Contractor Succeeds At the Supreme Court Against Public Owner – Obtaining Fee Award and Determination The City Acted In Bad Faith
September 20, 2021 —
Lindsay T. Watkins - Ahlers Cressman & Sleight PLLCA contractor won a rare but much-deserved victory at the Supreme Court on July 8, 2021 in Conway Construction Co. v. City of Puyallup, 197 Wn.2d 825, 490 P.2d 221 (2021). The case, which involved an aggressive stance by a public owner:
- confirmed that the public owner bears the burden of demonstrating a termination for default is justified,
- reaffirmed the requirement to provide an opportunity to cure, and
- rejected the public owner’s attempts to escape its own contract language that the contractor relied upon.
John Ahlers and Lindsay Watkins of Ahlers Cressman and Sleight and Jamie Becker of Osborne Construction submitted the Amicus Brief for the Associated General Contractors (AGC) of Washington in support of Conway to the Supreme Court.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay T. Watkins, Ahlers Cressman & Sleight PLLCMs. Watkins may be contacted at
Lindsay.Watkins@acslawyers.com
Quick Note: October 1, 2023 Changes to Florida’s Construction Statutes
November 13, 2023 —
David Adelstein - Florida Construction Legal UpdatesEffective October 1, 2023, there were changes to Florida’s statutory scheme dealing with construction projects. This includes Florida’s Lien Law. A copy of these changes can be found below which identify additions in blue and deletions with strikethroughs. No different than before, if you have questions or concerns as to your statutory rights on a construction project, do the prudent thing, consult a construction lawyer. A construction lawyer can help you understand changes to the applicable statutory scheme or how the statutory scheme pertains to your rights. This is important because you want to make sure you understand statutory changes that apply to your work and rights.
A noteworthy change, bolded in blue below, is that there is now a basis to lien for a contractor performing construction management services “which include scheduling and coordinating construction and preconstruction phases for the construction project, or who provides program management services”:
Fla. Stat. s. 713.01 (8) “Contractor” means a person other than a materialman or laborer who enters into a contract with the owner of real property for improving it, or who takes over from a contractor as so defined the entire remaining work under such contract. The term “contractor” includes an architect, landscape architect, or engineer who improves real property pursuant to a design- build contract authorized by s. 489.103(16). The term also includes a licensed general contractor or building contractor, as those terms are defined in s. 489.105(3)(a) and (b), respectively, who provides construction management services, which include scheduling and coordinating preconstruction and construction phases for the construction project, or who provides program management services, which include schedule control, cost control, and coordinating the provision or procurement of planning, design, and construction for the construction project.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Not Pandemic-Proof: The Ongoing Impact of COVID-19 on the Commercial Construction Industry
December 06, 2021 —
George B. Green Jr. - Construction ExecutiveThe impact of COVID-19 has been felt in nearly every industry and arena across the country, with the exception of construction—or so that is the general perception. Perceptions are often wrong though, and this one is no different. The truth is that the construction industry has been hit just as hard, if not harder, than every other industry.
As the COVID-19 pandemic struck in the spring of 2020, construction projects plowed forward full steam ahead. Roadwork seemed to increase and developers continued to systematically acquire property and initiate large-scale projects. Perhaps it was these observations that led many to the conclusion that construction was pandemic-proof as the rest of society attempted to cobble together something that vaguely resembled a normal business year. But the construction industry has endured many challenges over the last 18 months, and unfortunately, the challenges do not appear to be evaporating anytime soon.
The industry has been primarily affected in the areas of scheduling, manpower and permitting, which has ultimately affected pricing. The entire way jobs are scheduled has been turned upside down. The supply chain issues that many have experienced for everyday household items have hit the construction industry as well.
Reprinted courtesy of
George B. Green Jr., Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Green may be contacted at
ggreen@wwhgd.com
Fort Lauderdale Partner Secures Defense Verdict for Engineering Firm in High-Stakes Negligence Case
June 10, 2024 —
Lewis Brisbois NewsroomFort Lauderdale, Fla. (June 3, 2024) - Fort Lauderdale Managing Partner Cheryl Wilke recently secured a defense verdict for civil engineering firm Gulfstream Design Group and its owner, Matthew Lahti, in a high-stakes professional negligence case in which the plaintiff sought more than $20 million. The verdict by a six-person jury in St. Augustine followed a nine-day trial.
The case involved a 100-acre tract of land in St. Johns County, Florida, owned by the plaintiff, Cynthia Taylor. The land was zoned for rural farming, and she wished to sell the property for development. She entered into a contract with Southeast Georgia Acquisitions (“SGA”) to sell the property with the goal of creating a 200-home subdivision. SGA hired Doug Burnett as land use counsel and our client, Gulfstream Design Group, as the civil engineer to design the project.
In St. Johns County, only a property owner can submit a Planned Unit Development Plan (“PUD”) for the purpose of rezoning. In this case, Burnett and Gulfstream created text and a proposed map for the PUD and submitted it for approval. The PUD was approved first at the staff level, then by planning and zoning and then by the County Commission. All the services were provided prior to closing with PUD approval, a condition of sale.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Charles Eppolito Appointed Vice-Chair of the PBA Judicial Evaluation Commission and Receives Prestigious “President’s Award”
November 30, 2020 —
Charles Eppolito, III - White and Williams LLPPartner Charles (Chuck) Eppolito, III has been appointed as a Vice-Chair of the Pennsylvania Bar Association (PBA) Judicial Evaluation Commission. His three-year term begins immediately and will expire September 30, 2023. The PBA Judicial Evaluation Commission is responsible for developing and implementing a judicial evaluation process for appellate judicial candidates in the Commonwealth of Pennsylvania. As Vice-Chair, Chuck will oversee reviewing the investigative panel's report, interviewing each candidate, discussing qualifications and reaching an agreement upon and issuing a rating for each candidate for appellate judicial office.
Chuck has a long history of involvement with the 25,000-member organization, serving as PBA Secretary from 2007 to 2010, Chair of the House of Delegates from 2011 to 2013 and President from 2018 to 2019. Most recently, it was announced that Chuck is a recipient of a PBA “President’s Award” for his dedication and commitment to fulfilling the mission of the PBA COVID-19 Task Force. The award will be presented during the virtual PBA Awards Luncheon on Thursday, November 19, 2020.
Read the court decisionRead the full story...Reprinted courtesy of
Charles Eppolito, III, White and Williams LLPMr. Eppolito may be contacted at
eppolitoc@whiteandwilliams.com
Home Prices in 20 U.S. Cities Increase at Slower Pace
February 25, 2014 —
Victoria Stilwell – BloombergHome prices in the U.S. climbed at a slower pace in the year through December, pointing to a moderation in the market that will help keep more properties within reach for prospective buyers.
The S&P/Case-Shiller index of property values in 20 cities rose 13.4 percent from December 2012 after increasing 13.7 percent in the year ended in November, the group said today in New York. It was the first deceleration since June. The gain matched the median estimate of 33 economists surveyed by Bloomberg.
Price appreciation is slowing as rising mortgage rates combined with harsh winter weather to cool home purchases over the past few months. Smaller increases mean more homes will remain affordable as the labor market improves, helping maintain the rebound in residential real estate that has boosted growth.
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, BloombergMs. Stilwell may be contacted at
vstilwell1@bloomberg.net
Contractor Sues Supplier over Defective Products
June 28, 2011 —
CDJ STAFFFast Track Specialties has sued RJF International after needing to remove wall protection units at Methodist West Houston Hospital, according to an article in the Houston Chronicle. Fast Track claims that contractors had to disconnect gas, water, and electric from the area to facilitate removal of corner guards, handrails, and crash guards from the hospital. This cost the contractor more than $135,000.
Fast Track is claiming that RJD International has committed breach of contract, breach of warranty, and negligent representation.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Dispute Resolution Provision in Subcontract that Says Owner, Architect or Engineer’s Decision Is Final
March 29, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn subcontracts, it is not uncommon to see a provision that says something to the effect:
Should any dispute arise between the parties respecting the true construction or interpretation of the Plans, Specifications and/or the Contract Requirements, the decision of the Owner or the Owner’s designated representative as set forth in the General Contract shall be final.
This is a provision in a subcontract dealing with dispute resolution, typically when there is a dispute as to whether the subcontractor is performing extra-contractual or base contract work regarding an “interpretation of the Plans, Specifications, and/or the Contract Requirements.” It is not uncommon for there to be a dispute as to whether certain work is within the subcontractor’s scope of work or outside the subcontractor’s scope of work and subject to a change order.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at