One Way Arbitration Provisions are Enforceable in Virginia
October 07, 2019 —
Christopher G. Hill - Construction Law MusingsHere at Construction Law Musings, I’ve discussed arbitration clauses (pros and cons) as well as the fact that in our fair Commonwealth, contracts are enforced as written (for better or worse). A case out of the Eastern District of Virginia takes both of these observations and uses them to make it’s decision.
In United States ex rel. Harbor Constr. Co. v. T.H.R. Enters., the Newport News Division of the Eastern District of Virginia federal court considered the following provision and it’s enforceability:
At CONTRACTOR’s sole election, any and all disputes arising in any way or related in any way or manner to this Agreement may be decided by mediation, arbitration or other alternative dispute resolution proceedings as chosen by CONTRACTOR…. The remedy shall be SUBCONTRACTOR’s sole and exclusive remedy in lieu of any claim against CONTRACTOR’s bonding company pursuant to the terms of any bond or any other procedure or law, regardless of the outcome of the claim. The parties further agree that all disputes under this Subcontract shall be determined and interpreted pursuant to the laws of the Commonwealth of Virginia….
This provision was the crux of the argument made by T. H. R., the Defendant, in making a motion to dismiss or stay the lawsuit for payment filed by Harbor Construction. As background, Harbor Construction contracted with T. H. R. to perform work at Langley Air Force Base. Alleging non-payment of approximately $250,000.00, Harbor filed a complaint with three counts, one under the Federal Miller Act, one for breach of contract, and a third for unjust enrichment.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Specification Challenge; Excusable Delay; Type I Differing Site Condition; Superior Knowledge
January 02, 2024 —
David Adelstein - Florida Construction Legal UpdatesAn Armed Services Board of Contract Appeals dispute, Appeal of L.S. Black-Loeffel Civil Constructors JV, ASBCA No. 62402, 2023 WL 5827241 (ASBCA 2023), involved which party bore liability for delay—the federal government or the prime contractor–based on various legal theories. Without detailing the factual details, a number of interesting legal issues were raised in this dispute including (1) a defective specification challenge, (2) excusable delay, (3) Type I differing site condition, and (4) superior knowledge. These legal issues are discussed below.
1. Specification Challenge (Defective Specifications)
The contractor claimed that the government’s specifications were defective in regard to a thermal control plan. The government countered that the specifications were not design specifications but performance specifications. The specifications were performance based because they did not tell the contractor how to achieve the performance-based criteria.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Crumbling Roadways Add Costs to Economy, White House Says
July 16, 2014 —
Roger Runningen – BloombergMore than two-thirds of U.S. roadways are in need of repair and the poor condition of the nation’s transportation network results in billions in extra costs, according to a White House report.
The report was released today in conjunction with President Barack Obama’s campaign to pressure Congress for a deal to replenish the Highway Trust Fund. The fund, supplied by fuel taxes, is heading toward insolvency as early as next month, jeopardizing jobs and projects during the peak construction season.
Crumbling roads and bridges cut into economic growth, by increasing transportation costs and delaying shipments, according to the report.
“A well-performing transportation network keeps jobs in America, allows businesses to expand, and lowers prices on household goods to American families,” said a 27-page report by the Council of Economic Advisers and National Economic Council.
Read the court decisionRead the full story...Reprinted courtesy of
Roger Runningen, BloombergMr. Runningen may be contacted at
rrunningen@bloomberg.net
Attorneys' Fees Awarded "Because Of" Property Damage Are Covered by Policy
August 29, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe Ninth Circuit upheld the District Court's decision that the insured Association of Apartment Owners was entitled to coverage for the attorneys' fees incurred [prior post here].Assoc'n of Apartment Owners of the Moorings, Inc. v. Dongbu Ins. Co., Ltd., 2018 U.S. App. LEXIS 20251 (9th Cir. July 20, 2018).
The District Court for the District of Hawaii granted summary judgment to the AOAO, requiring Dongbu to indemnify the AOAO for an award of attorney's fees that an arbitrator ordered the AOAO to pay to the underlying claimants. The claimants prevailed on a claim that their condominium unit incurred water damage due to a common roof leak. Dongbu's policy required it to reimburse those sums that the AOAO was legally obligated to pay as damages because of property damage. The AOAO became legally obligated to pay the claimants' fees once the state court confirmed the arbitration award. Further, the water damage to the home constituted covered property damage under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Owner’s Slander of Title Claim Against Contractor Recording Four Separate Mechanics Liens Fails Under the Anti-SLAPP Statute
February 01, 2021 —
Garret Murai - California Construction Law BlogMost mechanics lien actions follow a pretty standard process:
- A mechanics lien claimant, either a contractor subcontractor, material supplier, or laborer, performs work but is not paid;
- Mechanics lien claimant records a mechanics lien on the property in which work was performed; and
- Within 90 days thereafter files suit to foreclose on the mechanics lien.
Sometimes, either before or after a mechanics lien claimant files suit, the owner will record a mechanics lien release bond, in which case mechanics lien claimant files suit against the release bond.
But what if a mechanics lien claimant records a mechanics lien, the owner records a mechanics lien release bond, and the mechanics lien claimant records three different but identical mechanics liens thereafter? Is this even legal?
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Kiewit and Two Ex-Managers Face Canada Jobsite Fatality Criminal Trial
October 12, 2020 —
Scott Van Voorhis - Engineering News-RecordCanada appears set to try a rare criminal case against a major company—U.S. contractor Kiewit Corp.—for a workplace fatality stemming from a more than decade-old accident on a remote British Columbia hydroelectric project that killed a 24-year-old field employee.
Reprinted courtesy of
Scott Van Voorhis, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Federal District Court Grants Preliminary Approval of Settlement on Volcano Damage
September 13, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted preliminary approval of the class action settlement reached on behalf of insureds who suffered property damage due to the 2018 Kilauea eruption on the Big Island. Aquilina v. Certain Underwriters at Lloyd's London, 2021 U.S. Dist. LEXIS 152614 (D. Haw. Aug. 13, 2021).
After destruction of their homes due to lava flow, plaintiffs sued various insurers and agents as a putative class action. Plaintiffs claimed they purchased surplus lines policies brokered and underwritten by various defendants. The policies each contained an exclusion for the peril of lava flow, which plaintiffs claimed rendered them worthless or unsuitable given that their properties were located in a high-risk lava zone.
Plaintiffs alleged that defendants breached obligations under the Hawaii Surplus Lines Act, which required that surplus lines insurers conduct a diligent search for other available coverage before placing a homeowner with surplus lines coverage. Plaintiffs alleged defendants should have advised them of the availability of lava-damage coverage through the Hawaii Property Insurance Association (HPIA), a statutorily created association of admitted insurers established in part in response to Kilauea's eruption patterns, which made the private insurance market less likely to Insure certain high-risk areas.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
'There Was No Fighting This Fire,' California Survivor Says
September 14, 2020 —
The Associated Press (Brian Melley & Terence Chea) - BloombergBerry Creek, Calif. (AP) -- John Sykes built his life around his cabin in the dense woods of Northern California. He raised his two children there, expanded it and improved it over time and made it resilient to all kinds of disaster except fire.
So when the winds started howling Tuesday and the skies became so dark from smoke that he had to turn on his lights at midday, he didn’t hesitate to leave it all behind in an instant before any evacuation order.
With the disaster two years ago in nearby Paradise, in which 85 people perished in the deadliest and most destructive fire in modern state history, still fresh on his mind, Sykes got his wife and a friend into his car and left with only a change of clothes each.
“All I could do is look in the rear view mirror and see orange sky and a mushroom cloud and that told me it was hot and to keep going,” Sykes said Friday. “It was a terrifying feeling.”
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg