Contractors Must Register with the L&I Prior to Offering or Performing Work, or Risk Having their Breach of Contract Case Dismissed
March 27, 2023 —
Jill Guingcangco - Ahlers Cressman & Sleight PLLCThe Washington State Legislature has an interest in protecting the public from “unreliable, fraudulent, financially irresponsible, or incompetent contractors” (RCW 18.27.140), which is why contractors are required to register with the Department of Labor and Industries (“L&I”) before advertising, offering to do work, or performing any work as a contractor. RCW 18.27.020. Accordingly, if a contractor brings an action for the collection of compensation or sues for breach of contract for work they performed, that individual is required to allege and prove that, at the time they performed the work, they were a registered contractor. RCW 18.27.080.
In
Dobson v. Archibald,1 Dobson worked as a longshoreman, but also simultaneously performed home repair work for pay during her off time. Dobson never registered as a contractor with L&I. Dobson acquired customers for her home repair work through a referral process. Dobson was referred to Archibald through a mutual friend who Dobson performed some home repair work for. Archibald subsequently hired Dobson to refinish the hardwood floors in Archibald’s home.
Read the court decisionRead the full story...Reprinted courtesy of
Jill Guingcangco, Ahlers Cressman & Sleight PLLCMs. Guingcangco may be contacted at
jill.guingcangco@acslawyers.com
HUD Homeownership Push to Heed Lessons From Crisis, Castro Says
January 14, 2015 —
Clea Benson – BloombergNow that regulators have fixed the worst abuses of the 2008 credit crisis, it’s time to start promoting homeownership again, according to the top U.S. housing official.
The Department of Housing and Urban Development will do its part, spending this year focusing on ways to help more Americans buy homes, HUD Secretary Julian Castro said today in a Washington speech outlining the agency’s priorities.
Read the court decisionRead the full story...Reprinted courtesy of
Clea Benson, BloombergMs. Benson may be contacted at
cbenson20@bloomberg.net
Colorado Court of Appeals Finds Damages to Non-Defective Property Arising From Defective Construction Covered Under Commercial General Liability Policy
December 20, 2012 —
HEIDI GASSMAN, HIGGINS, HOPKINS, MCLAIN & ROSWELLThe recently decided case of Colorado Pool Systems, Inc. v. Scottsdale Insurance Company (Colo. Ct. App. 10CA2638, October 25, 2012), confirms that absent specific exclusions in the policy, a commercial general liability (“CGL”) policy covers damages to non-defective property arising from a builder’s own defective workmanship.
Colorado Pool Systems, Inc. (“Colorado Pool”) was hired as a subcontractor to install a swimming pool at Founders Village Pool and Community Center (“Founders Village”) in Castle Rock, Colorado. After the concrete shell of the pool was placed, some of the rebar frame was found to be too close to the surface. Founders Village demanded that Colorado Pool remove and replace the pool, and Colorado Pool contacted its insurance carrier, Scottsdale Insurance Company (“Scottsdale”), with which Colorado Pool held a CGL policy. After inspecting the pool, Scottsdale’s claims adjuster stated that the insurance policy would cover losses associated with removing and replacing the pool.
Read the court decisionRead the full story...Reprinted courtesy of
Heidi Gassman, Higgins, Hopkins, McLain & Roswell, LLC.Ms. Gassman can be contacted at
gassman@hhmrlaw.com
Congratulations to San Diego Partner Alex Giannetto and Senior Associate Michael Ibach on Settling a Case 3 Weeks Into a 5-Week Trial!
April 15, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPPartner Alex Giannetto and Senior Associate Michael Ibach of BWB&O’s San Diego office started a trial in San Diego set to last at least five weeks. Plaintiffs alleged causes of action of negligence, trespass and nuisance against BWB&O’s client, arguing the owner/property manager did not properly handle alleged overwatering of the front yard, allegedly resulting in a landslide impacting 8 homes on a City slope in Carlsbad. Cross-Complainant City alleged independent negligence to fix the slope it owned and controlled as well as various indemnity-based causes of action against BWB&O’s client. Plaintiffs claimed over $24 million in damages, while Cross-Complainant placed sole blame for the incident on BWB&O’s client around $6 million.
Heading into trial, it was made clear that neither Plaintiffs nor Cross-Complainant would accept anything less than 7-figures to settle BWB&O’s client out of the case. In the first week of trial, BWB&O was able to leverage motions in limine, opening statements, and cross-examinations to secure a dismissal of three of the four causes of action alleged by Plaintiff that were associated with pain & suffering. In the second week of trial, BWB&O secured a dismissal of Cross-Complainant’s negligence cause of action paving the way for a settlement with Plaintiffs. Leveraging the threat of a non-suit when Plaintiffs rested, BWB&O secured resolution of Plaintiffs’ complaint for a fraction of what had previously been sought. Finally, BWB&O was able to secure a dismissal of the remaining indemnity-based causes of action in the cross-complaint and fully extract the client from the matter.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Benefit of the Coblentz Agreement and Consent Judgment
August 26, 2024 —
David Adelstein - Florida Construction Legal UpdatesIf you are not familiar with the concept of what is commonly known as a Coblentz agreement relative to an insurance coverage dispute, review these prior postings (
here and
here and
here). This is a good-to-know agreement if you are a claimant and need to consider an avenue of collection if the insured’s carrier denies coverage out of the gate (meaning the carrier has denied both the duty to defend and the duty to indemnify).
A recent Eleventh Circuit Court of Appeals opinion demonstrates the Coblentz agreement concept. In Barrs v. Auto-Owners Ins. Co., 2024 WL 3673089 (11th Cir. 2024), an owner asserted a construction defect claim against its contractor. The owner hired the contractor to deconstruct a building and the contractor hired a demolition subcontractor. The owner noticed work was not being performed and materials (e.g., lumber) were missing; the demolition subcontractor had stolen materials. The subcontractor was terminated, and the owner claimed the contractor’s negligence allowed the theft and delayed his project. The contractor’s commercial general liability (CGL) insurer notified the insured-contractor that coverage did not exist and refused to defend the contractor. The owner sued the contractor under various theories of liability. The owner and contractor entered into a settlement agreement (i.e., the Coblentz agreement) where the contractor “admitted liability in the amount of $557,500.00….A consent judgment was entered against [the contractor] that closely tracked the settlement agreement but did not indicate which portion of the damages award was attributed to which claims. The agreement also assigned [owner] and all of [the contractor’s] rights to claim coverage and to recover available funds under [the contractor’s CGL policy].”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Chinese Millionaire Roils Brokers Over Shrinking Mansion
August 20, 2014 —
John Gittelsohn and Karen Gullo – BloombergMillionaire Hiroshi Horiike spent two years searching California for a dream home, one grander than any he could find in his native China.
After visiting more than 80 properties in the Los Angeles area with an agent from Coldwell Banker, Horiike paid $12.25 million in cash for a four-bedroom, six-bath Tuscan-style mansion with a swimming pool, spa and guest house on 5.1 acres (2.1 hectares) overlooking the Pacific Ocean.
There was just one catch. After settling in, Horiike found the Malibu home had less living space than he’d been told -- a third less. It had 9,434 square feet (876 square meters) instead of the 15,000 square feet shown in marketing brochures from the seller’s agent, who also worked with Coldwell Banker.
Mr. Gittelsohn may be contacted at johngitt@bloomberg.net; Ms. Gullo may be contacted at kgullo@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn and Karen Gullo, Bloomberg
Reminder: In Court (as in life) the Worst Thing You Can Do Is Not Show Up
September 28, 2017 —
Christopher G. Hill - Construction Law MusingsAs long time (and possibly recent) readers of Construction Law Musings know, I am a Virginia Supreme Court Certified Mediator. In that capacity, I spend quite a bit of time sitting in general district court courtrooms in places like Goochland and Caroline Counties “court sitting” awaiting a referral from the judge of a case with parties ready and willing to take advantage of the mediation process.
As I sit there wearing my mediator “hat,” I see case after case be called for the first return date. Without fail, several cases are called where the defendant fails to appear after being served with process. There are even a case or two where the plaintiff (the party that picked the return date in the first place) fails to appear. In the first instance, where the defendant doesn’t appear, the judge almost inevitably enters a judgment for the amount sued for by the plaintiff. In the latter instance, the case is dismissed without prejudice to the plaintiff with a shake of the head by the judge at the wasted time and filing fee. This post focuses on the first case.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Offices of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
No Coverage for Defects in Subcontrator's Own Work
February 11, 2019 —
Tred R. Eyerly - Insurance Law HawaiiDamage to the concrete floor installed by the insured subcontractor was not property damage and thus not covered under the insured's CGL policy. Kalman Floor Co. v. Old Republic Gen. Ins. Corp., 2019 U.S. Dist. LEXIS 3319 (D. Colo Jan. 8, 2019).
In 2007, Kalman Floor Co. was subcontracted to construct over 158,000 square feet of concrete flooring for a cold storage facility. The concrete floor was completed in late 2008. In late 2009, the contractor notified Kalman that pockmarks, or "pop-outs," were visible on the concrete flooring. The only damage to tangible property in the facility caused by the pop-outs was the concrete flooring itself.
On January 31, 2009, Old Republic issued a general liability policy to Kalman for one year. The policy excluded for damage to "your work," defined as "work or operations performed by you or on your behalf." Old Republic denied coverage for damage to the concrete floor. Kalman sued, seeking a declaration that the exclusions did not bar coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at