Quick Note: Independent Third-Party Spoliation Of Evidence Claim
June 18, 2019 —
David Adelstein - Florida Construction Legal UpdatesIn an earlier posting I discussed the difference between first-party spoliation of evidence and third-party spoliation of evidence.
There is NO independent cause of action for first-party spoliation of evidence because that can be dealt with directly in the underlying lawsuit. This deals with the assertion that an actual party to a lawsuit spoiled evidence.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Palo Alto Considers Fines for Stalled Construction Projects
November 20, 2013 —
CDJ STAFFThe city of Palo Alto, California is considering adopting a law that would fine residents with expired building permits. The City Council took up the issue in response to complaints from residents about stalled construction projects in their neighborhoods.
In the public testimony, one resident noted that a site near her home was fenced off in 2007, with the home demolished in 2008, after which nothing has happened. The City Council is proposing fines of $200 per day, after a 30-day grace period, increasing to $400 per day two months after that, going to $800 per day on the 121st day.
Read the court decisionRead the full story...Reprinted courtesy of
Approaches to Managing Job Site Inventory
August 30, 2017 —
Jessica Stark - Construction InformerThere is no question that organization on the job site can mean the difference between efficient performance and costly errors. A simple mistake can cost a company thousands, which is why details are carefully articulated and supervisors become better scrutinizers than magazine editors. But for some reason, many companies don’t consider managing job site inventory under this same attentive category, or perhaps they don’t know about the technology available to help them do it.
Whole Inventory, Big to Small
For contractors, keeping track of every piece of material and equipment lowers losses and keeps crews busy. This is especially true for contractors in the trades who often have specialized equipment in inventory such as power supplies, HVAC “smart energy” components or inspection equipment. Once everything is accounted for, the possibility of loss is decreased and there’s a chance to evaluate the use of all materials and equipment. This can show the efficiency of allotted resources. Is there enough equipment on the site to get tasks completed? Is there a need for more? Less? Having excess equipment can sometimes prepare a crew for problem scenarios. But it can also mean the construction company is overpaying for unneeded resources. However, the only way to know is by effectively managing job site inventory. That includes all equipment and materials.
Read the court decisionRead the full story...Reprinted courtesy of
Jessica Stark, Construction Informer
Construction Client Advisory: The Power of the Bonded Stop Notice Extends to Expended Construction Funds
February 07, 2014 —
Steven M. Cvitanovic - Haight Brown & Bonesteel LLPCFO to CEO: “I have bad news, the developer on our biggest project has run out of money.” Frightening words for sure, but contractors should not overlook the bonded stop notice in situations where the construction lender seemingly has expended all construction funds. The recent case of Brewer Corporation v. Point Center Financial, Inc. 2014 WL 346636 illustrates this point.
Contractors have two options at their disposal to secure payment on private works of improvement. The first is the mechanics lien. However, construction loan trust deeds are normally recorded prior to the commencement of construction and therefore have priority over mechanics liens. Connolly Development, Inc. v. Superior Court (1976) 17 Cal.3d 803, 827. Enter the bonded stop notice. The bonded stop notice requires the lender to withhold unexpended funds and, if it fails to do so, it is personally liable to the claimant for the full amount of the claim. But the stop notice also has the power of “priority” over any assignment of construction loan funds, whether before or after a stop notice is served. Civil Code § 3166, now Civil Code § 8544.
Read the court decisionRead the full story...Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLPMr. Cvitanovic may be contacted at
scvitanovic@hbblaw.com
New Jersey Supreme Court Upholds $400 Million Award for Superstorm Sandy Damages
February 22, 2021 —
Kerianne E. Kane - Saxe Doernberger & Vita In New Jersey Transit Corp. v. Certain Underwriters at Lloyd’s London,1 New Jersey’s highest court upheld an appellate decision2 finding that New Jersey Transit Corporation (“NJT”) was entitled to full coverage under its property insurance policy for damages caused by Superstorm Sandy.
In July 2012, NJT secured a multi-layered “all risks” property insurance program from eleven insurers for the policy period of July 1, 2012, to July 1, 2013. The policies covered all perils and damage to NJT’s property unless specifically excluded. The primary layer, issued by Lexington Insurance Company, provided the first $50 million of coverage. The second layer provided coverage up to $100 million, the third layer provided an additional $175 million, and the fourth layer provided coverage of $125 million, for a total of $400 million in coverage.
The excess layer insurers included Certain Underwriters At Lloyd’s, London, Torus Specialty Insurance Company, and several other carriers. All participating insurers’ policies included a standard policy form and separate endorsements, some of which were included in all policies and some of which were unique to specific insurers.
Read the court decisionRead the full story...Reprinted courtesy of
Kerianne E. Kane, Saxe Doernberger & VitaMs. Kane may be contacted at
kkane@sdvlaw.com
The EPA and the Corps of Engineers Propose Another Revised Definition of “Waters of the United States”
February 14, 2022 —
Anthony B. Cavender - Gravel2GavelOn December 7, 2021, the most recent proposed revision to the Clean Water Act’s term, “Waters of the United States” was published in the Federal Register. (See 86 FR 69372.) Comments on this proposal must be submitted by February 7, 2022. This term controls the scope of federal regulatory powers in such programs as the development of water quality standards, impaired waters, total maximum daily loads, oil spill prevention, preparedness and response plans, state and tribal water quality certification programs, the National Pollutant Discharge Elimination System (NPDES) permit program, and the Corps of Engineers’ dredge and fill program. The Environmental Protection Agency (EPA) and the Corps of Engineers have jointly drafted this comprehensive proposed rule, which also responds to President Biden’s Executive Order 13990, issued in January 2021.
Background
The agencies noted that they have repeatedly defined and re-defined “Waters of the United States” since the Clean Water Act was enacted in 1972. This level of sustained commitment is unique to this program, perhaps reflecting the importance of the programs that are implemented through the Clean Water Act. The most recent rulemaking efforts took place in 2015, 2017, 2020 and now 2022, and the Supreme Court has issued several landmark rulings in response to these efforts. See City of Milwaukee v. Illinois, 451 US 304 (1981), United States v. Riverside Bayview, 474 US 121 (1985), SWANCC v. United States, 531 US 159 (2001), Rapanos v. United States, 547 US 715 (2006), National Association of Manufacturers v. Department of Defense, 138 S Ct 617 (2018), and County of Maui, Hawaii v. Hawaii Wildlife Fund, 140 S, Ct 1462 (2020). The rules promulgated in 2015 and entitled, “Clean Water Act: Definition of Waters of the United States” expanded the scope of federal regulatory jurisdiction, but the 2020 rule, entitled the “Navigable Waters Protection Rule,” contracted that scope. Now, the agencies have proposed the “Revised Definition of ‘Waters of the United States,’” which will rescind the 2020 rule and inevitably restore something of the scope of the 2015 rule by returning to the familiar “1986 rules” that were issued by the Corps of Engineers in 1986 and EPA in 1988, as modified by the recent Supreme Court decisions mentioned above. Both the 2015 and 2020 rules were mired in litigation and the Corps and EPA view the resort to the 1986 rules as a fresh start for the Clean Water Act. In short, the topsy-turvy history of regulation under the Clean Water Act continues.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
A Tort, By Any Other Name, is Just a Tort: Massachusetts Court Bars Contract Claims That Sound in Negligence
March 20, 2023 —
Gus Sara - The Subrogation StrategistIn University of Massachusetts Building Authority v. Adams Plumbing & Heating, Inc., 2023 Mass. App. Unpub. LEXIS 28, 102 Mass. App. Ct. 1107, the Appeals Court of Massachusetts (Appeals Court) considered whether the lower court properly held that the plaintiff’s breach of contract and indemnification claims were time-barred by the statute of repose because they sounded in tort. The Appeals Court held that while the six-year statute of repose only applies to tort claims, they can also bar claims for breach of contract and indemnification if they sound in tort. The Appeals Court affirmed the lower court’s ruling, finding that the plaintiff’s breach of contract and indemnification claims were just negligence claims disguised as non-tort claims.
In 2013 and 2014, the University of Massachusetts (UMass) retained various contractors to renovate the dining hall for one of its campus buildings, which included the installation of new ductwork for the kitchen’s exhaust system. The dining hall opened for service in September 2014. In the Spring of 2018, it was discovered that the ductwork for the kitchen had collapsed. Further investigation revealed other deficiencies with the exhaust system. On December 1, 2020, UMass filed a lawsuit against various contractors, asserting negligence, breach of contract, and indemnification. The breach of contract claims alleged breach of express warranties.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
'Major' Mass. Gas Leak Follows Feds Call For Regulation Changes One Year After Deadly Gas Explosions
October 21, 2019 —
Johanna Knapschaefer - Engineering News-RecordA natural gas leak in explosive range forced Lawrence, Mass. residents to evacuate their homes early on Sept. 27, according to electric utility National Grid, which cut power to more than 1,300 customers to avoid another disaster like last year's natural gas explosions and fires in Lawrence and two other towns north of Boston. The leak came just days after federal officials called for changes to national pipeline regulations as they released a final report on the causes of the Sept. 13, 2018, disaster.
Read the court decisionRead the full story...Reprinted courtesy of
Johanna Knapschaefer, ENRENR may be contacted at
ENR.com@bnpmedia.com