The Administrative Procedure Act and the Evolution of Environmental Law
September 19, 2022 —
Anthony B. Cavender - Gravel2GavelEnacted in 1946, the Administrative Procedure Act (APA) has provided a lasting framework for federal agency rulemaking and adjudication, as well as establishing the power of the federal courts to exercise judicial review over these actions of the federal bureaucracy. The APA is codified at 5 U.S.C. §§ 551–559, and §§ 701-706. There have been very few amendments made to the APA over these years, which indicates that Congress is reasonably satisfied with its administration and implementation.
What follows is an overview of how the APA has been used by the courts to resolve disputes involving the federal agencies, with particular attention being paid to the development of environmental law and practice. While there have been very few amendments to the statute, the courts have been free to enlarge upon the sometimes-opaque text of the APA to, in effect, change the law, even in an era when “textual fidelity” to the language of the statute is the prevalent approach.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Insurer's Denial of Coverage to Additional Insured Constitutes Bad Faith
May 21, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe insurer's unreasonable denial of a defense and indemnity to a lessor/additional insured was found to be in bad faith. Seaway Props. v. Fireman's Fund Ins. Co., 2014 U.S. Dist. LEXIS 55998 (W.D. Wash. April 22, 2014).
Seaway leased restaurant space to Ciao Bella Food, LLC. In January 10, 2010, the underlying plaintiff was on her way to the restaurant when she attempted to step down from a concrete platform between the building parking lot and the entrance to the restaurant. Seaway's lease gave Ciao Bella the right to use the common areas, including the parking lot, but did not grant Ciao Bella exclusive control over the common areas. The plaintiff suffered injuries and claimed both Ciao Bella and Seaway were liable.
Seaway's lease required Ciao Bella to maintain a CGL policy and to name Seaway as an additional insured. Ciao Bella did so by securing a policy with Fireman's Fund. Fireman's Fund had notice of the plaintiff's claim by November 2010. Seaway demanded in March 2012 that Fireman's Fund indemnify and defend it. In September 2012, two years after it first learned of the plaintiff's injury, Fireman's Fund denied coverage, asserting that Seaway was not an insured under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Litigation—Battles on Many Fronts
May 07, 2015 —
Craig Martin – Construction Contractor AdvisorWhen you are involved in construction litigation, you have battles on several fronts, including those against subcontractors, owners, insurers and the court. Shoring up your defenses on each of these fronts is imperative, or you may lose the battle or, worse yet, the war.
A recent opinion out of the Eleventh Circuit Court of Appeals (overseeing federal courts in Alabama, Florida and Georgia) Carithers v. Mid-Continent Casualty Company, illustrates the various battle fronts involved in a construction case. In this case, the Carithers (Home Owner) sued their homebuilder, Cronk Duch Miller & Associates (Contractor) in state court after discovering multiple defects with their home.
Battle Front #1—Claim Against Contractor
The Contractor and Home Owner entered into a consent judgment for approximately $90,000.00 and the Contractor assigned its claim against its insurer to the Home Owner. It is unlikely that the Contractor paid the $90,000.00 judgment. The Home Owner likely agreed not to collect on the $90,000.00 in exchange for the chance to pursue the Contractor’s claim against its insurer.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Suing A Payment Bond Surety in Different Venue Than Set Forth in The Subcontract
August 10, 2021 —
David Adelstein - Florida Construction Legal UpdatesThe venue to file a lawsuit can be an important issue for a variety of reasons, whether for convenience or the prospect of a more favorable outcome. Oftentimes, there is a venue provision in a contract that provides where the exclusive venue for any dispute arising out of the contract must be brought.
In a recent case, Southeastern Concrete Constructors, LLC v. Western Surety Company, 2021 WL 2557297 (Fla. 2d DCA 2021), dealing with a Florida Department of Transportation (FDOT) project, a subcontractor filed suit against the general contractor’s FDOT payment bond issued under Florida Statute s. 337.18. The subcontractor did not file suit against the general contractor. The subcontractor filed suit in Hillsborough County, Florida. However, the subcontract contained a venue provision requiring disputes under the subcontract to be brought in Levy County, Florida. Based on this venue provision in the subcontract, the trial court granted a motion to transfer the venue of the dispute to Levy County. This, however, was reversed on appeal.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
More on Fraud, Opinions and Contracts
February 06, 2019 —
Christopher G. Hill - Construction Law MusingsHere at Construction Law Musings, I have discussed the interaction between fraud and contracts on many occasions. Recently, I got to put my advice into action. I am counsel for the plaintiff in the matter of Environmental Staffing Acquisition Corp. v. Beamon, et. al. in the Portsmouth, VA Circuit Court and recently got a great opinion (.pdf) right on point that was recently featured in Virginia Lawyers Weekly.
The basic facts are these. My client, Environmental Staffing (En-Staff) filed a Little Miller Act claim and a claim for breach of contract for Beamon’s failure to pay for temporary staffing that En-Staff provided it at the Jeffry Wilson housing project demolition in Portsmouth, VA. Beamon then counterclaimed for fraud and breach of contract claiming that some statements to the effect that a particular supervisor was qualified along with presentation of the individual’s resume constituted fraud. My client demurred to the two fraud counts (actual and constructive).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Reservation of Rights Letter Merely Citing Policy Provisions Inadequate
February 14, 2023 —
Tred R. Eyerly - Insurance Law HawaiiIn an unpublished opinion, the Fourth Circuit affirmed the district court's finding that the insurers' reservation of rights letters did not provide a basis for denial of coverage. Stoneiedge At Lake Keowee Owners Ass'n Inc. v. Cincinnati Ins. Co., 2022 US. App. LEXIS 34292 (4th Dist. Dec. 13, 2022).
The Stoneledge AOAO sued the general contractor Marlick Home Builders, LLC and other defendants after construction of 37 units. The complaint alleged construction defects that resulted in water intrusion and other physical damage. Marlick notified its insurers, Cincinnati Insurance Company and Builders Mutual. Various reservation of rights letter were sent by the insurers.
In the underlying case, a judgment was entered against Marlick totalling approximately $1.6 million. As a judgment creditor of Marlickm, Stoneledge sued Cincinnati and Builders Mutual. The district court granted Stonelege's motion for summary judgment, primarily on the ground that the insurers failed to reserve the right to contest coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Air in There: Offices, and Issues, That Seem to Make Us Stupid
October 28, 2015 —
Eric Roston – BloombergIt's tempting to conclude from the climate change debate that all that carbon dioxide in the air is making everybody dumber.
In fact, all that carbon dioxide in the air is making everybody dumber.
Workers showed diminished cognitive functioning after spending several hours in office air that had normal levels of CO2 and chemical pollutants and ordinary ventilation, in a study published this week in Environmental Health Perspectives. Researchers tinkered with the levels of carbon dioxide and volatile organic compounds (airborne chemicals) and the amount of outside air pumped in, while the subjects did their regular work, though at a Syracuse University lab. The levels were chosen to simulate the indoor environment of conventional offices, LEED Platinum "green" buildings, and green buildings with an elevated outdoor ventilation rate ("Green+"). The 24 participants, including architects, engineers, and marketing professionals, were exposed to different conditions on different days during the six-day study, not knowing of the changes.
At 3 pm every day, the researchers administered computer-based cognitive tests of strategy-setting and focus, for example, and recorded the results and the kind of air the participants had been breathing. A day spent in the air of an extra-ventilated green building correlated with the best performance on the tests. Participants performed 61 percent better in green-building air than in conventional air, and 101 percent higher in the Green+ scenario. The research was supported in part by a United Technologies gift to Harvard's T.H. Chan School of Public Health. United Technologies, which makes building systems, wasn't involved in the experiment itself.
Read the court decisionRead the full story...Reprinted courtesy of
Eric Roston, Bloomberg
Ruling Dealing with Constructive Changes, Constructive Suspension, and the Implied Covenant of Good Faith and Fair Dealing
January 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesA dispute pending in the Armed Services Board of Contract Appeals (ASBCA) dealt with interesting legal issues on a motion to dismiss. See Appeals of McCarthy Hitt-Next NGA West JV, ASBCA No. 63571, 2023 WL 9179193 (ASBCA 2023). The dispute involves a contractor passing through subcontractor claims due to impacts caused by the COVID-19 pandemic and the government’s response to the pandemic. More particularly, the claim centers on the premise that the government “failed to work with [the contractor] in good faith to develop a collaborative and cooperative approach to manage and mitigate the impacts and delays arising from the COVID-19 pandemic.” See Appeals of McCarthy Hitt.
The contractor (again, submitting pass through claims from subcontractors) claimed: (a) constructive changes to the contract entitling it to an equitable adjustment under the Changes clause of Federal Acquisition Regulation (F.A.R.) 52.243-4; (b) construction suspensions of the contractor’s work entitling it to an equitable adjustment under the Suspensions of Work clause of F.A.R. 52-242-14; and (c) the government breached the implied covenant of good faith and fair dealing. Each of these legal issues and theories will be discussed below because they are need-to-know legal issues. Keep these legal issues in mind, and the ASBCA’s ruling on the motion to dismiss as its analysis may demonstrate fruitful in other applications.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com