The Impact of Sopris Lodging v. Schofield Excavation on Timeliness of Colorado Construction Defect Claims
January 26, 2017 —
Jean Meyer - Colorado Construction LitigationOn October 20, 2016, the Colorado Court of Appeals announced the Sopris Lodging, LLC v. Schofield Excavation, Inc.[1] decision. The Sopris decision significantly altered the potential pitfalls awaiting a general contractor in pursuit of third-party claims as well as potential defenses available for a subcontractor defending against third-party claims.
By way of background, the Sopris construction defect case arose out of the following facts: TDC was the general contractor for the construction of a hotel owned by Sopris Lodging. On March 11, 2011, Sopris Lodging sent TDC a notice of claim regarding alleged construction defects. On May 24, 2013, Sopris Lodging filed a complaint in district court asserting construction defect claims against one of the subcontractors of the hotel, and against the general contractor’s principals, but not the general contractor. Contemporaneous with the filing of the suit, Sopris Lodging and TDC entered into an agreement to toll the statute of limitations on Sopris Lodging’s potential claims against TDC. In August 2013, Sopris Lodging joined the general contractor to the suit. A year later, in 2014, the general contractor joined a variety of subcontractors as third-party defendants.
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Jean may be contacted at
meyer@hhmrlaw.com
Insurer's Appeal of Jury Verdict Rejected by Tenth Circuit
March 06, 2023 —
Tred R. Eyerly - Insurance Law HawaiiAfter a jury awarded damages related to the insurer's delayed payment under the claim and the insurer's post trial motions to set aside the verdict were denied, the Tenth Circuit affirmed. US General, LLC v. GuideOne Mut. Ins. Co., 2022 U.S. App. LEXIS 34066 (10th Cir. Dec. 12, 2022).
Crossroads American Baptist Church submitted a claim to GuideOne for hailstorm damage. Crossroads hired US General as the general contractor to perform the repairs and later assigned its interest in the insurance policy to US General.
Numerous disputes arose between Crossroads and GuideOne regarding the cost of the repairs. There were delayed payments and portions of the repairs were never paid for. The delayed payments meant GuideOne's ability to begin making the repairs was hindered because it was more expensive to start and stop a project.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Hard to Believe It, Construction Law Musings is 16
January 07, 2025 —
Christopher G. Hill - Construction Law MusingsOn this date back in 2008 (wow, that seems so long ago), I began Construction Law Musings on the Blogger platform with a brief announcement. Little did I know that this corner of the internet (or is it Blawgosphere?) would still be around in 2024!
In the time since I made that short entry 16 years ago (I know, I can’t believe it either), I’ve met several construction lawyers here in Virginia who refer to me as the “blog guy.” To be recognized for the work I do here at Construction Law Musings, something that benefits me (and I hope the readers), and which I do for the fun of it, is an honor.
The blog has since taken on a life of its own in many respects, allowing me to meet some of the great construction pros who have provided a guest post or two for Musings and added their different perspectives. Musings also kept me up on at least most of the trends in Virginia construction law by making me post consistently (though sometimes less consistently than others). Now, around 975 posts and 16 years later, I find it hard to believe that so much time has passed and effort has been put into what started on a whim and the plan that I’d post thoughts on the legal landscape and construction from the perspective of a Virginia construction lawyer.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Ruling Dealing with Constructive Changes, Constructive Suspension, and the Implied Covenant of Good Faith and Fair Dealing
January 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesA dispute pending in the Armed Services Board of Contract Appeals (ASBCA) dealt with interesting legal issues on a motion to dismiss. See Appeals of McCarthy Hitt-Next NGA West JV, ASBCA No. 63571, 2023 WL 9179193 (ASBCA 2023). The dispute involves a contractor passing through subcontractor claims due to impacts caused by the COVID-19 pandemic and the government’s response to the pandemic. More particularly, the claim centers on the premise that the government “failed to work with [the contractor] in good faith to develop a collaborative and cooperative approach to manage and mitigate the impacts and delays arising from the COVID-19 pandemic.” See Appeals of McCarthy Hitt.
The contractor (again, submitting pass through claims from subcontractors) claimed: (a) constructive changes to the contract entitling it to an equitable adjustment under the Changes clause of Federal Acquisition Regulation (F.A.R.) 52.243-4; (b) construction suspensions of the contractor’s work entitling it to an equitable adjustment under the Suspensions of Work clause of F.A.R. 52-242-14; and (c) the government breached the implied covenant of good faith and fair dealing. Each of these legal issues and theories will be discussed below because they are need-to-know legal issues. Keep these legal issues in mind, and the ASBCA’s ruling on the motion to dismiss as its analysis may demonstrate fruitful in other applications.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Sixth Circuit Affirms Liability Insurer's Broad Duty to Defend and Binds Insurer to Judgment Against Landlord
September 07, 2020 —
Michael V. Pepe & Janie Reilly Eddy - Saxe Doernberger & VitaIn a victory for policyholders, the Sixth Circuit affirmed that a landlord’s insurer owed a duty to defend the landlord in a bodily injury claim arising out of a fire that killed three and injured one. The Court held that the insurer breached its duty to defend and was bound to the insured’s $3 million consented judgment.
Transition Investments LLC, an owner of three properties in the Detroit area, purchased a general liability insurance policy with Hamilton Specialty Insurance Company to insure its properties. At one of the properties, a faulty stove started a fire, destroying the building, injuring one person and killing three others. The estates of the deceased and the injured party sued Transition in Michigan state court. In their complaint, the plaintiffs contended that Transition failed to provide a habitable premise and neglected to maintain the property’s stove, which allegedly caused the fire. The plaintiffs argued that Transition’s negligent maintenance of the property led to the fire and the resulting injuries. Transition subsequently tendered the claim to Hamilton. Hamilton claimed that the insurance policy did not cover the fire’s damages and refused to participate in the state court litigation. Ultimately, Transitions entered into a consent judgment with the plaintiffs for $3 million.
Reprinted courtesy of
Michael V. Pepe, Saxe Doernberger & Vita and
Janie Reilly Eddy, Saxe Doernberger & Vita
Mr. Pepe may be contacted at mvp@sdvlaw.com
Ms. Eddy may be contacted at jre@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Rooftop Solar Leases Scaring Buyers When Homeowners Sell
June 26, 2014 —
Will Wade – BloombergDorian Bishopp blames the solar panels on his roof for costing him almost 10 percent off the value of the home he sold in March.
That’s because instead of owning them he leased the panels from SunPower Corp. (SPWR), requiring the new owner of the house to assume a contract with almost 19 years remaining. He had to shave the asking price for the house in Maricopa, Arizona, to draw in buyers unfamiliar with the financing arrangement.
Leasing is driving a boom in solar sales because most require no money upfront for systems that cost thousands of dollars. That’s made solar affordable for more people, helping spur a 38 percent jump in U.S. residential installations in the past year. Since the business model only gained currency in the past two years, the details embedded in the fine print of the deals are only starting to emerge.
Read the court decisionRead the full story...Reprinted courtesy of
Will Wade, BloombergMr. Wade may be contacted at
wwade4@bloomberg.net
Drought Dogs Developers in California's Soaring Housing Market
September 17, 2015 —
John Gittelsohn – BloombergCalifornia’s already tight housing market is facing another long-term complication: drought.
The state’s dry spell is creating challenges for developers at a time when home prices are soaring because of limited inventory. The metropolitan areas of San Jose, San Francisco and San Diego had the nation’s biggest gap between the number of new jobs and residential building permits from 2012 to 2014, according to a report Wednesday by the National Association of Realtors. Now the drought, into its fourth year, stands to curb affordability further.
“It’s contributing to price appreciation by restricting supply,” said Mark Boud, founder of Real Estate Economics, a housing-consulting firm based in Irvine, California.
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn, Bloomberg
Need and Prejudice: An Eleventh-Hour Trial Continuance Where A Key Witness Is Unexpectedly Unavailable
July 10, 2018 —
Angela S. Haskins & Allegra Perez - Haight Brown & Bonesteel LLPIn Padda v. Superior Court (GI Excellence), No. E070522, the Court of Appeal, Fourth Appellate District, Division Two, recently held that a trial court abused its discretion in denying Defendants/Cross-Complainants’ request for a trial continuance where their key expert witness suddenly became ill twelve days before trial and before his deposition had been taken.
Reprinted courtesy of
Angela S. Haskins, Haight Brown & Bonesteel LLP and
Allegra Perez, Haight Brown & Bonesteel LLP
Ms. Haskins may be contacted at ahaskins@hbblaw.com
Ms. Perez may be contacted at aperez@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of