Architect Named Grand Custom Home Winner for Triangular Design
November 05, 2014 —
Beverley BevenFlorez-CDJ STAFFRobert Gurney, architect, created a triangular shaped home design to deal with restricted space on a corner lot that has "stumped developers for years," according to Custom Home.
"Using the wedge-shaped lot’s height limit and property line setbacks to define a structure, Gurney designed a striking triangle-plan house that not only answers its owners’ program requirements, but also makes a handsome and respectful addition to the existing streetscape," according to Custom Home.
Gurney told Custom Home that the clients--two graphic designers--helped make it successful. “They’re design-oriented,” he said, “so they were pretty much on board with whatever we came up with. And, fortunately, they didn’t need a lot of space; they’re empty-nesters.”
Read the court decisionRead the full story...Reprinted courtesy of
Georgia Court of Appeals Upholds Denial of Coverage Because Insurance Broker Lacked Agency to Accept Premium Payment
December 07, 2020 —
Lawrence J. Bracken II, Michael S. Levine & Rachel E. Hudgins - Hunton Insurance Recovery BlogIn American Reliable Insurance Company v. Lancaster, the Georgia Court of Appeals reversed the denial of a property insurer’s summary judgment motion concerning the insurer’s denial of a fire loss claim. The basis of the denial was that the policyholders had failed to pay the policy premium. The policyholders, Charlie and Wanda Lancaster, claimed that they had paid their policy premiums for several years to their insurance agent, Macie Yawn. In October 2014, American Reliable mailed a renewal notice to the Lancasters notifying them that premium payments had to be made directly to the insurer. After it did not receive payment from the Lancasters, American Reliable sent them a cancellation notice in December 2014, again notifying them that payments be made directly to the insurer. The Lancasters denied having received either notice from American Reliable, but the record included a receipt for certificate of mailing.
After the Lancaster’s home burned down in 2015, American Reliable denied coverage on the grounds that the policy had been cancelled for nonpayment of premium. In the subsequent coverage action, the trial court denied American Reliable’s motion for summary judgment, ruling that a factual issue existed as to the actual and apparent agency of the insurance agent, Yawn. On appeal, the Court of Appeals found that the trial court erred in deciding that there was a factual issue concerning Yawn’s agency. Specifically, the Court of Appeals ruled that the record showed American Reliable had terminated Yawn’s agency to accept policy premiums, and that the Lancaster’s received notice of that termination in the renewal and cancellation notices. In addition to determining that Yawn was not an actual agent, the Court held that Yawn did not have apparent agency, because the notices sent to the Lancasters stated that the premium payment was to be paid to American Reliable, not to the agent.
Reprinted courtesy of
Lawrence J. Bracken II, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and
Rachel E. Hudgins, Hunton Andrews Kurth
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Hudgins may be contacted at rhudgins@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Luxury Home Sales are on the Rise
February 04, 2014 —
Beverley BevenFlorez-CDJ STAFFThe New York Times reports that the sale of luxury homes is on the rise: “Yet despite the bursting of the housing bubble, the ensuing recession and the slow recovery, buyers have not abandoned luxury homes. It turns out that they just took a break. In July 2013, sales of homes costing more than $1 million were up 46.6 percent from the previous July.”
“The housing market is being driven by the move-up buyer, the luxury buyer,” Brad Hunter, chief economist and director of consulting at Metrostudy told the New York Times. “And those who have strong incomes, secure jobs, their stock portfolio is doing well — they are able to buy whatever they want. And what they are buying is larger houses.”
Toll Brothers design director, Tim Gehman, said that “the homes that sell best today are those with the biggest kitchens and most expansive master suites — much as they were before the recession,” according to the New York Times.
Read the court decisionRead the full story...Reprinted courtesy of
House of the Week: Spanish Dream Home on California's Riviera
July 30, 2014 —
Emily Heffter – BloombergFamous clients of renowned Los Angeles architect Richard Landry are not known for their restraint.
The Brentwood estate he designed for Tom Brady and Gisele Bundchen has a moat and just sold to Dr. Dre for $40 million. Michael Jackson died in a home Landry designed (a rental), and he has designed luxurious mansions for Wayne Gretzky, Michael Bolton, Mark Wahlberg and Kenny G.
Still, homeowner Lorna Auerbach did something unique when Landry started designing her dream home in Pacific Palisades: She flew him to Spain, with her, for 10 days.
Read the court decisionRead the full story...Reprinted courtesy of
Emily Heffter, Bloomberg
California Court Forces Insurer to Play Ball in COVID-19 Insurance Coverage Suit
December 13, 2022 —
Latosha M. Ellis & Yosef Itkin - Hunton Insurance Recovery BlogOne of the threshold issues in COVID-19 insurance coverage cases that have been brought across the country is whether the policyholder’s allegations meet the applicable pleading standard in alleging that the virus caused physical loss or damage. In many cases, the courts have gotten it wrong, effectively holding policyholders to a higher standard than required. But recently, a California federal judge righted those wrongs by acknowledging the correct pleading standard in that case, which is whether the allegations state a plausible claim for relief. Ashcroft v. Iqbal, 556 U.S. 662, 679 (2009). The Court, here, correctly recognized that the policyholder, the Los Angeles Lakers, met that pleading standard when it alleged that the COVID-19 virus can cause physical loss or damage by physically altering property.
In its complaint, the Los Angeles Lakers alleged that the virus physically altered its property by changing its chemical and physical property conditions, creating viral vectors that required remedial measures before the property was safe again. Los Angeles Lakers, Inc. v. Fed. Ins. Co., 591 F. Supp. 3d 672 (C.D. Cal. 2022), adhered to on reconsideration, 2022 WL 16571193 (C.D. Cal. Oct. 26, 2022). The Court agreed that these allegations by the Lakers adequately pled physical alteration to support a claim for property damage. The insurer requested reconsideration of the decision, and the Court emphatically affirmed its prior decision, explaining its rationale as follows:
The Court lacks the scientific expertise necessary to conclude, based solely on the allegations in the FAC . . . that it is not plausible for the Lakers’ property to have been physically altered by the Virus, which the Lakers adequately alleged. Consequently, the Court, in the March 17 Order, concluded that the Lakers’ theory was plausible. Whether the Lakers can actually prove its theory will be determined at summary judgment or trial.
Reprinted courtesy of
Latosha M. Ellis, Hunton Andrews Kurth and
Yosef Itkin, Hunton Andrews Kurth
Ms. Ellis may be contacted at lellis@HuntonAK.com
Mr. Itkin may be contacted at yitkin@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
DC Circuit Upholds EPA’s Latest RCRA Recycling Rule
September 23, 2019 —
Anthony B. Cavender - Gravel2GavelOn July 2, 2019, the U.S. Court of Appeals for the District of Columbia Circuit decided the case of California Communities Against Toxics, et al. v. EPA. In this decision, the court rejected the latest petition to strike or vacate EPA’s 2018 revisions to the Resource Conservation and Recovery Act (RCRA) hazardous waste recycling rules. In 1985, EPA promulgated a new regulatory definition of “solid waste,” which is the linchpin of the agency’s very stringent hazardous waste management rules. (See the rules located at 40 CFR Sections 260-268.) Unless a material is a “solid waste” as defined by the rules, it cannot also be a hazardous waste.
The 1985 rules grappled with the challenges posed by recycling practices, and attempted to distinguish between legitimate recycling which is not subject to hazardous waste regulation, and other more suspect forms of recycling. The rules are complex and replete with nuance. In doing so, EPA was adhering to RCRA’s statutory mandate that it develop appropriate rules to govern the treatment, storage and disposal of hazardous waste, while also promoting “properly conducted recycling and reuse.” The DC Circuit reviewed the 1985 rules in the seminal case of American Mining Congress v EPA, 824 F.2d 1177 (1987), (AMC) and stressed that only those materials that were truly discarded could be regulated as solid waste; for instance, those materials that were destined for immediate recycling or recovery in an ongoing production process were not discarded and hence were not solid waste. Over the years, the court has struggled to clarify the basic holding of AMC in numerous cases while EPA has frequently revised and amended the RCRA rules, and in particular the definition of solid waste, in an attempt to balance the policies mandated by the statute.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Arbitration Provisions Are Challenging To Circumvent
May 13, 2019 —
David Adelstein - Florida Construction Legal UpdatesArbitration provisions are enforceable and they are becoming more challenging to circumvent, especially if one of the parties to the arbitration agreement wants to arbitrate a dispute versus litigate a dispute. Remember this when agreeing to an arbitration provision as the forum for dispute resolution in your contract. There is not a one-size-fits-all model when it comes to arbitration provisions and how they are drafted. But, there is a very strong public policy in favor of honoring a contractual arbitration provision because this is what the parties agreed to as the forum to resolve their disputes.
By way of example, in Austin Commercial, L.P. v. L.M.C.C. Specialty Contractors, Inc., 44 Fla.L.Weekly D925a (Fla. 2d DCA 2019), a subcontractor and prime contactor entered into a consultant agreement that contained the following arbitration provision:
Any controversy or claim arising out of or relating to this Agreement or the breach thereof shall be subject to the dispute resolution procedures, if any, set out in the Prime Contract between [Prime Contractor] and the [Owner]. Should the Prime Contract contain no specific requirement for the resolution of disputes or should the [Owner] not be involved in the dispute, any such controversy or claim shall be resolved by arbitration pursuant to the Construction Industry Rules of the American Arbitration Association then prevailing, and judgment upon the award by the Arbitrator(s) shall be entered in any Court having jurisdiction thereof.
The prime contract between the owner and prime contractor did not require arbitration.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
First Look at Long List of AEC Firms Receiving PPP Loans
July 20, 2020 —
Tom Ichniowski & Scott Blair - Engineering News-RecordThousands of construction and design firm from all parts of the U.S. appear on lists of companies that have received federal Paycheck Protection Program forgivable loans, according to federal documents just made public.
Reprinted courtesy of
Tom Ichniowski, Engineering News-Record and
Scott Blair, Engineering News-Record
Mr. Ichniowski may be contacted at ichniowskit@enr.com
Mr. Blair may be contacted at blairs@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of