Teaching An Old Dog New Tricks: The Spearin Doctrine and Design-Build Projects
October 30, 2018 —
John Castro - Gordon & Rees Construction Law BlogThe United States District Court for the Southern District of California has now held that the Spearin doctrine applies to design-build subcontractors where the subcontractor is expected to design a portion of their work. The case is United States for the use and benefit of Bonita Pipeline, Inc., et al. v. Balfour Beatty Construction, LLC, et al. (“Bonita Pipeline”) (Case No. 3:16-cv-00983-H-AGS).
In Bonita Pipeline, a subcontractor sued the general contractor and its sureties alleging breach of contract, breach of implied warranty, declaratory relief, and recovery under the Miller Act. The subcontractor then filed a motion for partial summary judgment against the general contractor on its declaratory relief cause of action, seeking a finding that the general contractor could not shift legal responsibility for its defective plans and specifications to the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
John Castro, Gordon & Rees Scully MansukhaniMr. Castro may be contacted at
jcastro@grsm.com
Three-Year Delay Not “Prompt Notice,” But Insurer Not “Appreciably Prejudiced” Either, New Jersey Court Holds
November 04, 2019 —
Anthony L. Miscioscia and Timothy A. Carroll - White and Williams LLPIn Harleysville Preferred Insurance Company v. East Coast Painting & Maintenance, LLC, 2019 U.S. Dist. LEXIS 135295 (D.N.J. Aug. 12, 2019) (East Coast Painting), the U.S. District Court for the District of New Jersey held that an insurer, which received notice of a bodily injury accident three years after it happened, was not “appreciably prejudiced” by such late notice, even as the court acknowledged notice three years later did not satisfy the policy’s “prompt notice” condition. The court also held that the policy’s “Operational Exclusion,” which excluded coverage for bodily injury arising out of the operation of “cherry pickers and similar devices,” did not apply because the accident arose out of the use of a “scissor lift,” which is not a device similar to a cherry picker.
East Coast Painting arose out of a Queens, New York bridge-painting project, during which an employee of the insured, East Coast Painting and Maintenance LLC was injured while “standing on a scissor lift mounted to the back of a truck,” owned and operated by East Coast. The employee sued various project-related entities which, in turn, joined East Coast as a defendant. East Coast sought coverage under its business auto policy, and the insurer agreed to defend the insured under a reservation of rights. The insurer subsequently sought a declaration that it did not owe coverage based on, among other things, the policy’s “Operational Exclusion,” and the insured’s failure to satisfy the policy’s “prompt notice” condition. The insurer moved for summary judgment on both of those bases, but the court in East Coast Painting denied the motion.
As for the insurer’s “prompt notice” defense, the court in East Coast Painting concluded that, the insured’s notice to the insurer was not prompt because it did not receive notice until three years after the accident. But, the court added, the inquiry does not end there. “[T]his Court must determine whether [the insurer] was appreciably prejudiced by that delay.” Reviewing the facts, the court held that the insurer was not “appreciably prejudiced,” even though during the three-year delay the lift truck was “not properly maintained” or “in the same condition it was at the time of the Accident.” The court observed that the insurer had “ample other evidence with which it can defend itself,” such as experts who inspected the lift truck and opined about the cause of the accident.” [Emphasis added.] Further, “there are multiple contemporaneous accident reports,” “a list of the East Coast employees on site at the time,” “photographs of the lift truck and its location when [the employee] was injured,” and “depositions of [the employee] and others regarding the events at issue.” Thus, the court held, the insurer was not prejudiced and summary judgment was inappropriate.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams LLP and
Timothy A. Carroll, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Feds Outline Workforce Rules for $39B in Chip Plant Funding
April 10, 2023 —
James Leggate - Engineering News-RecordSemiconductor chip producers must pay their construction workforce prevailing wages and will be “strongly encouraged” to use project labor agreements if they want a piece of the $39 billion available in federal funding to support fabrication plant construction, expansion or modernization projects, U.S. Commerce Secretary Gina Raimondo says.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Construction Defect Bill a Long Shot in Nevada
June 28, 2013 —
CDJ STAFFConstruction defect reform may still be on the table in Nevada, according to the Reno Gazette Journal. Assembly member Pat Hickey got a committee hearing for Assembly Bill 504 on Sunday. The bill is backed by the construction industry and opposed by trial lawyers. Hickey told the Assembly Commerce and Labor committee that “this bill is not perfect, I would like for it to do more,” and said that without changes Nevada will “continue to reward litigation over resolution.”
AB504 would, among other provisions, provide some protection to subcontractors from the actions of general contractors, though Ira Hansen, an assembly member from Sparks and the owner of a plumbing business, called it a “backhanded slap.” The Gazette noted that similar language pertaining to subcontractors was in AB367, which is sponsored by Democrats. Hickey and Hansen are both Republicans.
Read the court decisionRead the full story...Reprinted courtesy of
No Friday Night Lights at $60 Million Texas Stadium: Muni Credit
March 26, 2014 —
Darrell Preston and Aaron Kuriloff – BloombergPervasive cracking has shuttered the $60 million home of a high-school football championship team in Texas after less than two years. Investors in the tax-free bonds that paid for the stadium are unscathed.
Taxpayers in Allen Independent School District north of Dallas and the $29 billion Texas Permanent School Fund, a state bond insurer, are responsible for $119 million of debt that paid for the venue and other facilities, leading officials to find a new site for graduation and possibly games after closing 18,000-seat Eagle Stadium last month.
The development suggests the fund, created in 1854 to help pay for education, shouldn’t be used for stadiums, said Colby Harlow, president of hedge fund Harlow Capital Management. The Permanent Fund has top credit ratings and secures about $55 billion of bonds, according to the Texas Education Agency. The pool has at times reached the limit of debt it can back, preventing districts from accessing it. The guarantee is still a boon to bondholders.
Mr. Merelman may be contacted at smerelman@bloomberg.net; Mr. Sillup may be contacted at msillup@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Darrell Preston and Aaron Kuriloff, Bloomberg
10-story Mass Timber 'Rocking' Frame Sails Through Seismic Shake Tests
June 19, 2023 —
Nadine M. Post - Engineering News-RecordA 10-story mass timber “rocking” frame, designed to be resilient enough to withstand powerful earthquakes with little or no structural damage, proved its worth May 9 during seismic simulations at the largest high-performance outdoor shake table, located at the University of California San Diego.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Bel Air Mansion Construction Draws Community Backlash
December 17, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to the New York Times, a Bel Air hillside mansion in Los Angeles has outraged neighbors who refer to the unfinished, 30,000 square foot and almost 70 feet high building as “the Starship Enterprise.” Despite legal violations such as tearing down the original structure without the city’s permission, the height being twice the legal limit, and digging into the hillside though the site is an “earthquake-induced landslide area,” the case has not progressed much in four years because the actual owner is a shell company.
The New York Times summarized the issues at 901 Strada Vecchia as follows: “After the unapproved teardown and leveling of the hillside, the construction team did ask permission to grade the hill but used a survey that made it appear that workers had not already removed significant loads of dirt. Then they joined two buildings that were supposed to be separate and built so high that they drastically violated the city’s height limit.”
Read the court decisionRead the full story...Reprinted courtesy of
California’s Prompt Payment Laws: Just Because an Owner Has Changed Course Doesn’t Mean It’s Changed Course on Previous Payments
April 20, 2016 —
Garret Murai – California Construction Law BlogWe’ve written before about California’s prompt payment laws which are designed to help contractors get paid in a timely and orderly fashion, which is always nice, right?
California’s prompt payment laws require that project owners pay their direct contractors, who are in turn required to pay their subcontractors who are in turn required to pay their sub-subcontractors and so on within certain statutorily set deadlines, or be subject to prompt payment penalties nearly as high as the interest you pay on your credit cards.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com