Formal Request for Time Extension Not Always Required to Support Constructive Acceleration
April 25, 2022 —
David Adelstein - Florida Construction Legal UpdatesDoes a constructive acceleration claim require the contractor to always request an extension of time which is then denied by the owner? While this is certainly the preference and the contractor should be requesting an extension of time as a matter of course for an excusable delay, the answer is NO! in certain circumstances. This is conveyed in the factually detailed case discussed below where a formal request for an extension of time was not required for the contractor to support its constructive acceleration claim.
But first, what is constructive acceleration:
Constructive acceleration “occurs when the government demands compliance with an original contract deadline, despite excusable delay by the contractor.” The Federal Circuit in Fraser defined the elements of constructive acceleration as follows:
(1) that the contractor encountered a delay that is excusable under the contract; (2) that the contractor made a timely and sufficient request for an extension of the contract schedule; (3) that the government denied the contractor’s request for an extension or failed to act on it within a reasonable time; (4) that the government insisted on completion of the contract within a period shorter than the period to which the contractor would be entitled by taking into account the period of excusable delay, after which the contractor notified the government that it regarded the alleged order to accelerate as a constructive change in the contract; and (5) that the contractor was required to expend extra resources to compensate for the lost time and remain on schedule.
Nova Group/Tutor-Saliba v. U.S., 2022 WL 815826, *42 (Fed.Cl. 2022) quoting Fraser Constr. Co. v. U.S., 384 F.3d 1354, 1361 (Fed. Cir. 2004) (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Testimony from Insureds' Expert Limited By Motion In Limine
October 21, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court considered the scope of testimony to be offered by the insureds' expert regarding a policy written for sanitation districts. Binghamton-Johnson City Joint Sewage Bd. v. Am. Alternative Ins. Corp., 2015 U.S. Dist. LEXIS 112210 (N.D. N.Y. Aug. 25, 2015).
The city of Binghamton and the city's Sewage Board sued American Alternative Insurance Corporation (AAIC) for coverage for a collapsed wall. AAIC sought the limit to testimony of the insureds' expert, Paul B. Nielander, through a motion in limine.
AAIC argued that Nielander was not qualified as an expert in interpreting insurance policies. His knowledge and experience was limited to insurance practices in other states and the words contained in policies other than AAIC policies. He had no experience with (i) negotiating, drafting, or performing under an AAIC policy, (ii) handling claims or interpreting policies written in New York State, or (iii) drafting policies or otherwise participating in what he conceded was a "niche market" of providing insurance to sanitation districts. Further, Neilander was not qualified to offer expert analysis of when the structural failure of the wall occurred because he had no training or experience as an engineer.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
New York Developer gets Reprieve in Leasehold Battle
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to The Real Deal, a “Manhattan Supreme Court judge granted an injunction in favor of Tribeca Mews developer Thurcon Properties, which is fighting to keep the leasehold on several adjacent parcels in connection with a certificate of occupancy.”
In 2013, Thurcon Properties was sued by the condo board, who claimed “the certificate of occupancy was pushed back at the building due to a number of construction defects.” The Real Deal further reported that the condo board “claimed the developers sold about 10 units to an outside buyer, and took some of the proceeds for themselves.”
Recently, a judge “ordered Feldman Heritage, owner of the ground lease at 125 Church and several adjacent sites, to appear in court on April 30,” because he wants the lease owner “to show why Thurcon should not be given the chance to cure the alleged lease default.”
Read the court decisionRead the full story...Reprinted courtesy of
BHA has a Nice Swing Donates to CDCCF
May 21, 2014 —
Beverley BevenFlorez-CDJ STAFFBert L. Howe & Associates (BHA) would like to congratulate the winners of the BHA Has a Nice Swing golf game for charity. With the help of the participants, BHA was able to donate $1800 to the Construction Defect Community Charitable Foundation (CDCCF). CDCCF was established to provide financial assistance for active members of the construction defect community who have uninsured expenses because of a disability, sickness, and/or the death of a community member or their immediate family member.
BHA would also like to congratulate their booth’s raffle winners. Prizes included an iPad Air, four sets of Dodger tickets, a Day at the Del Mar Races, and Best Buy gift cards.
Read how the CDCCF assists the construction defect community... Read the court decisionRead the full story...Reprinted courtesy of
Consider the Risks Associated with an Exculpatory Clause
November 24, 2019 —
David Adelstein - Florida Construction Legal UpdatesAn exculpatory clause in a contract is a clause aimed at relieving another party from certain liability. A disclaimer and insulation from liability. Obviously, if you are the party relieving the other party from liability, you want to consider this risk including the potential enforceability of this risk if something goes wrong. If you are the party asking for the insulation from liability, you do not want to create an exculpatory provision that disclaims and insulates you of all liability arising from the contract as it may create an illusory effect – that the agreement is nothing but a naked promise on your end because your promise is fully disclaimed and you are insulated from liability if you break your promise. This could result in an unenforceable contract.
The validity of such an exculpatory clause was at-issue in Pier 1 Cruise Experts v. Revelex Corp., 2019 WL 3024618 (11thCir. 2019). Although not a construction dispute, the exculpatory clause in this case was with two fairly sophisticated parties and expressly insulated one of the contracting parties from “any…damages regardless of kind or type…whether in contract, tort (including negligence), or otherwise.” Pier 1 Cruise Experts, 2019 WL at *7. This is a powerful exculpatory clause because it could be broadly construed to insulate that party from its own breaches of the contract.
In Florida:
[A]n exculpatory clause is enforceable so long as (1) the contracting parties have equal bargaining power and (2) the clause’s provisions are clear and unambiguous. With respect to the latter requirement, ‘the intention to be relieved from liability [must be] made clear and unequivocal and the wording must be so clear and understandable that an ordinary and knowledgeable person will know what he is contracting away.” In the same vein, exculpatory clauses are ‘strictly construed against the party seeking to be relieved of liability.’
Pier 1 Cruise Experts, 2019 WL at *7 (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Privileged Communications With a Testifying Client/Expert
June 10, 2019 —
Shannon M. Warren - The Subrogation StrategistIn
In re City of Dickinson, 568 S.W.3d 642 (Tex. 2019), the Supreme Court of Texas recently assessed whether a client’s emails with its counsel were subject to disclosure after the client was designated as a testifying expert witness. In re City of Dickinson involved a coverage dispute between a policyholder and its insurer. The policyholder moved for summary judgment on the issue of causation, essentially alleging that its insurer did not pay all damages caused by Hurricane Ike. In responding to the motion, the insurer relied upon an affidavit by one of its employees, a claims examiner, that included both factual testimony and expert witness testimony.
The policyholder subsequently filed a motion to compel, seeking the production of emails between the claims examiner and the insurer’s counsel that were generated while the affidavit was being drafted. The emails contained numerous revisions of the affidavit. The insurer objected, asserting that the emails were protected by the attorney-client privilege and were generated in the course of the rendition of legal services.
The trial court granted the motion to compel, ordering production. Ultimately, after a series of appeals, the Supreme Court had to decide whether the documents in dispute were subject to discovery. In resolving this issue, the court examined the rules pertaining to expert disclosures. As noted by the court, the rules authorize the production of all documents provided to a testifying expert witness. Thus, the court was faced with determining if its rules required the disclosure of documents that are also subject to the attorney-client privilege.
Read the court decisionRead the full story...Reprinted courtesy of
Shannon M. Warren, White and WilliamsMs. Warren may be contacted at
warrens@whiteandwilliams.com
History and Gentrification Clash in a Gilded Age Resort
October 05, 2020 —
Alex Ulam - BloombergNewport, Rhode Island, is a small New England beachfront town with a permanent population of 26,000 and an amazing collection of historic homes. Billed as “America’s First Resort,” the 350-year-old city on Aquidneck Island hosts more than 3 million tourists every year. They come for the boating, the famous folk and jazz festivals (both canceled this summer), and the architecture.
The narrow streets of the Point along the waterfront are lined with hundreds of modest homes from the early 1700s, one of the largest ensembles of colonial architecture in the country. On Historic Hill sits an assortment of grander antebellum, classical and Gothic Revival structures from the latter part of the 18th and early to mid-19th century, many built by Southern plantation owners. Newport also boasts what is probably the most opulent thoroughfare in the country, a several-mile stretch of Bellevue Avenue lined with shade trees and palatial limestone mansions built by Gilded Age robber barons and industrialists.
Read the court decisionRead the full story...Reprinted courtesy of
Alex Ulam, Bloomberg
Insurance Alert: Insurer Delay Extends Time to Repair or Replace Damaged Property
November 26, 2014 —
Valerie A. Moore & Christopher Kendrick – Haight Brown & Bonesteel LLPIn Stephens & Stephens XII v. Fireman's Fund Ins. (No. A135938, filed November 24, 2014), the plaintiffs obtained property insurance on a warehouse. Within a month, it was discovered to be stripped of all wiring and metal. Fireman's Fund paid for emergency repairs but nothing more, concerned that the damage had occurred outside the policy period.
The policy provided for valuation of either "replacement cost," meaning the expenditure required to replace the damaged property with "new property of comparable material and quality," or "actual cash value," defined as the actual, depreciated value of the damaged property. For replacement cost, Fireman’s Fund was not required to pay "until the lost or damaged property is actually repaired ... as soon as reasonably possible after the loss or damage," and only "[t]he amount [the insured] actually spend[s]...."
In the subsequent bad faith lawsuit, the jury awarded the full cost of repair, despite there being no repairs. The appeals court reversed, holding that there was no right to an immediate award for the costs of repairing the damage; however, the court nonetheless held that the insured was entitled to a "conditional judgment," awarding those costs if repairs were actually made.
Reprinted courtesy of
Valerie A. Moore, Haight Brown & Bonesteel LLP and
Christopher Kendrick, Haight Brown & Bonesteel LLP
Ms. Moore may be contacted at vmoore@hbblaw.com; Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of