How Small Mistakes Can Have Serious Consequences Under California's Contractor Licensing Laws.
February 15, 2018 —
Eric Reed - Myers, Widders, Gibson, Jones & Feingold, LLPIn construction, some risks have nothing to do with how well a contractor executes a project. Licensing problems is one of these risks. Even a brief lapse caused by an unintentional administrative error can give the CSLB grounds to discipline a contractor, or enable a customer to seek disgorgement and other remedies provided by Business and Professions Code section 7031. This article discusses five tips for mitigating the liabilities associated with licensing problems.
Tip 1: Take workers' compensation insurance very seriously. Workers’ compensation insurance problems can trigger license suspension in California. Business and Professions Code section 7125.4 calls for automatic suspension if a contractor cannot provide proof of workers’ compensation insurance for any period of time. This is particularly serious for residential remodelers who claim exemption for workers’ compensation but are later discovered – usually during litigation with a homeowner – to have “off the books” workers helping them. Courts can declare the contractor retroactively unlicensed under these circumstances and order it to disgorge,
i.e., to pay back, every penny paid by the customer for the entire project (even for materials). (Bus. & Prof. Code, § 7031, subd. (b);
Wright v. Issak (2007) 149 Cal.App.4th 1116.) The contractor will also find itself unable to collect any amounts owed to it by the customer. (Bus. & Prof. Code, § 7031, subd. (a).)
Tip 2: Watch out for licensing confusion after a merger or acquisition. The economic downturn of 2008 and 2009 resulted in consolidation throughout the building industry. The newly merged or acquired entities often allowed redundant licenses to expire, assuming they could complete all pending projects under the umbrella of the acquiring company's license. Many learned this was a mistake the hard way. Armed with the California Supreme Court's opinion in
MW Erectors, Inc. v. Niederhauser Ornamental & Metal Works Co., Inc. (2005) 36 Cal.4th 412, customers began refusing to pay invoices and demanding disgorgement under Business and Professions Code section 7031 because the original contractor did not maintain licensure “at all times.” Many of these customers succeeded.
Tip 3: If a license suspension has occurred or is imminent, prepare to prove substantial compliance. Section 7031(a) and (b) give a disgruntled or indebted customer every incentive to capitalize on a contractor's licensing problems. Subdivision (e) is where a contractor must turn to protect its interests if this happens. It allows the contractor to prove “substantial compliance” with licensing requirements and avoid (a)’s and (b)’s sharp edges if it can show the following:
(1) The contractor “had been duly licensed as a contractor in this state prior to the performance of the act or contract”;
(2) It “acted reasonably and in good faith to maintain proper licensure”; and
(3) It “acted promptly and in good faith to remedy the failure to comply with the licensure requirements upon learning of the failure.”
The Court of Appeal confirmed in
Judicial Council of California v. Jacobs Facilities, Inc. (2015) 239 Cal.App.4th 882 that a contractor, upon request, is entitled to a hearing on these three factors before it is subjected to disgorgement under Section 7031(b). The legislature amended Section 7031 shortly after the Court of Appeal published this case. The Assembly’s floor analysis went so far as to directly quote the opinion’s observation that penalizing a construction firm for “technical transgressions only indirectly serves the Contractors Law’s larger purpose of preventing the delivery of services by unqualified contractors.” (Assem. Com. on Bus. and Prof., Off. of Assem. Floor Analyses, analysis of Sen. Holden's No. 1793 (2015-2016 Reg. Sess.) as amended August 2, 2016, p. 2.) This echoed an industry consensus that clarifying the law was needed to ensure that properly licensed and law-abiding construction firms were not “placed at fatal monetary risk by malicious lawsuits motivated by personal gain rather than consumer protection.” (Assem. Com. on Judiciary, com. on Assem. Bill No. 1793 (2015-2016 Reg. Sess.), pp. 6-7.)
Unfortunately, existing law does not give many examples of what it means to act “reasonably and in good faith to maintain proper licensure” or to act “promptly and in good faith” to fix license problems. A practical approach is for a contractor to work backwards by assuming it will need to prove substantial compliance at some point in the future. Designated individuals within the organization should have clear responsibility over obtaining and renewing the proper licenses and should keep good records. If necessary, these designees can testify about the contractor's internal policies and their efforts to fix licensing problems when they arose. For example, if the suspension resulted from not providing the CSLB proof of workers’ compensation insurance, the designee can testify about the cause (a broker miscommunication, transmission error,
etc.) and produce documents showing how he or she worked promptly to procure a certificate of insurance to send CSLB. Saved letters, emails, and notes from telephone calls will provide designees and their successors with an important resource months or years down the line if a dispute arises and the contractor is required to reconstruct the chronology of a licensing glitch and prove its due diligence.
Tip 4: Don't sign new contracts unless all necessary licenses are active and any problems are resolved. A recently-formed contractor should not begin soliciting and signing contracts until all required licenses are confirmed as “active.” The first requirement of substantial compliance – being “duly licensed as a contractor in this state prior to the performance of the act or contract” – cannot be met by a contractor that first obtains its license mid-project. (Bus. & Prof. Code, § 7031, subd. (e)(1);
Alatriste v. Cesar’s Exterior Designs (2010) 183 Cal.App.4th 656.) A licensed contractor should also consider refraining from signing new contracts if there is any reason to believe its license might be suspended in the near future – especially if the suspension will be retroactive. Having a suspension on record at the time of contracting may complicate the question of whether the contractor was “duly licensed . . . prior to performance” for the purposes of substantial compliance.
Tip 5: Any judgment against a contractor can cause license suspension if not handled promptly and correctly. The Business and Professions Code authorizes the CSLB to suspend the license of a contractor that does not pay a construction related court judgment within 90 days. The term “construction related” is interpreted to include nearly all types of disputes involving a contractor. (16 Cal. Code Reg. 868;
Pacific Caisson & Shoring, Inc. v. Bernards Bros. Inc. (2015) 236 Cal.App.4th 1246, 1254-1255.) This means a contractor should treat a judgment against it for unpaid office rent, for example, as one carrying the same consequences as one arising from a construction defect or subcontractor claim. The contractor should also not assume that filing an appeal, or agreeing with the other side to stay enforcement, automatically excuses the 90-day deadline in the eyes of the CSLB. It does not. A contractor must notify the CSLB in writing before this period expires, then post bond for the amount of judgment, if it wishes to delay payment for any reason. (Bus. & Prof. Code, § 7071.17, subd. (d).) A suspension may result if it does not. This applies even to small claims judgments.
Recent case law and the 2016 amendments to Business and Professions Code section 7031 provide some solace to those caught in the dragnet of California's licensing laws. But avoiding these problems altogether is preferable. Consider licensing the foundation of a successful business and deserving of the same attention as the structures a contractor builds.
Eric R. Reed is a business and insurance litigator in the Ventura office of Myers, Widders, Gibson, Jones & Feingold, LLP.
Read the court decisionRead the full story...Reprinted courtesy of
Eric Reed, Myers, Widders, Gibson, Jones & Feingold, LLPMr. Reed may be contacted at
ereed@mwgjlaw.com
The Montrose Language Interpreted: How Many Policies Are Implicated By A Construction Defect That Later Causes a Flood?
March 17, 2011 —
Shaun McParland BaldwinThe Court of Appeals of Indiana recently addressed the “Montrose” language added to the CGL ISO form in 2001 in the context of a construction defect claim where a fractured storm drain caused significant flooding a year after the drain was damaged. The insuring agreement requires that “bodily injury or “property damage” be caused by an occurrence and that the “bodily injury or “property damage” occur during the policy period. The Montrose language adds that the insurance applies only if, prior to the policy period, no insured knew that the “bodily injury or “property damage” had occurred in whole or in part. Significantly, it also states that any “bodily injury” or “property damage” which occurs during the policy period and was not, prior to the policy period known to have occurred, includes a continuation, change or resumption of that “bodily injury” or “property damage” after the end of the policy period.
In Grange Mutual Cas. Co. v. West Bend Mut. Ins. Co., No. 29D04-0706-PL-1112 (Ct. App. IN March 15, 2011), http://www.ai.org/judiciary/opinions/pdf/03151109ehf.pdf, Sullivan was the General Contractor for a school construction project. Its subcontractor, McCurdy, installed the storm drain pipes. One of the storm pipes was fractured in 2005 while McCurdy was doing its installation work. More than a year later, the school experienced significant water damage due to flooding. It was later discovered that the flooding was due to the fractured storm drain. Sullivanrsquo;s insurer paid $146,403 for the water damage. That insurer brought a subrogation claim against McCurdy and its two insurers: West Bend and Grange. West Bend had issued CGL coverage to McCurdy while the construction was ongoing, including the date in which the storm pipe was fractured. Grange issued CGL coverage to McCurdy at the time of the flooding. Those two carriers jointly settled the subrogation claim and then litigated which insurer actually owed coverage for the loss. Significantly, the loss that was paid included only damages from the flooding, not any damages for the cost of repairing the pipe.
Read the full story...
Reprinted courtesy of Shaun McParland Baldwin of Tressler LLP. Ms Baldwin can be contacted at sbaldwin@tresslerllp.com
Read the court decisionRead the full story...Reprinted courtesy of
Heat Exposure Safety and Risk Factors
July 04, 2023 —
The Hartford Staff - The Hartford InsightsSummer is here and being outside in the heat can take a toll on your body if you’re not properly prepared. It’s important to regulate your body temperature by both hydrating and gradually acclimating your body to withstand the increasingly hot conditions. Your body has “heat control mechanisms” which get overworked in hot, humid and poorly ventilated areas. When you’re exercising or doing physical labor, your muscles generate heat as a metabolic by-product.
Sweating can dissipate heat when the air is dry or a breeze is blowing. But when humidity rises and the air becomes denser, sweat doesn’t evaporate from the skin as readily. When this occurs, your core body temperature becomes too high and you can suffer from heat cramps, heat exhaustion or heat stroke. This heat stress can occur suddenly and be very dangerous, that’s why it’s important to be able to recognize the warning signals. This chart will help you identify your body’s heat stress signals and apply the appropriate action to prevent heat-related problems.
Read the court decisionRead the full story...Reprinted courtesy of
The Hartford Staff, The Hartford Insights
New York Appellate Court Applies Broad Duty to Defend to Property Damage Case
January 03, 2022 —
Craig Rokuson - Traub Lieberman Insurance Law BlogIn the recent case of New York Marine and Gen. Ins. Co. v. Eastman Cooke & Associates, 153 N.Y.S.3d 840, 841 (N.Y. App. Div. 1st Dept. 2021), New York’s first department affirmed a duty to defend under New York law. In the underlying action, the plaintiff alleged property damages due to prolonged construction work in a different unit of the subject property. The underlying plaintiff sued the owner of the subject property, which in turn sued Eastman Cooke, the general contractor at the premises. New York Marine denied coverage to Eastman Cooke, asserting that the underlying suit did not seek damages occurring during the New York Marine policy period, and commenced a declaratory judgment action.
The trial court held—and the First Department affirmed—that New York Marine has a duty to defend Eastman Cooke. Initially, the court found that the underlying suit alleged property damage as required for coverage, because there were allegations regarding loss of use of the property. The court also found that the underlying suit alleged damages occurring during the New York Marine policy period. Although the underlying complaint alleged that the underlying plaintiffs were reimbursed for damages occurring during the New York Marine policy period by another insurer, the court held that the evidence was that the payments only covered a certain part of the damages sought. Accordingly, because there was a reasonable possibility that some unreimbursed damages may fall within the New York Marine policy period.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Rokuson, Traub LiebermanMr. Rokuson may be contacted at
crokuson@tlsslaw.com
Pennsylvania Mechanics’ Lien “Waivers” and “Releases”: What’s the Difference?
March 19, 2015 —
Thomas C. Rogers – White and Williams LLPIn the world of Pennsylvania mechanics’ liens there is much confusion about the interchangeable use of the words mechanics lien “waiver” and mechanics’ lien “release.” Many who work in the world of real estate in Pennsylvania, be they contractors, subcontractors, developers, lenders, or attorneys, use these terms interchangeably without understanding that there is a meaningful difference. Failure to understand the difference creates confusion when discussing issues and drafting documents regarding mechanics’ liens.
In Pennsylvania a mechanics’ lien “waiver” is the pre-construction waiver of liens that was historically executed by a general contractor and an owner and filed with the Prothonotary in the county in which construction is located. These pre-construction lien “waivers,” assuming they were properly prepared, signed by the contractor and owner and filed in accordance with applicable law, negated the ability of that contractor and its subcontractors to file a mechanics’ lien on the subject property. These pre-construction lien “waivers” were part of every construction loan closing up through the amendments to the Pennsylvania Mechanics’ Lien Act that went into effect in 2007. Since 2007, the Mechanics’ Lien Act has been amended twice to further address those circumstances in which pre-construction lien waivers still have vitality. Except with respect to those narrow situations specifically provided for in the statute, pre-construction lien “waivers” are against public policy in Pennsylvania.
Read the court decisionRead the full story...Reprinted courtesy of
Thomas C. Rogers, White and Williams LLPMr. Rogers may be contacted at
rogerst@whiteandwilliams.com
Colorado’s Abbreviated Legislative Session Offers Builders a Reprieve
October 26, 2020 —
David M. McLain – Colorado Construction LitigationWould you believe me if I told you that this year could have been worse for builders? Had COVID-19 not hit, the Colorado Legislature may have passed bills that would have had a severely negative impact on the home building industry. In response to the COVID-19 pandemic, the Legislature temporarily adjourned in mid-March, 67 days into the 120-day legislative session. After a two-month recess, the Legislature returned for approximately one month to pass critical bills including the state budget, the school finance act and what to do with the money from the federal CARES Act. Of the bills on the calendar when the Legislature temporarily adjourned, legislators focused on those that were “fast, free, and friendly,” and let the others fall by the wayside.
Bills that died included SB 20-138, which would have extended Colorado’s statute of repose for construction defect claims from six plus two years to 10 plus two years. The bill also contained a number of accrual and tolling provisions, which would have made it harder for builders to convince tribunals that claims were untimely. This bill died on the Senate floor, for lack of support. We will see whether plaintiffs’ attorneys will revive this effort next year.
SB 20-093, while not an outright ban on arbitration or a legislative overturning of the Vallagio decision, would have made it harder to administer and more difficult to get cases into arbitration. The bill died under the “fast, free, and friendly” test, i.e., it faced too much opposition. I expect to see this bill again next year, in some form.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Part I: Key Provisions of School Facility Construction & Design Contracts
May 16, 2018 —
David R. Cook Jr. - Autry, Hall & Cook, LLPWe all expect our school construction projects will go smoothly, on time and under budget. But despite our best efforts, some projects will encounter speed bumps, detours or outright roadblocks. While there are many precautions a school facility manager may take, one of the best precautions is to have solid construction and design contracts.
A good contract will account for the known risks and specify an outcome in favor of the school authority. School construction risks can be categorized into a few categories: performance risk, time risk, cost risk and political risk. Some risks are typical to all construction projects, while others are peculiar to the unique needs of school authorities.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Avoiding Lender Liability for Credit-Related Actions in California
October 27, 2016 —
Anthony J. Carucci – Snell & Wilmer Real Estate Litigation BlogAside from general statutory prohibitions on lender discrimination, there are certain circumstances under California law in which lenders may be held liable for credit-related actions, such as negotiating or denying credit. See generally 11 Cal. Real Est. § 35:3 (explaining that the business of lending money is subject to the Unruh Civil Rights Act, Cal. Civ. Code § 51 et seq., the Fair Employment and Housing Act, Cal. Gov. Code § 12900 et seq., the Federal Fair Housing Act, 42 U.S.C. § 3601 et seq., and the Equal Credit Opportunity Act, 15 U.S.C. § 1691, et seq.). Specifically, lenders have been held liable for credit-related actions where, among other things, the lender (1) breached a loan commitment; (2) committed fraud; or (3) breached a fiduciary duty owed to the borrower.
The Lender-Borrower Relationship
As a general rule, a lender does not owe a duty of care to a borrower when the lender’s involvement in a transaction does not exceed the scope of its conventional role as a lender of money. Oaks Management Corp. v. Superior Court (2006) 145 Cal.App.4th 453, 466 (“[I]t is established that absent special circumstances . . . a loan transaction is at arms-length and there is no fiduciary relationship between the borrower and lender.”); Nymark v. Heart Fed. Savings & Loan Assn. (1991) 231 Cal.App.3d 1089, 1096 (holding lender owed no duty of care to a borrower in preparing an appraisal of the real property that was security for the loan when the purpose of the appraisal is to protect the lender by satisfying it that the collateral provided adequate security for the loan, and noting that “as a general rule, a financial institution owes no duty of care to a borrower when the institution’s involvement in the loan transaction does not exceed the scope of its conventional role as a mere lender of money”).
Read the court decisionRead the full story...Reprinted courtesy of
Anthony J. Carucci, Snell & WilmerMr. Carucci may be contacted at
acarucci@swlaw.com