Update Coverage for Construction Defect Claims in Colorado
February 11, 2013 —
Tred R. Eyerly Whether construction defect claims against an insured contractor or subcontractor are covered is undergoing an intense debate in Colorado that is reminiscent of the current coverage battle in Hawaii.
Although I missed the case until recently, the decision in Colo. Pool Sys. v. Scottsdale Ins Co., 2012 Colo. App. LEXIS 1732 (Colo. Ct. App. Oct. 25, 2012), appears to divert from a prior case from the Colorado Court of Appeals, Gen. Sec. Indem. Co. v. Mountain States Mut. Cas. Co., 205 P.3d 529 (Colo. App. 2009). Gen. Security held that faulty workmanship, standing alone, was not an "accident." Gen. Security was heavily relied upon by the Hawaii Intermediate Court of Appeals when it found construction defects arose from breach of contract and were not covered under a liability policy. See Group Builders v. Admiral Insurance Co., 123 Haw. 142, 231 P.3d 67 (Haw. Ct. App. 2010).
In Colo. Pool Sys., Colorado Pool hired subcontractors to construct a poll's concrete shell. After the shell was poured, an inspection noticed that some re-bar was too close to the surface. The owner turned to its general contractor, White Construction Group, and demanded that the pool be removed and replaced. White turned to Colorado Pool, who notified its carrier, Scottsdale.
Read the court decisionRead the full story...Reprinted courtesy of
Insurance Law HawaiiMr. Eyerly can be contacted at
te@hawaiilawyer.com
Negligent Misrepresentation in Sale of Building Altered without Permits
September 30, 2011 —
CDJ STAFFThe Supreme Court of New Hampshire has ruled in the case Wyle v. Lees. The Leeses owned a two-unit apartment building in North Conway, New Hampshire. They hired a contractor to add a third, larger apartment, including a two-car garage. The Leeses and their contractor submitted a building permit application. They were informed that site plan review was required. After receiving approval on the site plan, construction started. At no point did they obtain a building permit and the construction was never inspected. The Leeses subsequently added more space to the unit, reducing parking spaces below the minimum required. Again, they did not obtain a building permit.
In 2007, three years after all these changes were complete, the Leeses sold their building to Mr. Wyle. To the question “are you aware of any modifications or repairs made without the necessary permits?” they answered “no.” About six weeks after closing, Wyle “received a letter from the town code enforcement officer regarding the legality of the removal of a garage door from the new unit.” A subsequent inspection revealed “numerous building and life safety code violations.”
Mr. Wyle brought a claim against the Leeses for negligent misrepresentation. The defendants filed a motion “seeking to preclude economic loss damages.” At a two-day bench trial, Mr. Wyle won. The Leeses appealed.
The appeals court found that “the defendants negligently misrepresented that the premises were licensed for immediate occupancy and that the defendants had obtained all necessary permits,” and thus upheld the lower court’s finding of negligent misrepresentation. The appeals court also rejected the Leeses’ argument that damages must be apportioned on all parties, including “the plaintiff himself, the plaintiff’s building inspector, and the defendant’s contractor,” finding a lack of “adequate evidence.”
The Leeses further argued that they were unaware that modifications and repairs were accomplished without the required permits. The appeals court noted that “the trial court found that both the conditional approval and final approval for the site plan stated that a building permit and a certificate of occupancy were required prior to any use.” The court concluded that the Leeses “knew or should have known of the falsity of their representation.”
The appeals affirmed the findings of the trial court.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
First Trump Agenda Nuggets Hit Construction
January 26, 2017 —
Pam Radtke Russell, Mary B. Powers & Debra K. Rubin - Engineering News-RecordPresident Donald J. Trump began making good on campaign promises to put Americans back to work and reduce the size of government, as he signed orders and memoranda setting in motion approval of the Obama administration-halted Keystone XL and Dakota Access pipelines and streamlining of infrastructure and manufacturing permitting processes. But firms and watchdog groups are concerned how an announced freezing of government hiring and contracting will play out, as well as the future of environmental protection.
Reprinted courtesy of Engineering News-Record staff
Pam Radtke Russell,
Mary B. Powers and
Debra K. Rubin Read the court decisionRead the full story...Reprinted courtesy of
Ms. Rubin may be contacted at
rubind@enr.com
The Contractor’s Contingency: What Contractors and Construction Managers Need to Know and Be Wary Of
December 04, 2023 —
Skyler L. Santomartino - Peckar & Abramson, P.C.Contractors and construction managers who enter into cost reimbursable contracts subject to a guaranteed maximum price (GMP) are responsible for all project costs exceeding the GMP. For this reason, it is imperative that contractors negotiate and incorporate into the GMP a financial buffer that accounts for the unanticipated project costs that are not reimbursable as change orders or costs of the work. This is where the contractor’s contingency comes into play.[
1]
The contractor’s contingency is a vehicle that allows contractors to mitigate some of the risks inherent in GMP contracts. When drafted properly, a contingency clause allows the contractor and only the contractor to access funds set aside by the owner to address unpredictable or unknown project costs.
Read the court decisionRead the full story...Reprinted courtesy of
Skyler L. Santomartino, Peckar & Abramson, P.C.Mr. Santomartino may be contacted at
ssantomartino@pecklaw.com
Settlement Ends Construction Defect Lawsuit for School
October 02, 2013 —
CDJ STAFFThe school district in the Chicago-area town of Lake Zurich has made last settlement in a construction defect lawsuit. The $80,000 settlement from Terra Group of Chicago brings the total settlement with the Community Unit School District 95 to about $1.9 million. Other firms included Bovis Lend Lease, Legat Architects, Larson Engineering, and Illinois Masonry Corporation.
The school district had contracted for work on several schools in the district. The buildings opened in 2004, with defect claims made in 2007. Defect claims included the failure of a retaining wall and need for reinforcement of stairwells. The settlement with Terra Group was made under the agreement that it was a compromise with no concession of liability.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Workers Unearth Bones
June 28, 2011 —
CDJ STAFFWhile digging for a new steam line at Eastern Michigan University, workers unearthed some old bones. Experts have yet to determine if the bones are human or animal, however Walter Kraft, the EMU vice president of communications, noted that a handle also unearthed might have come from a casket. Cindy Heflin, reporting in AnnArbor.com notes that until 1900 a Catholic cemetery was located in the area. Although the bodies were relocated, these may have been left behind.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Foundation Differences Across the U.S.
October 15, 2014 —
Beverley BevenFlorez-CDJ STAFFThe National Association of Home Builders’ Eye on Housing analyzed data from the Survey of Construction (SOC) to demonstrate the differences in foundations built across the nation. For instance, “about 30 percent of new single-family homes started in 2013 have a full or partial basement, 54 percent are built on slabs, and 15 percent have a crawl space. The remaining share, including homes built on stilts or pilings, accounted for about 1 percent of homes started in 2013.”
Climate is the deciding factor in what type of foundations are used, Eye on Housing reported. “In colder regions where codes require foundations to be deep the marginal cost of providing a full or partial basement is not that great. So basements are the most common type of foundation in the colder climate divisions.” The warm climate area of the West South Central division are primarily built on slabs. However, “the other two divisions that make up the South region – the East South Central and South Atlantic –are still largely built on slabs but crawl spaces are also common.”
Read the court decisionRead the full story...Reprinted courtesy of
No Rest for the Weary: Project Completion Is the Beginning of Litigation
June 18, 2019 —
Albert Li & Bob Fitzsimmons - Construction ExecutiveIn today’s environment, most construction projects end up in some form of litigation. Construction is full-time employment for lawyers – from contract negotiation to project management, lien and payment issues. Years after project completion, a company still can face construction defect litigation and be served with a Notice of Opportunity to Repair, which in most states is now codified into statute. This is the beginning of what most likely will become a lawsuit, involving many of the subcontractors.
Watch Out for the Construction Contract Blame Game
The first phase of post construction litigation involves the review of contract and insurance policy language in an attempt to transfer responsibility in the litigation to other parties.
Before construction began, contract negotiation focused on budget and timeline. In the post-construction phase, two less noticed provisions of the contract are critical – indemnity and insurance.
Reprinted courtesy of
Albert Li & Bob Fitzsimmons, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Fitzsimmons may be contacted at rfitzsimmons@rumberger.com
Mr. Li may be contacted at ali@rumberger.com
Read the court decisionRead the full story...Reprinted courtesy of