Construction Contracts Need Amending Post COVID-19 Shutdowns
October 19, 2020 —
Richard P. Higgins - Construction ExecutiveNo one could have expected the coronavirus pandemic in the beginning of 2020. True, there were rumblings about a sickness in China that was highly contagious and infecting many people. Death tolls began rising as the world watched in disbelieve. After all, this is 2020. This is not supposed to happen. We should have been able to control the spread of the virus, but we could not. COVID-19 quickly spread throughout the world causing havoc and economic despair.
While some sectors of the construction industry are not as impacted as others, contractors industry-wide need to consider how COVID-19 will impact their contractual obligations. Depending on what happens and what the government decides to do to stop the spread of the coronavirus, project delays, supply chain distributions, lost productivity and work stoppages may continue for months. All of this will impact the contracts that contractors have with owners. Contractors may not be able to preform according to the terms of the contract through no fault of their own. Owners may no longer qualify for the financing needed to pay for the project.
FORCE MAJEURE
According to Investopedia, “force majeure refers to a clause that is included in contracts to remove liability for natural and unavoidable catastrophes that interrupt the expected course of events and prevent participants from fulfilling obligations.”
Reprinted courtesy of
Richard P. Higgins, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Higgins may be contacted at
Richard.Higgins@MCC-CPAs.com
Mississippi Supreme Court Addresses Earth Movement Exclusion
December 09, 2019 —
Anthony Hatzilabrou - Traub LiebermanRecently, the Mississippi Supreme Court held that structural damages to the foundation of an insured’s home came within the earth movement exclusion in a homeowner’s policy, notwithstanding a provision in the policy which provided coverage for water damage resulting “from accidental discharge or overflow of water … from within … [p]lumbing, heating, air condition or household appliance.”
In Mississippi Farm Bureau Cas. Ins. Co. v. Smith, 264 So. 3d 737 (Miss. 2019), the appellee, Smith, filed a lawsuit against her homeowner's insurance company, Mississippi Farm Bureau Casualty Insurance Company (“Farm Bureau”) for its refusal to pay for repairs to the foundation of Smith’s home. Smith alleged that the refusal to pay for repairs amounted to breach of contract and asserted claims for bad faith and tortious breach of contract. In response, Farm Bureau filed a motion for summary judgment on the basis of the policy’s earth-movement exclusion, which provided that Farm Bureau “did not insure for loss caused directly or indirectly by…Earth Movement…[which] means…[a]ny other earth movement including earth sinking, rising or shifting... caused by or resulting from human or animal forces.” Smith filed a cross-motion for partial summary judgment on the basis that the earth-movement exclusion did not preclude coverage because her insurance policy also contained a clause expressly covering water damage.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony Hatzilabrou, Traub LiebermanMr. Hatzilabrou may be contacted at
thatzilabrou@tlsslaw.com
U.S. Supreme Court Limits the Powers of the Nation’s Bankruptcy Courts
June 11, 2014 —
Earl Forte – White and Williams LLPOn June 9, 2014, the Supreme Court of the United States issued its much-awaited decision in Executive Benefits Insurance Agency v. Arkison, Chapter 7 Trustee of Estate of Bellingham Insurance Agency, Inc., Case No. 12-1200, in which the court confirmed that the power of the nation’s bankruptcy courts to hear and decide cases involving state-created private rights in which the bankruptcy proof of claim process has not been directly invoked, is severely limited by Article III of the Constitution of the United States.
The decision in Executive Benefits, while providing some clarity to practitioners and the public following the Court’s June 2011 decision in Stern v. Marshall, 131 S. Ct. 2594 (2011), nevertheless will make a substantial portion of bankruptcy litigation matters more cumbersome and potentially more expensive to guide through the bankruptcy system. Clients and practitioners are best advised to hire knowledgeable counsel to help navigate the more complex procedural waters created by this decision.
Although the Court in Executive Benefits did resolve a pending procedural question that had dogged practitioners since Stern was decided in 2011, the Court’s decision in Executive Benefits now makes it abundantly clear that many disputes that were previously heard and decided in the nation’s bankruptcy courts can no longer be decided there and must be submitted to the district courts for full de novo review and entry of a final judgment or order. It is difficult to see how this decision will not make bankruptcy litigation more cumbersome and expensive by adding an additional layer of judicial involvement to many matters, notably to fraudulent transfer and other avoidance “claw back” actions that historically have been decided in the bankruptcy courts and used famously in Madoff and other cases as an efficient device for creating value for creditors.
Read the court decisionRead the full story...Reprinted courtesy of
Earl Forte, White and Williams LLPMr. Forte may be contacted at
fortee@whiteandwilliams.com
Preserving your Rights to Secure Payment on Construction Projects (with Examples)
March 22, 2017 —
David Adelstein – Florida Construction Legal UpdatesAll participants across the construction industry should understand what efforts they should take to maximize and collateralize payment. No one wants to work for free and, certainly, no one in the construction industry wants to work without ensuring there is some mechanism to recover payment in the event they remain unpaid. Being proactive and knowledgeable can go a long way when it comes to recovering your money.
Your Contract – It starts with the contract. You should understand those risks that are allocated to you and those that are allocated to another party. And, you should understand the contractual mechanism to resolve claims and disputes and whether your contract has a prevailing party attorney’s fees provision. In addition to contractual rights, there are tools for you to maximize your collection efforts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Construction Group Seeks Defense Coverage for Hard Rock Stadium Claims
December 09, 2019 —
Sergio F. Oehninger & Daniel Hentschel - Hunton Insurance Recovery BlogIn an insurance coverage action pending in the S.D.N.Y., Hunt Construction Group (Hunt) contends that Berkley Assurance Company wrongfully denied defense coverage for claims arising out of the renovation of Hard Rock Stadium (home to the Miami Dolphins and Miami Hurricanes football teams).
The stadium owner, South Florida Stadium LLC (SFS), hired Hunt to serve as the construction manager for the renovation project. Hunt subcontracted with Alberici Constructors Inc. (Alberici) to design and fabricate roof structures for the stadium.
Hunt and SFS sued Alberici over its work on the project. In March 2017, Alberici asserted counterclaims against Hunt and SFS. In May 2018, SFS sought defense and indemnification from Hunt with respect to Alberici’s coverage claims.
Hunt is insured under claims made and reported professional liability insurance policies issued by Berkley with policy periods from June 15, 2016 to June 15, 2017 (with an automatic extended reporting period through August 14, 2017) and from July 15, 2017 to June 15, 2018. Hunt notified Berkley of Alberici’s counterclaim on July 20, 2017 (within the extended reporting period of the 2016-2017 policy) and of SFS’s indemnity claim on June 5, 2018 (within the 2017-2018 policy period).
Reprinted courtesy of
Sergio F. Oehninger, Hunton Andrews Kurth and
Daniel Hentschel, Hunton Andrews Kurth
Mr. Oehninger may be contacted at soehninger@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Two More Lawsuits Filed Over COVID-19 Business Interruption Losses
April 13, 2020 —
Michael S. Levine - Hunton Andrews KurthTwo more lawsuits were filed yesterday concerning business interruption losses resulting from the COVID-19 pandemic. The plaintiffs, the Chickasaw and Choctaw nations, filed their lawsuits, copies of which can be found
here and
here, in Oklahoma state court against a litany of property insurers, led by AIG. The lawsuits seek an order that any financial losses suffered by the nations’ casinos, restaurants and other businesses as a result of the coronavirus pandemic are covered by the nations’ insurance policies.
According to the complaints:
On or about March of 2020, the United States of America became infected by COVID 19 resulting in a pandemic. As a result of this pandemic and infection, the Nation’s Property sustained direct physical loss or damage and will continue to sustain direct physical loss or damage covered by the policies, including but not limited to business interruption, extra expense, interruption by civil authority, limitations on ingress and egress, and expenses to reduce loss. As a direct result of this pandemic and infection, the Nation’s Property has been damaged, as described above, and cannot be used for its intended purpose.
Read the court decisionRead the full story...Reprinted courtesy of
Michael S. Levine, Hunton Andrews KurthMr. Levine may be contacted at
mlevine@HuntonAK.com
Vacation Rentals: Liability of the Owner for Injury Suffered by the Renter
May 13, 2019 —
Kevin J. Parker - Snell & Wilmer Real Estate Litigation BlogWith the explosion of the “private” rental business wherein residential property owners rent their house or condo on a short-term basis to third-parties, certain legal issues have arisen with regard to the duties owed by the property owner to the renter.
A recent Virginia Supreme Court case, Haynes-Garrett v. Dunn, 818 S.E.2d 798 (Va. 2018), addressed that issue. In that case, the property owners owned a rental house in Virginia Beach. The property was not the owners’ main residence, but rather a vacation home that was sometimes used by the owners, but mostly used as a rental. The issue addressed by the court was whether – for the purpose of evaluating the owners’ duty of care to the renter – the relationship should be classified as a “landlord-tenant” relationship or an “innkeeper-guest” relationship. This classification was important because the duties of the owner to the renter were significantly different depending on the category. In the landlord-tenant arena, under Virginia law, the landlord has no duty to maintain the property in a safe condition because the property is deemed to be under the tenant’s exclusive control. (An exception being concealment or fraud by the landlord as to some defect in the premises that is known to the landlord but unknown to the tenant.) Assuming that exception does not apply, the tenant takes the premises in whatever condition they may be in, thus assuming all risk of personal injury from defects or dangerous conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin J. Parker, Snell & WilmerMr. Parker may be contacted at
kparker@swlaw.com
Why Employees Are Taking Ownership of Their Architecture Firms
January 22, 2024 —
Kriston Capps - BloombergThe architecture firm BNIM has always been a leader on sustainable design. In the late 1980s, principal emeritus Bob Berkebile was one of the first architects to push the industry to take the idea of green buildings seriously. Then-President Bill Clinton even recruited him to lead a climate-minded restoration of the White House. Berkebile and his Kansas City, Missouri–based firm — he’s the “B” in BNIM, alongside Tom Nelson, David Immenschuh and Steve McDowell — received top honors from the American Institute of Architects in 2011, among many other accolades.
Now the firm behind such projects as the US Embassy expansion in Kampala, Uganda, and a proposed South Loop park to deck over a highway in downtown Kansas City hopes to stand out in another way. In October, BNIM announced its transition to an employee stock ownership plan, or ESOP. The firm is one of a handful in the industry to recently embrace the employee-ownership model, following similar moves in 2021 by SHoP Architects and Zaha Hadid Architects.
Read the court decisionRead the full story...Reprinted courtesy of
Kriston Capps, Bloomberg