.net; Mr. Cohen may be contacted at mcohen21@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Kamlesh Bhuckory and Mike Cohen, Bloomberg