Design Professional Asserting Copyright Infringement And Contributory Copyright Infringement
May 01, 2019 —
David Adelstein - Florida Construction Legal UpdatesStandard form construction contracts between an owner and design profesional will address copyright protection, as well as other contractual protections, associated with a design professional’s “instruments of service.” An owner negotiating an agreement with a design professional should consider alternative language that broadens the scope of the contractual license given to it with respect to the use of the design. Regardless, a design professional’s copyright infringement claim is still a challenging claim to ultimately prevail on. While a design professional may likely survive the motion to dismiss stage in a copyright infringement claim, whether it survives the summary judgment stage is another, more challenging, story.
“To state a claim for copyright infringement a plaintiff [design professional] must assert [and prove the following two prongs]: ‘(1) ownership of a valid copyright, and (2) copying of constituent elements of the work that are original.’” Robert Swedroe Architect Planners, A.I.A., P.A. v. J. Milton & Associates, Inc., 2019 WL 1059836, *3 (S.D.Fla. 2019) quoting Feist Publ’ns, Inc. v. Rural Tel. Serv. Co., Inc., 499 U.S. 340, 361 (1991).
In the first prong, the design professional must establish it complied with statutory formalities to own a valid copyright. Id.
In the second prong, the design professional must establish that the defendant copied constituent elements that are original. Id.
There is also a claim known as contributory copyright infringement.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dadelstein@gmail.com
Enerpac Plays Critical Role in Industry-changing Discovery for Long Span Bridges at The University of Nebraska-Lincoln
April 19, 2022 —
EnerpacMENOMONEE FALLS, Wis. (April 18, 2022) – Three years ago when Marc Maguire, assistant professor of construction programs at the University of Nebraska-Lincoln, started investigating a new stranded wire product for bridge girder reinforcing he thought the best strands for bridge construction were the industry standard 7-wire strands.
After running a multitude of analyses, Maguire and student researchers found that 19-wire 1-1/8 in. diameter strands outperform the typical 7-wire 1-1/6 in. diameter strands and allow bridges to reach unprecedented lengths. Further tests conducted by the Durham School of Architectural Engineering and Construction with the help of Enerpac hydraulic tools examined the bond strength, force transfer, and development length of the 19-wire strands.
"Traditionally, 19-wire strands are not often used in the U.S. because they are not widely available and they are much larger than standard strands," said Maguire. "We wanted to show that there was an alternative option to the common 7-wire strand--one that can perform at the same level, if not better."
About Enerpac
Enerpac is a global market leader in high pressure hydraulic tools, controlled force products, portable machining, on-site services and solutions for precise positioning of heavy loads. As a leading innovator with a 110-year legacy, Enerpac has helped move and maintain some of the largest structures on earth. When safety and precision matters, elite professionals in industries such as aerospace, infrastructure, manufacturing, mining, oil & gas and power generation rely on Enerpac for quality tools, services and solutions. For more information, visit www.enerpac.com.
Read the court decisionRead the full story...Reprinted courtesy of
San Francisco Office Secures Defense Verdict in Legal Malpractice Action
November 25, 2024 —
Lewis Brisbois NewsroomSan Francisco, Calif. (October 31, 2024) - After a ten-day jury trial in San Francisco Superior Court, Partner Alex Graft recently secured a defense verdict in a legal malpractice action arising out of underlying litigation with the claimants’ homeowners association. The claimants alleged his client attorneys negligently advised them that the terms of the settlement agreement would result in the creation of a so-called independent board of directors for the homeowners association. It did not come to fruition. After the attorneys withdrew, they sued for their outstanding fees, which elicited a cross-complaint alleging malpractice, breach of fiduciary duty, breach of contract and negligent misrepresentation.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Delays in Filing Lead to Dismissal in Moisture Intrusion Lawsuit
September 09, 2011 —
CDJ STAFFThe Alabama Court of Civil Appeals has upheld a summary judgment in the case of Franklin v. Mitchell. Walter Mitchell, doing business as Southern Classic Construction built a new home for the Franklins. The Franklins moved into the home in October 2001. In April 2006 they discovered sagging floors in both the bathroom and kitchen. They contacted Mitchell who suggested the flooring might be defective. The Franklins spent eight months attempting to contact the flooring manufacturer.
In March 2007, the Franklins had the home inspected. The sagging was determined to be due to a loss of strength in the decking because of condensation from the air conditioning system. Air returns were not properly sealed and drawing moisture into the structure. There was mold on the decking and floor joints.
When Mitchell was contacted by the Franklins, he told them his one-year warranty had expired but had the HVAC subcontractor, Southern Mechanical Heating & Air (owned by Mitchell’s father, Jim Mitchell), look at the situation. SMHA replaced and braced subfloors. Later, they entered the crawl space to tape ducts, seal the air return, and insulate the air vent housing. The Franklins were not satisfied with the repairs, as not all the ducts were taped, nor were the air vent housings insulated.
Franklin complained to Walter Mitchell who again cited his one-year warranty. Jim Mitchell said he would not report complaints to his insurer, stating that the repairs were unnecessary, that the work had been done correctly in the first place, and it was only done at the request of Walter Mitchell.
In February 2009, the Franklins sued Walker Mitchell. Mitchell denied the claims, citing in part the statute of limitations. Mitchell also filed complaints against three subcontractors, including his father’s firm. Mitchell received a summary judgment as the case started after Alabama’s six-year statute of limitations.
The appeals court rejected the Franklin’s argument that the claim of damage did not start until they were aware it was due to a construction defect. The court noted that as Walter Mitchell was licensed as a “residential home builder, the statute the Franklins cite did not apply, as it concerns architects, engineers, and licensed general contactors.”
Nor did they feel that Mitchells’ claim that his warranty had expired were sufficient to override the statute of limitations, quoting an earlier case, “Vague assurances do not amount to an affirmative inducement to delay filing suit.” Their claim of subsequent negligent repairs was rejected because Mitchell did not direct the specific actions taken by his father’s firm.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Builder’s Be Wary of Insurance Policies that Provide No Coverage for Building: Mt. Hawley Ins. Co v. Creek Side at Parker HOA
July 31, 2013 —
Brady Iandiorio, Higgins, Hopkins, McLain & Roswell, LLCOn the heels of a recent order regarding coverage under a Comprehensive General Insurance policy issued by Mt. Hawley Insurance Company (“Mt. Hawley”), builders should be very wary of CGL policies providing no coverage for property damage.
On January 8, 2013, District Court Judge R. Brooke Jackson granted a motion for declaratory judgment filed by Mt. Hawley. The order states that the subject insurance policies issued by Mt. Hawley to Mountain View Homes II, LLC (“MV Homes”), the builder developer of the Creek Side at Parker development (the “Project”), did not provide coverage for any of the work performed by MV Homes or its subcontractors on the Project.
MV Homes originally began construction on the Project in 2002 and completed construction in 2005. MV Homes was insured by National Fire and Marine Insurance Company (“National Fire”) and Mt. Hawley. In December 2008, Creek Side at Parker Homeowners Association, Inc. (“the HOA”) served notice on MV Homes. The HOA then instituted a construction defect lawsuit on June 1, 2009 against MV Homes and others. MV Homes initially demanded a defense and indemnity from National Fire, which provided a defense. Then, after two years, MV Homes demanded a defense and indemnity from Mt. Hawley in July 2011. Mt. Hawley denied coverage and did not provide a defense. The case was settled soon after, and National Fire reserved or assigned claims against Mt. Hawley.
Read the court decisionRead the full story...Reprinted courtesy of
Brady IandiorioBrady Iandiorio can be contacted at
Iandiorio@hhmrlaw.com
Rights Afforded to Employees and Employers During Strikes
October 16, 2018 —
Wally Zimolong - Supplemental ConditionsOne of the most powerful weapons in labor’s arsenal is a strike. Like most powerful weapons there is a dichotomy in a strike. On one hand, it can bring about concessions from management that labor seeks. On the other hand, it can permanently change the relationship between management and labor. However, one thing is certain, strike are – to put it mildly – chaotic.
During this chaotic period, employees and employers may wonder what rights they have during union-initiated strikes. We provide some brief explanations below, along with how union litigation can help enforce your rights.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Why Employees Are Taking Ownership of Their Architecture Firms
January 22, 2024 —
Kriston Capps - BloombergThe architecture firm BNIM has always been a leader on sustainable design. In the late 1980s, principal emeritus Bob Berkebile was one of the first architects to push the industry to take the idea of green buildings seriously. Then-President Bill Clinton even recruited him to lead a climate-minded restoration of the White House. Berkebile and his Kansas City, Missouri–based firm — he’s the “B” in BNIM, alongside Tom Nelson, David Immenschuh and Steve McDowell — received top honors from the American Institute of Architects in 2011, among many other accolades.
Now the firm behind such projects as the US Embassy expansion in Kampala, Uganda, and a proposed South Loop park to deck over a highway in downtown Kansas City hopes to stand out in another way. In October, BNIM announced its transition to an employee stock ownership plan, or ESOP. The firm is one of a handful in the industry to recently embrace the employee-ownership model, following similar moves in 2021 by SHoP Architects and Zaha Hadid Architects.
Read the court decisionRead the full story...Reprinted courtesy of
Kriston Capps, Bloomberg
Update: Amazon Can (Still) Be Liable in Louisiana
December 31, 2024 —
Michael Ciamaichelo - The Subrogation StrategistOn November 25, 2024, in Pickard v. Amazon.com, Inc., No. 5:20-cv-01448, 2024 U.S. Dist. LEXIS 215377, the United States District Court for the Western District of Louisiana (District Court) ruled that Amazon.com, Inc. (Amazon) could be liable for manufacturer-seller liability under the Louisiana Products Liability Act (LPLA) for a defective product sold by a third-party seller through the “Fulfillment by Amazon” program (FBA). The court also dismissed two tort claims against Amazon as follows: (i) Amazon does not qualify as a “seller” for purposes of non-manufacturer seller liability (because passing title is required for that claim); and (ii) there is insufficient evidence to prove the decedent, Archie Pickard (Pickard), relied on Amazon’s safety practices when purchasing the defective product, precluding a claim for negligent undertaking.
Background
Pickard died from injuries sustained in a house fire allegedly caused by a defective battery charger he purchased on Amazon. Jisell, a Chinese company and a third-party seller, manufactured and sold the charger. Amazon never took title to the charger but stored it in its warehouse and delivered it to Pickard through the FBA. Pickard’s children filed a wrongful death lawsuit against Amazon alleging three claims: (i) manufacturer-seller liability under the LPLA; and tort-based claims of (ii) non-manufacturer seller liability and (iii) negligent undertaking. After Amazon moved for summary judgment on all claims, the District Court certified questions to the Supreme Court of Louisiana (Supreme Court) seeking guidance as there was minimal guidance regarding the application of products claims to online marketplaces.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Ciamaichelo, White and Williams LLPMr. Ciamaichelo may be contacted at
ciamaichelom@whiteandwilliams.com