Recovering Time and Costs from Hurricane Helene: Force Majeure Solutions for Contractors
November 18, 2024 —
Matthew DeVries - Best Practices Construction LawWhen Hurricane Helene struck North Carolina, it caused severe disruptions to construction projects across the state. Baxter International’s North Cove facility in Marion, N.C., was completely shut down after floodwaters damaged the site and bridges leading to it. Elsewhere, landslides and floods wiped out large sections of Interstate 40, making transportation of materials and equipment nearly impossible. Many contractors in western North Carolina found their projects halted, and their schedules thrown off by this force majeure event.
In situations like these, contractors and subcontractor need a plan to mitigate the impact of such natural disasters on their projects. Here are five practical tips to help you secure time extensions and/or compensation for delays:
1. Include a Robust Force Majeure Clause in Your Contract
When disaster strikes, your contract is your first line of defense. A well-drafted force majeure clause can make the difference between bearing the costs yourself and getting an extension or compensation. The clause should clearly list specific events such as hurricanes, floods, and road closures as qualifying force majeure events.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew DeVries, BuchalterMr. DeVries may be contacted at
mdevries@buchalter.com
Construction Problem Halts Wind Power Park
November 13, 2013 —
CDJ STAFFEngineers have yet to determine why a blade on a wind turbine broke at a wind power plant in Michigan, but as part of their investigation they are halting work on the final 10 turbines. The already completed 60 turbines have been taken out of operation. As a result, the Echo Wind Park is no longer generating power.
Scott Simons, a spokesperson for the project, said “we’re not going to put anyone or anything at risk until we get to the bottom of this.” However, Dennis Buda, the project manager, attributed the broken blade to a manufacturing defect. Construction was planned to end in November.
Read the court decisionRead the full story...Reprinted courtesy of
Crisis Averted! Pennsylvania Supreme Court Joins Other Courts in Finding that Covid-19 Presents No Physical Loss or Damage for Businesses
October 21, 2024 —
Edward M. Koch & Marc L. Penchansky - White and Williams LLPSeeking to find some relief from business losses experienced during the COVID-19 pandemic, many businesses turned to their property insurers for coverage for their lost income. A clear national trend emerged among courts deciding the issue, as most businesses could not establish coverage because they had not experienced a “direct physical loss of or damage to their covered property” as required by most policies.
While this legal question may have become an afterthought for many attorneys, the question remained an open one in Pennsylvania while the Pennsylvania Supreme Court considered two contradictory holdings issued in the Superior Court on this topic. Compare Macmiles, LLC v. Erie Ins. Exch., 286 A.3d 331 (Pa. Super. 2022) (holding there was no coverage for loss of use of a commercial property unaccompanied by any physical alteration or other physical condition that rendered the property unusable or uninhabitable) with Ungarean v. CNA, 286 A.3d 353 (Pa. Super. 2022) (holding that the policy at issue was ambiguous and therefore the policy covered the insured for COVID-related business losses). Last week, the Supreme Court considered the Superior Court’s holdings in Macmiles and Ungarean and held, at long last, that COVID-19 did not cause a direct physical loss of or damage to covered property.
Reprinted courtesy of
Edward M. Koch, White and Williams LLP and
Marc L. Penchansky, White and Williams LLP
Mr. Koch may be contacted at koche@whiteandwilliams.com
Mr. Penchansky may be contacted at penchanskym@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Duuers: Better Proposals with Less Work
July 21, 2018 —
Aarni Heiskanen - AEC BusinessSmall contractors, consultants, and design professionals have a love–hate relationship with responding to RFPs. Duuers, a Finnish startup, wants to turn this struggle into an inspiring experience.
“We followed a day in the life of a hand-picked group of entrepreneurs,” says Paula Viinamäki, co-founder of Duuers. “We were flies on the wall, observing how small business owners wrestle with their daily tasks. Proposal-writing seemed to be an especially painful and time-consuming, yet vital, job.”
Defining the Scope through Experiments
After discovering this poorly supported but essential job that had to be done, Viinamäki and Jussi Paanajärvi, the other co-founder of Duuers, realized that they might be onto something. Consequently, they decided to start working on a prototype app for proposal-writing in the spring of 2017.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Legal Risks of Green Building
March 22, 2021 —
Mark D. Shifton - Construction ExecutiveAll construction projects involve elements of legal risk. Insurance and indemnity claims, delay claims and professional negligence claims are simply accepted risks when involved in construction. Green building projects are no exception to this rule, and often involve unique issues that are not present in typical construction projects.
Green building projects commonly employ new or untested construction materials, require construction methods that lack significant track records, and ultimate building performance often fails to meet design expectations. As such, green building projects may give rise to entirely new types of legal risk that should be considered and allocated early in the process.
In the past 15 years, the number of buildings for which green certifications have been sought has grown exponentially, and the growth rate of green building and sustainable construction has far outpaced the growth rate of the construction industry as a whole. As green building projects become increasingly common (and often increasingly required by the federal, as well as state and local governments), the unique legal risks presented by green building projects take on an increase importance.
Reprinted courtesy of
Mark D. Shifton, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Shifton may be contacted at
mshifton@gllawgroup.com
Tidal Lagoon Plans Marine Project to Power Every Home in Wales
March 05, 2015 —
Louise Downing – Bloomberg(Bloomberg) -- Tidal Lagoon Power Ltd., a U.K. marine-energy developer, is planning its second project, a 2.8-gigawatt power plant that will use the tides to generate enough electricity for every home in Wales.
The company submitted an environmental impact assessment for the marine power plant that would use 90 turbines installed between Cardiff and Newport, according to an e-mailed statement Monday. The closely held company expects to submit a full planning application in 2017 and the project may go into operation in 2022.
Read the court decisionRead the full story...Reprinted courtesy of
Louise Downing, BloombergMs. Downing may be contacted at
ldowning4@bloomberg.net
Public Projects in the Pandemic Pandemonium
September 07, 2020 —
Ashlynn E. Hutton, Michael J. Crook & Christian F. Torgrimson - Construction ExecutiveDespite the ongoing pandemic, states are opening up for business and establishing a new normal. This determination to move forward includes pushing public transportation projects full steam ahead. While this may be good news for certain industries, it may not be for commercial property owners hoping to see a slow down to public projects and avoid a taking of private property. As many grapple with new economic realities, we examine the approaches employed by states in the southeast to manage construction of public projects in this unprecedented time.
GEORGIA
The Georgia Department of Transportation (GDOT) is moving forward with all of its previously funded public projects, including the massive I-285 Top-End Project, designated as a “Major Mobility Project” for the Atlanta metro region. Affecting approximately 260 property owners along I-285 and Georgia Highway 400, environmental review of the project continues. GDOT anticipates a contract let date in 2022 and construction start in 2023. Like ocean liners, these projects don’t turn on a dime. Under the 2015 Transportation Funding Act, the budgeted funds cannot be shifted to other needs or projects due to economic shutdown. Once environmental review is complete, GDOT will approve the final design and move toward acquiring right-of-way from affected property owners.
Reprinted courtesy of
Ashlynn E. Hutton, Michael J. Crook & Christian F. Torgrimson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
World’s Biggest Crane Lifts Huge Steel Ring at U.K. Nuclear Site
January 25, 2021 —
Rachel Morison - BloombergThe world’s largest crane hoisted the first of three massive steel rings that will encase one of the reactors at Electricite de France SA’s nuclear construction site in the U.K., a key milestone in getting the project completed on time.
Operators of the 250-meter (820-foot) tall crane, affectionately known as “Big Carl,” lifted the ring that weighs as much as a jumbo jet overnight to take advantage of windless conditions.
Hinkley Point C is the U.K.’s first new nuclear power plant in more than two decades. Once up and running the reactor will generate electricity for six million homes by 2025.
It’s the largest and most advanced infrastructure project in the country and, when finished, will contain 3 million tons of concrete and 50,000 tons of structural steel, enough to build a railway line between London and Rome.
Read the court decisionRead the full story...Reprinted courtesy of
Rachel Morison, Bloomberg