Kushner Company Files Suit Against Jersey City Over Delays to Planned Towers
July 10, 2018 —
Associated Press - Engineering News-RecordJERSEY CITY, N.J. (AP) — Jared Kushner's family company has filed a lawsuit against a New Jersey city, saying it forced the delay of a major twin-tower project due to "political animus" toward President Donald Trump.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR staff may be contacted at
ENR.com@bnpmedia.com
ABC Announces Disaster Relief Efforts and Resources Following Hurricane Milton
October 15, 2024 —
ABC - Construction ExecutiveHURRICANE RELIEF
Florida, Georgia, South Carolina, North Carolina, Virginia and Tennessee were hit with
Hurricane Helene, and now Florida is facing additional damage from
Hurricane Milton, which is expected to make landfall on Wednesday, Oct. 9. Damages from Helene have already been catastrophic, and our hearts and prayers go out to all currently affected and those who may be in the path of Milton. Florida Gov. DeSantis has
declared a state of emergency for 51 counties ahead of this impending storm.
Donate to the ABC Cares Foundation via the online portal.
The ABC Florida East Coast chapter and the ABC Cares Foundation Inc. are committed to assisting communities impacted by Hurricanes Helene and Milton. 100% of donations made to the ABC Cares Foundation—an IRS 501(c)(3)—for this purpose will be restricted, directly supporting regional needs, and are 100% tax deductible.
Donate to the American Red Cross through ABC’s donation portal.
Your Red Cross disaster relief gift will help people whose lives have been upended by wildfires, storms, floods and countless other crises. This custom website tracks donations by the ABC community and can be dedicated to a friend or loved one.
Donate
Reprinted courtesy of
ABC, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Daily Reports – The Swiss Army Knife of Project Documentation
June 08, 2020 —
Christopher A. Henry - ConsensusDocsProject “Daily Reports” are some of the most important, yet overlooked aspects of a construction project. These reports serve many beneficial roles such as holding parties accountable to their obligations, providing the basis for an as-built schedule, recording manpower, documenting site conditions, and recording any other important and relevant information that happened on the job site that day. Daily reports can also provide information to help with claims or disputes that may arise in the future, such as noting weather delays, providing backup for future delay claims, and providing information to dispute claims made against your company. Finally, daily reports also serve as a useful communication tool during the project and a source of real time information for parties that want to know how the work is commencing on a day to day basis. Because daily reports are the “Swiss army knife” of project documentation, it is extremely important that a contractor puts for its best effort when creating them.
It is no secret that a construction project can become more chaotic as the schedule progresses. Unfortunately, when that is the case, the effort put into creating these reports drops off and sometimes the responsibility of creating such reports is thrown aside altogether. I can speak from experience. Prior to entering the practice of law, I was a project engineer for a general contractor in Atlanta. As an engineer in the field, one of my many responsibilities was to enter the daily reports. Based off this experience, below are some thoughts on how to prepare useful daily reports.
1. Check the contract. The contract you entered may set forth specific requirements for the daily reports, such as where to file them, the required format, and specific information that must be included. Complying with contractual requirements is necessary for a successful project. One word of caution for subcontractors, a subcontract will often incorporate the prime contract. If that is the case, be sure to check the prime contract for any specific language relating to daily reports.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher A. Henry, Jones Walker LLP Mr. Henry may be contacted at
chenry@joneswalker.com
Use Your Instincts when Negotiating a Construction Contract
August 07, 2018 —
Christopher G. Hill - Construction Law MusingsI have often discussed the more “mechanical” aspects of contract negotiation and drafting here at Construction Law Musings. However, there is another, less objective (possibly) and more “feel” oriented aspect to construction contracting that can have as big an impact on your construction project. What am I talking about? Your instinct as a construction professional when looking the other party in the eye and getting a feel for the company or individual with whom you are contracting.
Why is this so important? Firstly, and this is a truism, no matter how well drafted your construction contract is (and it should be well drafted and reviewed by an experienced construction attorney), if the other party wishes to “play games” and not honor the terms of that contract, you could still very well end up in litigation with the attendant frustration and expense. Having a great looking, well thought out and at least reasonably “fair” construction contract may make the litigation process somewhat less painful but it does not completely avoid the risk of litigation. If the other party or parties to the contract decide not to pay you or perform as they promised, you are left to enforce whatever contract you have in place.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Environmental Roundup – May 2019
July 09, 2019 —
Anthony B. Cavender - Gravel2GavelFederal Courts of Appeal
Dam Claims Collapse
On May 7, 2019, the U.S. Court of Appeals for the Eleventh Circuit decided the case of Navelski, et al. v. International Paper Company. After a major storm, a dam constructed by International Paper to serve the operations of its local paper mill, was breached, releasing millions of gallons of water into a nearby creek resulting in the flooding of many homes located downstream from the creek. IP was sued by the homeowners in a class action, alleging negligence and strict liability for conducting an abnormally dangerous activity. The trial court dismissed the strict liability claim, and the jury found IP was not negligent in the operation of the dam. On appeal, the court upheld the jury verdict, agreeing that the verdict was supported by the evidence heard by the jury. The appeals court also agreed that the strict liability claim was properly dismissed as a matter of law because the operation of this dam was not an abnormally dangerous activity under Florida law. The plaintiffs had also argued that the jury should not have been advised that the home county, Escambia County, has applied for a FEMA grant which apparently made the case that some of the downstream homes were naturally prone to flooding. A redacted version of the application was allowed to be shown to the jury, but the appeals court held that the plaintiffs had not demonstrated that the court ruling was prejudicial.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
2021 California Construction Law Update
December 29, 2020 —
Garret Murai - California Construction Law BlogThis Christmas looks to be a Blue Christmas as the nation grapples with rising infection, hospitalization and death rates due to COVID. But there’s always 2021 to look forward to, which, of course, also means new laws impacting the construction industry.
Due to COVID there were two unscheduled breaks during the second half of the 2019-2020 legislative session as legislators sheltered-in-place. As a result, there were fewer bills introduced and enacted than in previous legislative session. A total of 2,223 bills were introduced in 2020 compared to 2,625 bills in 2019, of which 428 bills made it to the Governor’s desk, and 372 were signed into law.
Among the bills signed into law were bills, unsurprisingly, related to COVID. In addition, the 2020 legislative session saw the passage of legislation creating a new licensing classification for residential renovation contractors, new laws expanding and clarifying when prevailing wages are required to be paid, and legislation extending the period during which seniors can cancel certain contracts.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Utah Becomes First State to Enact the Uniform Commercial Real Estate Receivership Act
March 29, 2017 —
David Leta - Snell & Wilmer Real Estate Litigation BlogOn March 25, Utah became the first state to enact the Uniform Commercial Real Estate Receivership Act (“UCRERA”) which was drafted by the National Conference of Commissioners on Uniform State Laws (the “Conference”) and adopted by the Conference at its annual meeting in July 2015. The Utah Uniform Commercial Real Estate Receivership Act, (the “Utah Act”) mirrors UCRERA and applies to all commercial real property receiverships that are filed in the Utah District Courts on and after May 9, 2017.
The Utah Act provides both substantive and procedural guidance in an area of law that historically has been marked by inconsistency and uncertainty. This new law not only will provide judges, lenders and other receivership constituents with much needed instruction about their respective rights and responsibilities in commercial receivership proceedings, but it also is likely to reduce the cost and increase the predictability of these receiverships in Utah.
Read the court decisionRead the full story...Reprinted courtesy of
David Leta, Snell & WilmerMr. Leta may be contacted at
dleta@swlaw.com
Insurer Springs a Leak in Its Pursuit of Subrogation
August 21, 2023 —
Katherine Dempsey - The Subrogation StrategistIn Nationwide Prop & Cas. Ins. Co. v. Fireline Corp., No. 1:20-cv-00684, 2023 U.S. Dist. LEXIS 104241, the United States District Court for the District of Maryland (District Court) considered whether the events giving rise to the plaintiff’s claims fell within the scope of a previously formed agreement, thereby rendering the plaintiff’s claims subject to the agreement’s time limitation and waiver of subrogation provisions. The District Court found that the claims fell within the scope of the agreement.
The plaintiff, Nationwide Property & Casualty Insurance Company (Insurer), provided property insurance to Maple Lawn Homeowners Association, Inc. (Maple Lawn) for common property located in Fulton, Maryland, including a community center (the Subject Premises). On January 18, 2018, Maple Lawn entered into an Inspection Agreement (the Agreement) with defendant, Fireline Corporation (Fireline), wherein Fireline agreed to provide:
- annual fire alarm inspection and testing services,
- quarterly sprinkler inspection and testing, and
- annual portable fire extinguisher testing and inspection.
Read the court decisionRead the full story...Reprinted courtesy of
Katherine Dempsey, White and Williams LLPMs. Dempsey may be contacted at
dempseyk@whiteandwilliams.com