Top 10 Hurricane Preparedness Practices for Construction Sites
September 25, 2018 —
Andrew Gilbert - Construction ExecutiveLast year, the National Oceanic and Atmospheric Administration (NOAA) recorded that the North Atlantic saw the third highest number of major hurricanes to date. North America alone saw three tropical storms and four hurricanes make landfall, the most since 2005.
As the 2018 hurricane season takes shape (running from June 1 to Nov. 30), it’s imperative to begin construction site hurricane planning efforts early and to be as prepared as possible prior to any storm. Preparing for a storm can help ensure the safety of not only project and onsite teams, but also of the surrounding communities.
1. DEVELOP AND REVIEW A HURRICANE PREPAREDNESS AND SAFETY PLAN
Prior to hurricane season, make sure the project contractor has provided the team with a hurricane preparedness and safety plan. Review this plan with the entire team and the owner. This document outlines the exact timeline and steps the contractor will take to safely secure the project site in the event of a storm. The integrated process is especially important when dealing with renovation projects, exterior upgrades or projects that connect new construction to existing facilities.
Reprinted courtesy of
Andrew Gilbert, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Gilbert may be contacted at
andrew.gilbert@cbre.com
The Job is Substantially Complete, the Subcontract was Never Signed, the Subcontractor Wants to be Paid—Now What?
July 28, 2016 —
John P. Ahlers – Ahlers & Cressman PLLCA recent case in North Carolina illustrates the types of problems created when a general contractor accepts a subcontractor’s bid and then allows the subcontractor to perform the work without obtaining a signed subcontract.[i] In this case, the general contractor (Choate Construction Company – “Choate”) accepted a bid from a foundation subcontractor (Southeast Caissons, LLC – “SEC”). Choate sent the subcontract to SEC. SEC provided its changes in a “Proposed Addendum” to the subcontract stating, “[SEC] hereby accepts the terms of the attached Subcontract, subject to and conditioned upon Choate[’s] acceptance of the terms set forth in this Addendum[.]” After that, Choate called SEC and exchanged emails concerning the subcontract terms, but did not reach an agreement. SEC then performed its subcontract and sought payment, and acknowledged it had not signed the subcontract. Choate agreed it owed SEC something, but refused to pay because SEC did not have a signed subcontract, asserting the subcontract was not binding on Choate.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Irvine Partner Cinnamon J. Carr and Associate Brittney H. Aquino Prevail on Summary Judgment
June 17, 2024 —
Linda Carter - Kahana FeldCongratulations to Irvine Partner Cinnamon J. Carr and Associate Brittney H. Aquino for Prevailing on a Motion for Summary Judgment!
Irvine Partner Cinnamon J. Carr and Associate Brittney H. Aquino prevail on summary judgment in a slip and fall case venued in Riverside County!
Plaintiff filed a lawsuit alleging negligence against Kahana Feld’s client, a grocery store with over 50 stores throughout Southern California. Prior to Plaintiff’s fall, security cameras captured footage of a third-party customer picking up a case of water bottles near the entrance of the store. The customer tilted the case and water streamed to the floor. The customer then returned the leaky case to the pallet, picked up another case of water, and walked away. Approximately a minute and 10 seconds later, Plaintiff walked through the area, slipping on the spilled water.
Read the court decisionRead the full story...Reprinted courtesy of
Linda Carter, Kahana FeldMs. Carter may be contacted at
lcarter@kahanafeld.com
Insuring Lease/Leaseback Projects
August 19, 2024 —
David G. Jordan & Jeffrey J. Vita - Saxe Doernberger & Vita, P.C.Overview
Several states utilize a unique statutory mechanism to allow school districts to finance the construction of public-school facilities. This arrangement (known as a “lease-leaseback agreement”) allows a school district to lease property to a contractor/developer, who then constructs or renovates a school facility on the property. Once the work is completed, the contractor/developer leases the school building back to the school district. The school district then makes lease payments over time, often many years, which can be structured in various ways to spread out the cost of construction. The arrangement typically requires a site lease for the land leased to the contractor/developer, a facilities lease for the lease-back of the school building to the school district and a traditional construction agreement. In some ways, the arrangement resembles a Public-Private Partnership (PPP) whereby a public entity collaborates with a private entity for the purpose of financing and delivering a project traditionally provided solely by the public sector.
Reprinted courtesy of
David G. Jordan, Saxe Doernberger & Vita, P.C. and
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C.
Mr. Jordan may be contacted at DJordan@sdvlaw.com
Mr. Vita may be contacted at JVita@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: SCOTUS Clarifies Alien Tort Statute and WOTUS Is Revisited
July 11, 2021 —
Anthony B. Cavender - Gravel2GavelWhat follows is a brief account of some of the notable U.S. environmental and administrative law cases recently decided.
THE U.S. SUPREME COURT
Nestle USA, Inc. et al. v. Doe, et al.
The Supreme Court has decided another important case interpreting the Alien Tort Statute. Released on June 17, 2021, this decision reverses the Ninth Circuit which had ruled that the respondents—six individuals who alleged they were child slaves employed on Ivory Coast cocoa farms, could sue the American-based companies for aiding and abetting child slave labor. Without dissent, the Court rejected this reading of the ATS and affirmed its own recent rulings on the scope of the ATS.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Visual Construction Diaries – Interview with Jeff Sassinsky of Fovea Aero
November 30, 2017 —
Aarni Heiskanen - AEC BusinessJeff Sassinsky, President of Fovea Aero, gave me a live demonstration on Fovea Aero Vision – an app that allows you to a get a fully immersive visual construction diary of your project.
The idea for the development of Fovea Aero Vision came from discussions with general contractors, owners, and other construction industry professionals. They were talking about the use of smartphones, particularly phone cameras, in construction. The photos, for example, of a fitting that does not look right end up in a folder on a server or goes back and forth in email messages. “The lack of any structure behind both the collection and the storage and sharing of the photos is hampering their usage,” Jeff said. “We wanted to solve the problem by creating a full record of everything that takes place on a construction site, on a regular basis, sharing it among the stakeholders, and making it super easy to use.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi
“A No-Lose Proposition?”
October 07, 2024 —
Daniel Lund III - LexologyA Miller Act payment bond surety and its principal general contractor both sued in federal court in New Orleans by a project subcontractor sought to compel arbitration the claims against both contractor and surety based on an indisputably enforceable arbitration clause in the subcontract. This was urged to avoid separate actions against the contractor (arbitration) and its surety (litigation), even though the surety was not a party to the subcontract and, therefore, not a party to the arbitration clause.
In the face of the lack of an express agreement to arbitrate, the contractor and contractor argued that “no federal statute or policy prohibits all of Plaintiff’s claims from proceeding to arbitration….” Additionally, those parties urged that the surety should be allowed to affirmatively compel arbitration because the surety “would otherwise have the ability to assert the right to compel arbitration as a defense….”
The New Orleans federal district court was unpersuaded:
“[D]istrict courts within this circuit have recognized that ‘Miller Act claims by a subcontractor for unpaid labor and materials are separate and distinct from those for general breach of contract… [and] arbitration and Miller Act suits, are not, per se, inconsistent with one another.’…[A]bsent express contractual intent to subject Miller Act claims to arbitration, the court [will] not force the parties to arbitrate claims against nonparties to the contract at issue…. [C]laims against a surety, which was a non-signatory to the contract, would not be subject to arbitration without any contractual basis to do so.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Court Rejects Anti-SLAPP Motion in Construction Defect Suit
September 01, 2011 —
CDJ STAFFThe California Court of Appeals has upheld the denial of an anti-SLAPP motion in Claredon American Insurance Company v. Bishop, Barry, Howe, Haney & Ryder. This case was triggered by a water intrusion problem at a condominium complex, the Terraces at Emerystation, built and sold by Wareham Development Corporation. The insurer, Claredon, retained Risk Enterprise Management as the third party claims administrator. REM retained the law firm Bishop, Barry, Howe, Haney & Ryder. The construction defect case was settled in 2007 and the condo owners moved back by early 2008.
Due to issues with the claims settlement, Claredon filed against REM for “professional negligence, indemnity, apportionment and contribution,” with a cross-complaint that the cross-defendants negligently defended the developer, Wareham.
In response, the cross-defendants filed a motion to strike the cross-complaint under the anti-SLAPP statute. The trial court denied this motion and now this has been upheld by the appeals court.
The court noted that “The fundamental thrust of the cross-complaint is not protected litigation-related speech and petitioning activity undertaken on another’s behalf in a judicial proceeding.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of