CDJ STAFFHomeowners sometimes aren’t too clear on questions of “building codes, permit process or where to find the right materials,” according to Benoni Mocanu, the owner of MB Development. He’s ready to step in an help by offering construction consulting to homeowners doing their own remodeling projects. In addition to providing the advice to help them through their projects, they’re ready to step in if a homeowner finds that they can’t finish the project.
Read the court decisionRead the full story...Reprinted courtesy of
Massachusetts Clarifies When the Statute of Repose is Triggered For a Multi-Phase or Multi-Building Project
December 07, 2020 —
Jeffrey J. Vita & Anna M. Perry - Saxe Doernberger & Vita, P.C.Lennar Hingham Holdings, LLC (“Lennar”) built a twenty-eight-building, 150-unit condominium project containing twenty-four discrete phases over a seven-year span. The condominium association subsequently brought an action against Lennar and others alleging design and construction defects to four main components of the common elements: “decks and columns,” “roofing/flashing,” “exterior walls/flashing/building envelope,” and “irrigation system.” In response, the defendants argued that the plaintiff’s claims with respect to six of the twenty- eight buildings were barred by Massachusetts’s six-year statute of repose, G. L. c. 206 § 2B.
The United States District Court for the District of Massachusetts previously held that all twenty-eight of the condominium’s buildings should be treated as a single improvement for purposes of application of the statute of repose. Subsequently, the court certified the following question to the Massachusetts Supreme Judicial Court: Where the factual record supports the conclusion that a builder or developer was engaged in the continuous construction of a single condominium development comprising multiple buildings or phases, when does the six-year period for an action of tort relating to the construction of the condominium’s common or limited common elements start running?
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C. and
Anna M. Perry, Saxe Doernberger & Vita, P.C.
Mr. Vita may be contacted at JVita@sdvlaw.com
Ms. Perry may be contacted at APerry@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Questions of Fact Regarding Collapse of Basement Walls Prevent Insurer's Motion for Summary Judgment
December 19, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe court denied the insurer's motion for summary judgment on whether the policy covered the collapse of basement walls based upon factual issues presented. Sirois v. USAA Cas. Ins. Co., 2018 U.S. Dist. LEXIS 158508 (D. Conn. Sept. 18, 2018).
The insureds' purchased their home in 2010. In December 2015, a crack in the basement wall was noticed. It was not thought to be a serious problem. But in 2016, the insured read an article about defective concrete problems affecting homeowners in Connecticut. An inspector, Dean Soucy, was hired. He found faults and cracks in the foundation walls. Thereafter, a claim was submitted to USAA under homeowners' policies issued over the years to the insureds. USAA denied coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
When Your “Private” Project Suddenly Turns into a “Public” Project. Hint: It Doesn’t Necessary Turn on Public Financing or Construction
September 28, 2017 —
Garret Murai - California Construction Law BlogIn 1931, during the Great Depression, the federal government enacted the Davis-Bacon Act to help workers on federal construction projects. The Davis-Bacon Act, also known as the federal prevailing wage law, sets minimum wages that must be paid to workers on federal construction projects based on local “prevailing” wages. The law was designed to help curb the displacement of families by employers who were recruiting lower-wage workers from outside local areas. Many states, including California, adopted “Little Davis-Bacon” laws applying similar requirements on state and local construction projects.
California’s current prevailing wage law requires that contractors on state and local public works projects pay their employees the general prevailing rate of per diem wages based on the classification or type of work performed by the employee in the locality where the project is located, as well as to hire apprentices enrolled in state-approved apprentice programs and to make monetary contributions for apprenticeship training.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Limiting Plaintiffs’ Claims to a Cause of Action for Violation of SB-800
November 18, 2011 —
Samir R. Patel, Esq., Lorber, Greenfield, & Polito, LLPThere has been a fair share of publicity about the SB-800 amendments to the Civil Code (Civil Code section 896, et seq.) that codified construction defect litigation in 2002. Most of the publicity is geared toward the pre-litigation standards allowing a builder the right to repair before litigation is commenced by a homeowner. Less focus and attention has been given to the fact that violation of the SB-800 performance standards is being used by plaintiff’s counsel as an additional tool in the plaintiff’s pleading tool box against builders. Closer scrutiny to SB-800 reveals that those provisions should in fact act as a limitation to the pleading tools available to plaintiffs and an additional tool for builders in the defense of cases governed by SB-800.
The typical construction defect complaint contains the boiler plate versions of numerous causes of action. These causes of action include Strict Liability, Negligence, Negligence Per Se, Breach of Contract, Breach of Contract – Third-Party Beneficiary, Breach of Express Warranties, Breach of Implied Warranties, among others. The wide array of causes of action leave a defendant “pinned to the wall” because they require a complex defense on a multitude of contract and tort related causes of action. Furthermore, the statutes of limitations as to these claims widely differ depending upon if the particular defect is considered latent or patent. The truth of the matter remains, no matter what the circumstances, if a construction defect matter ultimately goes to trial, it is inevitable that plaintiffs will obtain a judgment on at least one of these causes of action.
On its own, the Strict Liability cause of action can be a thorn in a defendant’s side. A builder is obviously placing a product into the stream of commerce and strict liability is a tough standard to defend against, particularly when it concerns intricate homes comprised of multiple components that originally sold for hundreds of thousands of dollars. A Negligence cause of action can also be difficult to defend because the duty of care for a builder is what a “reasonable” builder would have done under the circumstances. An interpretation of this duty of care can easily sway a jury that will almost always consist of sympathetic homeowners. A Negligence Per Se cause of action can also leave a defendant vulnerable to accusations that a builder violated the Uniform Building Code or a multitude of other obscure municipal construction-related code provisions during the construction of the home. Lastly, the Breach of Contract cause of action leaves a builder relying on dense and intricate purchase and sale agreements with dozens of addenda which leave the skeptical jurors turned off by what they view as one-side, boilerplate provisions. Ultimately, when a matter is about to go to trial, the complexity of these complaints can benefit a plaintiff and increase a plaintiff’s bargaining power against a defendant who is attempting to avoid a potentially large judgment.
Enter the SB-800 statutes. The SB-800 statutes apply to all homes sold after January 1, 2003. Civil Code section 938 specifically states that “[t]his title applies only to new residential units where the purchase agreements with the buyer was signed by the seller on or after January 1, 2003.” (Civil Code §, 938.) As time progresses, more residential construction defect cases will exclusively fall under the purview of SB-800. Slowly but surely more SB-800 governed litigation is being filed, and its exclusive application is looming on the horizon.
On its surface, this “right to repair” regime has left builders with a lot to be desired despite the fact that it is supposed to allow the builder the opportunity to cure any deficiencies in their product before litigation can be filed by potential plaintiffs. However, the application of the time line for repair has shown to be impractical for anything but the most minor problems involving only small numbers of residential units. Moreover, the fact that the fruits of the builder’s investigation into the claimed defects in the pre-litigation context can freely be used as evidence against it in litigation makes builders proceed with trepidation in responding with a repair. For these reasons, more SB-800 litigation can be expected to result due to the shortcomings of the pre-litigation procedures, and savvy defense counsel should anticipate the issues to be dealt with in presenting the defense of such cases at trial.
This fact should not necessarily be met with fear or disdain. Within the SB-800 statutes, the legislature made it clear that they were creating a new cause of action for construction defect claims, but it further made it clear that this cause of action is a plaintiff’s exclusive remedy. The legislature giveth, but at the same time, the legislature taketh away. Throughout numerous provisions within the SB-800 statutes, the Civil Code states that claims for construction defects as to residential construction are exclusively governed by the Civil Code, and that the Civil Code governs any and all litigation arising under breaches of these provisions. Civil Code section 896 specifically states:
In any action seeking recovery of damages arising out of, or related to deficiencies in, the residential construction … the claimant’s claims or causes of action shall be limited to violation of, the following standards, except as specifically set forth in this title. (Civil Code §, 896.)
Civil Code section 896 then provides approximately fifty-plus standards by which a construction defect claim is assessed under that provision. Civil Code section 896 covers everything from plumbing to windows, and from foundations to decks, and in several instances expressly dictates statutes of limitations as to specific areas of construction that severely truncate the 10-year latent damage limitations period. As for any construction deficiencies that are not enumerated within Civil Code section 896, Civil Code section 897 explicitly defines the intent of the standards and provides a method to assess deficiencies that are not addressed in Civil Code section 896. Civil Code section 897 states:
Intent of Standards
The standards set forth in this chapter are intended to address every function or component of a structure. To the extent that a function or component of a structure is not addressed by these standards, it shall be actionable if it causes damage. (Civil Code §, 897.)
Therefore, Civil Code section 897 acts as a catch-all by which defects that are not covered within Civil Code section 896 can be evaluated on a damage standard mirroring the Aas case (damages must be present and actual). The result of sections 896 and 897 being read in combination is a comprehensive, all-inclusive set of performance standards by which any defect raised by Plaintiffs can be evaluated and resolved under a single SB-800 based cause of action.
Civil Code section 943 makes clear that a cause of action for violation of SB-800 performance standards is a plaintiff’s sole remedy for a residential construction defect action. Specifically, Civil Code section 943 states:
Except as provided in this title, no other cause of action for a claim covered by this title or for damages recoverable under 944 is allowed. In addition to the rights under this title, this title does not apply to any action by a claimant to enforce a contract or express contractual provision, or any action for fraud, personal injury, or violation of a statute. (Civil Code §, 943.)
Civil Code section 944 provides the method for computing damages within a construction defect action, as follows:
If a claim for damages is made under this title, the homeowner is only entitled to damages for the reasonable value of repairing any violation of the standards set forth in this title, [and] the reasonable cost of repairing any damages caused by the repair efforts… . (Civil Code §, 944.)
A cursory review of these statutes yields the conclusion that the legislature was attempting to create an exclusive cause of action that trumps all other causes of action where SB-800 applies. The remedy available to plaintiffs is limited to that allowed by the Civil Code. As noted above, “[n]o other cause of action for a claim covered by this title…is allowed.” (Civil Code §, 943.) Therefore, Civil Code sections 896, 897, 943, and 944 specifically prohibit the contract-based and tort-based causes of action typically pled by plaintiffs.
Plaintiff’s counsel has seized upon the language of section 943 to advance the argument that SB-800 still allows a plaintiff to advance typical contract and tort based causes of action. On the surface, this argument may seem compelling, but a minimum of scrutiny of the express language of section 943 dispels this notion. Section 943 says that it provides rights “[i]n addition” to those under the SB-800 Civil Code provisions. Clearly, the language in section 943 is intended to expressly underscore the fact that a plaintiff is not precluded from seeking relief in addition to that allowed under SB-800 for damages not arising from a breach of the SB-800 standards or for damages in addition to those recoverable under Section 944. This language does not provide an unfettered license to bring a Strict Liability, Negligence or other cause of action against a builder where SB-800 applies.
In fact, this language only keeps the door open for plaintiffs to pursue such causes of action not arising from a breach of the SB-800 standards should there be such supporting allegations. For example, if a plaintiff alleges that a builder breached an “express contractual provision” related to the timing of the completion of the home and close of escrow, and the contract specifies damages in this regard, a plaintiff may have a viable separate cause of action for Breach of Contract for recovery of those damages precisely because that is not an issue expressly dealt with in SB-800 in the performance standards under sections 896 and 897, or in the damage recovery terms under 944. As it stands, the vast majority of complaints are seeking redress for violation of the same primary right; that is, defects specifically outlined in Section 896 and 897 or which result in damages as stated in Section 944.
So, how does a builder defend against a complaint that contains multiple causes of action regarding construction defects for a home sold after January 1, 2003? There are numerous ways to approach this. First and foremost, these superfluous and improper causes of action can be attacked by demurrer seeking dismissal of all causes of action other than the cause of action alleging violation of SB-800. If the the time period within which to file a demurrer has passed already, a motion for judgment on the pleadings can be utilized to attack the improper causes of action in the same way as a demurrer can be used for this purpose.
The limitation to a demurrer or motion for judgment on the pleadings is that the judge is restricted to viewing only the four corners of the pleading when making a ruling. It is typical for plaintiffs’ counsel to cleverly (or one might even say, disingenuously) leave the complaint purposely vague to avoid a successful defense attack on the pleadings by not including the original date the residence was sold. In that instance, a motion for summary adjudication can be used to attack a plaintiff’s complaint. By simply providing evidence that the homes were originally sold after January 1, 2003, the improper causes of action should be subject to dismissal by summary adjudication. If the plaintiff is a subsequent purchaser, the builder still has recourse to enforce the pleading limitations under SB-800. Civil Code section 945 states that “[t]he provisions, standards, rights, and obligations set forth in this title are binding upon all original purchasers and their successors-in-interest.” (Civil Code §, 945.)
Attacking a plaintiff’s complaint to eliminate multiple causes of action can have numerous benefits. The practical result is that a plaintiff will only have one viable cause of action. The advantage is that the SB-800 performance standards include the defined performance standards and shortened statutes of limitations periods with regard to specific issues. Furthermore, as to defects which are not specifically provided for in Civil Code section 896, Civil Code section 897 requires a proof of actual damages. Therefore, a plaintiff must provide evidence of current damages and not simply conditions that may potentially cause damage in the future.
The Appellate Courts have yet to directly address and interpret these SB-800 provisions. The time for that is undoubtedly drawing near. For now, however, plaintiffs will have to find ways to accurately plead construction defect claims within the confines of one cause of action for breach of the performance standards enumerated within the Civil Code.
Printed courtesy of Lorber, Greenfield & Polito, LLP. Mr. Patel can be contacted at spatel@lorberlaw.com and Mr. Verbick at tverbick@lorberlaw.com.
Read the court decisionRead the full story...Reprinted courtesy of
Generally, What Constitutes A Trade Secret Is A Question of Fact
February 01, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn construction, contractors maintain competitiveness by compiling, combining, utilizing, or developing proprietary and unique systems. The systems can be from a cost standpoint (determining general conditions or general requirement costs and percentages including percentages for insurance) or can be with respect to certain construction assembly or delegated design components. Such proprietary and unique systems are trade secrets to the contractors and efforts are taken to identify such information as confidential when proposing on a project. Contractors would not want such systems disclosed to others because it would dilute and impact what they believe is valuable and makes them competitive in the marketplace.
Florida’s Uniform Trade Secret Act (“FUTSA”) creates a statutory cause of action for the misappropriation of trade secrets. (FUTSA is set forth in Florida Statute s. 688.001 en seq.) FUTSA displaces or “preempts all claims [such as common law claims] based on misappropriation of trade secrets.” Alphamed Pharmaceuticals Corp. v. Arriva Pharmaceuticals, Inc., 391 F.Supp.2d 1148, 1167 (S.D.Fla. 2005). See also Fla. Stat. s. 688.008.
Florida Statute s. 688.002 (found here) defines the terms “trade secret” and “misappropriation.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
State of Texas’ Claims Time Barred by 1982 Nuclear Waste Policy Act
June 13, 2018 —
Anthony B. Cavender - Gravel2Gavel Construction & Real Estate Law Blog On June 1, the U.S. Court of Appeals for the Fifth Circuit decided the case of State of Texas v. U.S., et al. The Court of Appeals held that the petition for mandamus filed by the State of Texas essentially seeking to compel the Nuclear Regulatory Commission (NRC) to establish a schedule for the operation of the Yucca Mountain, NV nuclear waste depository was untimely filed. The depository is very controversial in Nevada, and as a consequence, none of the many deadlines established by Congress have been met.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, Pillsbury Winthrop Shaw Pittman LLPMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Will the Hidden Cracks in the Bay Bridge Cause Problems During an Earthquake?
June 26, 2014 —
Beverley BevenFlorez-CDJ STAFFDespite a “no cracks” welding code and contract provision for the San Francisco-Oakland Bay Bridge, in 2008 Caltrans proceeded with the project despite welding cracks created by the Chinese firm hired to build the roadway, according to the Sacramento Bee. By the time the cracks had been discovered, the costs were at $6.5 billion and climbing, and fixing the cracks would be time-consuming and expensive.
However, there is some dispute as to rather the welding “cracks represent a hazard to the traveling public.”
“Examine history,” Brian Maroney, Caltrans’ chief engineer for the bridge, said in a recent interview by the Sacramento Bee. “… Caltrans reviewed major quakes around the globe and never found a case in which weld cracks caused bridge-roadway fractures.”
However, the Sacramento Bee reported that there was a case where welding cracks led to fractures. For instance, after the southern California earthquake in 1994 centered in Northridge, the Santa Clara River Bridge “suffered several fractures in steel girders. The breaks were traced to tiny cracks in welds, likely present before the quake, and worsened by vibrations of heavy trucks passing overhead. When the quake struck, the girders fractured.”
The Santa Clara bridge did not collapse. Sacramento Bee claimed it remained standing because the I-beam-shaped girders were “not fracture-critical.” However, the Bay Bridge’s “roadway consists of box-girder segments welded together. In effect, they create one contiguous, fracture-critical girder,” Abolhassan Astaneh-Asl, UC Berkeley engineering professor told the Sacramento Bee. “If welds crack and grow rapidly during a large quake, the entire roadway could fail.”
Read the court decisionRead the full story...Reprinted courtesy of