Difficulty in Defending Rental Supplier’s Claim Under Credit Application
October 11, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn construction, one of the easiest claims to prove from a burden of proof standpoint is that of a supplier, particularly a rental equipment supplier. Oftentimes, these claims are more in the realm of a collection claim because a rental supplier will generally be able to establish that a party opened an account with them, signed a credit application and personal guaranty, and equipment was rented and even delivered to a specific jobsite during set dates. Defending these claims is not so easy. And even if there is a defense as it relates to some amounts, there needs to be an upside challenging those amounts when factoring in the attorney’s fees, costs, and interest on the other amounts and on continuing the dispute.
An example of the difficulty in defending these claims from rental suppliers can be found in the recent case of Custom Design Expo, Inc. v. Synergy Rents, Inc., 2021 WL 4125806 (Fla. 2d DCA 2021). Here, a contractor rented equipment (e.g, forklifts) from a supplier. The equipment was rented on an open account and the contractor signed a personal guaranty. The supplier sued the contractor for about $81,000 that remained unpaid. The supplier appeared to waste no time and moved for summary judgment with an affidavit from its credit manager. The credit manager affirmed that the contractor executed a credit application for purposes of renting equipment on an open account, the application contained a personal guaranty, and the credit application formed the basis of a contract. The credit manager authenticated the credit application and affirmed that the contractor owed it about $81,000 in unpaid amounts for rental equipment that was furnished under the credit application.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Forget the Apple Watch. Apple’s Next Biggest Thing Isn’t for Sale
May 20, 2015 —
Garret Murai – California Construction Law BlogApple released its much anticipated Apple Watch this past month.
The Apple Watch is significant for Apple, not only because its profit and loss statement has a lot riding on it, but because it’s the company’s first foray into consumer “wearables.”
This isn’t the first time the Cupertino company has ventured into new areas, through. Since its first consumer product, the Apple I, was released in 1976, Apple has gone from personal computers – and its iterations, including, desktops, laptops and tablets – to music players, cell phones and now watches.
Today, Apple is less a computer company than a consumer electronics company, and even that doesn’t quite seem to go far enough, as it has become a lifestyle brand for many. Comparisons can be drawn to Sony during the mid-1980s when everyone aspired to a home filled with Sony televisions, Sony receivers and Sony Walkmans.
Part of Apple’s success is that it sells a lifestyle that transcends its products, in which a glossy, sophisticated minimalism and simplicity, are among its most recognizable characteristics. It goes beyond their products, and is embodied in their advertising, their online and retail stores, and their packaging. And while the Apple Watch may be Apple’s latest “big” thing, I think something even bigger is underfoot at Apple, and it’s something you can’t buy.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
How is Negotiating a Construction Contract Like Buying a Car?
March 01, 2017 —
Christopher G. Hill – Construction Law MusingsI know, you’re probably looking for a punchline, and likely thinking something along the lines of “only a construction attorney would be sitting in his office and come up with such an analogy,” but I really do think it’s a good one.
When you are buying a car, you look for priorities. Is the color what you want? Is the motor a hybrid or a v-6? Does it have Android Auto? What is the fuel mileage? All of these things may be more or less important to you. If you can get your priorities for a price that is attractive, you will likely let some other less important items, e. g. trunk space or rear seat leg room, slide and purchase the car anyway. Furthermore, you may use these minor items as negotiating points to either get one of the priorities or a lower price. Of course the dealership will want to get its priorities, likely a sale and a profit, when negotiating and will have certain items that it won’t move on just as you have terms that you won’t move on.
Much like when you walk onto the car lot, and particularly as a subcontractor looking at a contract from a general contractor, or a GC looking at the contract from the owner of a project, a construction contract presented to you is the starting point. When looking at the contract, be sure to have some non-negotiable items in mind when taking a critical eye to the terms of that contract. Some of these terms may be more or less negotiable depending on your experience with the other party to the construction contract. For instance, striking a pay if paid clause may be less important with a paying party with whom you have a 10 year history without payment problems. On the other hand, if it is your first contract with the other party, a stricter list may be required. So, much like a dealer that you know will stand behind its cars, you may be more willing to take more “risk” in entering a construction contract with a trusted/known owner or GC.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Future of Airport Infrastructure in a Post-Pandemic World
March 21, 2022 —
Cait Horner & Adam J. Weaver - Gravel2Gavel Construction & Real Estate Law BlogIn the wake of the COVID-19 pandemic, many service industries are reevaluating their physical footprint, and the aviation industry is no exception. Opportunities abound for developers, designers, and contractors to update and expand airport terminals to accommodate traditional needs while also meeting the growing demand for more open space (including larger outdoor areas in terminals and larger cargo facilities to meet the needs of Amazon, FedEx and UPS).
The Future of Passenger Terminals
In nearly every service industry, safety and hygiene policies are being overhauled, with a specific emphasis on the desire for more space across the board. Even before the pandemic caused a seismic shift in the way individuals interact with each other, airports and airlines had started reducing the number of unnecessary interactions between travelers and employees by introducing self-service check-in kiosks and contactless ordering at restaurants. The automation inside the airport will only continue to advance.
Reprinted courtesy of
Cait Horner, Pillsbury and
Adam J. Weaver, Pillsbury
Ms. Horner may be contacted at cait.horner@pillsburylaw.com
Mr. Weaver may be contacted at adam.weaver@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
North Carolina Appeals Court Threatens Long-Term Express Warranties
April 09, 2014 —
Beverley BevenFlorez-CDJ STAFFJonathan Massell of the firm Nexsen Pruet explained how a “recent holding by the North Carolina Court of Appeals is threatening to render many long-term express warranties ineffective,” in the online publication Lexology.
In Christie v. Hartley Construction, Inc., “the court held that the six-year North Carolina statute of repose for improvements to real property trumps the bargained-for duration terms of an express warranty.” In the Christie case, this meant that even though the homeowners had a twenty year warranty, because of the statute of repose, the warranty effectively expired after six years.
Massell stated to “be mindful of jurisdiction.” If the express warranty is in a state other than North Carolina, it’s possible that the claim could be filed in that state instead of North Carolina. For instance, according to Massell, South Carolina’s “statue of repose does not expire until eight years after the date of substantial completion for an improvement to real property.” Furthermore, “long-term warranties are not trumped by the South Carolina statute of repose.”
Read the court decisionRead the full story...Reprinted courtesy of
Tokyo Tackles Flood Control as Typhoons Swamp Subways
August 20, 2014 —
Jacob Adelman – BloombergBelow the condos and boutiques of Tokyo’s upscale Minato ward -- which includes Roppongi Hills, home to Goldman Sachs Group’s Japan headquarters -- a boring machine has carved out the city’s newest defense against floods.
“There are many buildings, there’s a freeway,” said Satoshi Yamamoto, who’s directing the Tokyo government’s 24.5 billion yen ($240 million) project to build a giant subterranean reservoir -- the city’s second of three -- to handle flood waters from the Furukawa river that winds through the area. “We decided the best approach was to go underground.”
When it’s completed in 2016, the 3.3-kilometer (2-mile) reservoir will be able to handle 135,000 cubic meters of water, enough to fill 54 Olympic-sized swimming pools. Tokyo is becoming increasingly reliant on this solution as more typhoons hit the country each year, a trend that Yamamoto said may be linked to global warming. The flooding is exacerbated by the city’s sprawling concrete footprint that keeps rainwater from seeping safely into the ground.
Read the court decisionRead the full story...Reprinted courtesy of
Jacob Adelman, BloombergMr. Adelman may be contacted at
jadelman1@bloomberg.net
Sustainability Puts Down Roots in Real Estate
January 27, 2020 —
Stephanie Amaru - Gravel2Gavel Construction & Real Estate Law BlogSustainability has evolved from a passing trend or niche preference into an undeniable, growing driver of the real estate market. This is particularly true as millennials comprise an increasing proportion of the workforce, home-buying population, and individuals influencing the future of real estate development in the United States.
If anything illustrates the significance of younger generations’ increasing interest in sustainability, it is the Global Climate Strike that drew participation of many thousands of young people, with 2,500 events scheduled in over 150 countries. In New York City, 1.1 million public school students were excused from school to join the strike in an event planned to precede the UN Summit, which itself was intended to push countries toward a commitment to faster transition to renewable energy and stricter climate targets. While both policymakers and citizens of previous generations have been split on their willingness to address global climate change with urgency, younger generations are feeling a stronger sense of responsibility for curbing the world’s trajectory towards a climate catastrophe, which will be inherited by them and their children. This has manifested in action that promotes awareness of and political action with respect to these issues—such as the Global Climate Strike—as well as evolving habits and preferences in both consumer goods and real estate.
Greener Space
In recent years, real estate developers have recognized that there is a market for “greener” developments that reduce annual expenditures on buildings, whether it be through small spaces requiring less electricity and promoting energy efficiency, or through renewable energy options such as solar photovoltaic power. Some real estate developers have chosen to install these options themselves, while others seek out sustainable financing options to cover the costs of renewable energy. If installing renewable energy is too costly, real estate developers will seek out more cost-effective locations for their brick-and-mortar operations.
Read the court decisionRead the full story...Reprinted courtesy of
Stephanie Amaru, PillsburyMs. Amaru may be contacted at
stephanie.amaru@pillsburylaw.com
Steps to Defending against Construction Defect Lawsuits
July 21, 2011 —
CDJ STAFFWriting in Claims Journal, Bryan Rendzio notes that the decline in construction has not been matched by a decline in construction defect lawsuits over condominiums. He reviews the ways in which lawyers representing developers can help protect their clients. He identifies four important considerations in defending developers from claims of construction defects.
He advocates a careful review of the contract. “Under a breach of contract claim, the insured’s duties to the party who brought the claim against the insured flow from the contract. Commonly, construction contracts limit the scope of recoverable damages, such as by waiving consequential damages.’
The next step, according to Rendzio is to check of a settlement agreement is already in place, noting that these are “a familiar occurrence in the construction industry, regardless of any lawsuits having been filed.”
He considers the statute of repose “the single-most decisive weapon an insured possesses in its arsenal during a condo defect lawsuit.” He notes that no lawsuits can be brought for construction defects after the end specified by the statute of repose, and if a lawsuit is brought beforehand, no additional parties can be named once the statute has taken effect.
Finally, he warns adjusters to be suspicious when a condo association requests contractual indemnification. He notes that the pitfall in this is that developers and the subsequent condominium association often have similar names, given the theoretical example of a condo project built by “Fake Lakes LLC” and later run by the “Fake Lakes Condominium Association.” Writing in regards to Florida law, he notes that condominium associations do not have successor interest in contracts developers made with contractors.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of