Statute of Limitations and Bad Faith Claims: Factors to Consider
May 16, 2022 —
Anastasiya Collins - Saxe Doernberger & Vita How much time do our clients have to bring a bad faith action against an insurer? Although we are not frequently asked this question, it is one that we constantly analyze before asserting a bad faith claim.
To answer this question, we look to the statute of limitations, which is a law passed by a state legislative body that sets the maximum amount of time for a party to bring a claim based upon a particular cause of action. For policyholders, knowing which statute of limitations applies to their bad faith claim is critical because it indicates whether it is possible to initiate legal proceedings. In addition, it determines the amount in damages available in case of a successful resolution.
Statute of Limitations in Breach of Contract vs. Tort Claims
One key determinant of a statute of limitations for bad faith is whether the claim is brought as a tort or a breach of contract action. The consequence of framing bad faith as a tort is that a policyholder is not just limited to contract damages. The policyholder can also receive recourse for emotional distress, pain, suffering, punitive damages, attorney’s fees, and other damages that the court may consider appropriate. Unfortunately, however, not every jurisdiction allows plaintiffs to bring bad faith actions as tort claims. While, for example, courts in California, Colorado, and Connecticut allow bad faith claims sounding in tort, courts in jurisdictions such as Tennessee do not.
Read the court decisionRead the full story...Reprinted courtesy of
Anastasiya Collins, Saxe Doernberger & VitaMs. Collins may be contacted at
ACollins@sdvlaw.com
US Court Questions 102-Mile Transmission Project Over River Crossing
February 07, 2022 —
Mary B. Powers - Engineering News-RecordA federal judge will decide in February whether to stop construction of a $492-million Iowa-to-Wisconsin transmission line, after issuing an opinion in mid-January “declaring” that federal rules preclude the 102-mile Cardinal-Hickory Creek project from crossing the 261-mile Upper Mississippi River National Wildlife and Fish Refuge by right-of-way or land transfer.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Quick Note: Discretion in Determining Prevailing Party for Purposes of Attorney’s Fees
January 25, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn prior articles I have discussed that courts apply the significant issues test to determine the prevailing party for purposes of being entitled to attorney’s fees. A party that recovers an affirmative judgement is NOT the de facto prevailing party for purposes of an entitlement to attorney’s fees in a breach of contract action (or a construction lien foreclosure action). This was the issue in a recent appeal discussed here where the party that recovered an affirmative judgment on a breach of contract case was not deemed the prevailing party for purposes of attorney’s fees. While the party prevailed on one of its claims, it did not prevail on others, and it recovered less than half of the damages it originally sought. The appellate court, affirming the trial court, held that the trial court has discretion to determine that the party that recovered an affirmative judgement was not the prevailing party entitled to its attorney’s fees under the signifiant issues test. This was not what the party was expecting when the attorney’s fees it expended far exceeded the judgment it recovered.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Creeping Incrementalism in Downstream Insurance: Carriers are Stretching Standard CGL Concepts to Untenable Limits
October 17, 2023 —
Eric M. Clarkson - Saxe Doernberger & VitaIn the construction sector, the importance of closely vetting downstream parties’ insurance has never been more critical. The markets have been hardening with no seeming end in sight and carriers are looking for any way to get an edge. Owners and general contractors need to be on the lookout for ever broader carrier-specific expansions of standard insurance provisions that are perilous for risk transfer. We are seeing more and more terms that go against the intent of ISO standard which is what is almost universally required in construction contracts.
One area where carriers are deviating from standard concepts is within pre-existing injury or damage exclusions in Commercial General Liability (“CGL”) policies. It is almost a universal requirement that downstream parties provide additional insured coverage to owners and general contractors on ISO form CG 00 01. Generally, ISO standard language provides coverage for sums the insured becomes legally obligated to pay as damages because of bodily injury or property damage. One of the few main requirements to trigger coverage is that the injury or damage must occur during the policy period. Over the years, ISO standard language has evolved to exclude injury or damage if an insured or certain persons knew that it had occurred before the policy period. Additionally, injury or damage is deemed to have been known to have occurred under certain circumstances.
Read the court decisionRead the full story...Reprinted courtesy of
Eric M. Clarkson, Saxe Doernberger & VitaMr. Clarkson may be contacted at
EClarkson@sdvlaw.com
Neighbor Allowed to Remove Tree Roots on Her Property That Supported Adjoining Landowners’ Two Large Trees With Legal Immunity
July 14, 2016 —
Paul R. Cressman, Jr. – Ahlers & Cressman PLLC BlogA recent Washington Court of Appeals opinion addressed the rights of a neighbor to destroy roots and branches on her property that belonged to trees located on an adjoining landowner’s property.[1]
Mustoe had two large Douglas-fir trees located entirely on her property, about two and one-half feet from the property line with her neighbor Ma. Ma caused a ditch to be dug on her property along the border with Mustoe’s lot. The ditch was 18-20 inches deep. In the process, Ma exposed and removed the trees’ roots, leaving them to extend only three-four feet from the trunks of the trees. This resulted in a loss of nearly half of the trees’ roots, all from the south side, exposing them to southerly winds with no support. The damaged trees posed a high risk of falling on Mustoe’s home. The landscape value of the trees was estimated to be $16,418. The cost of their removal was estimated to be $3,913.
Mustoe filed suit against Ma asserting that Ma had negligently, recklessly, and intentionally excavated and damaged her trees, along with other property, and also sought emotional distress damages. The trial court dismissed Mustoe’s suit. The Court of Appeals affirmed.
Read the court decisionRead the full story...Reprinted courtesy of
Paul R. Cressman, Jr., Ahlers & Cressman PLLC Mr. Cressman may be contacted at
pcressman@ac-lawyers.com
Quick Note: Be Careful with Pay if Paid Clauses (Both Subcontractors and General Contractors)
October 12, 2020 —
Christopher G. Hill - Construction Law MusingsAside from waiver of lien rights (something that will be illegal in Virginia after July 1, 2015), the most troublesome contractual impediment to payment for a subcontractor or supplier on a project often is the “pay if paid” clause. As a general rule, in Virginia, these clauses where drafted in the proper fashion, are enforceable. As I have said many times, in Virginia freedom of contract almost always wins out.
While this is the case, I emphasize that such clauses must be very explicit and specific. Furthermore, and in something that should be obvious, these clauses are generally limited by the Courts of Virginia to only be enforceable and to only forgive the need for payment if the upstream contractor on the construction job has not been paid for the work that the sub claiming non payment has done.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Alabama Court Determines No Coverage For Insured's Faulty Workmanship
June 28, 2013 —
Tred EyerlyThe Alabama Supreme Court found there was no coverage for the insured cabinet maker for claims arising from alleged faulty workmanship. Shane Traylor Cabinetmaker, L.L.C. v. Am. Resources Ins. Co., Inc., 2013 Ala. LEXIS 42 (May 3, 2013).
The insured was sued by a homeowner for property damage caused by faulty workmanship. The insurer refused to defend, contending there was no "occurrence." The trial court granted summary judgment to the insurer.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Bert L. Howe & Associates to Join All-Star Panel at West Coast Casualty Seminar
March 26, 2014 —
Beverley BevenFlorez-CDJ STAFFDon MacGregor of Bert L. Howe & Associates, a consulting firm, will join fellow panelists Hon. Peter Lichtman (ret), Hon. Nancy Wieben Stock (ret), Peter S. Curry, Brian Kahn, Esq., and Paul R. Kiesel, Esq in a break-out discussion entitled “Working Smarter with Technology” at this year’s West Coast Casualty Construction Defect Seminar being held May 15th-16th at the world-famous Disneyland Hotel in Anaheim, California.
West Coast Casualty's Construction Defect Seminar is the largest seminar of its kind worldwide focusing on all of the elements of the prosecution, defense, coverage and technologies of construction defect claims and litigation from a national perspective.
With offices in California, Nevada, Colorado, Florida and Texas (Houston & San Antonio), Bert L. Howe & Associates provides construction consulting and expert witness services to insurance professionals and lawyers specializing in construction defect litigation, construction risk analysis, and property claims arising from construction-related activities.
Download an Invitation and Register... Read the court decisionRead the full story...Reprinted courtesy of