"My Bad, I Thought It Was in Good Faith" is Not Good Enough - Contractor Ordered to Pay Prompt Payment Penalties
February 23, 2016 —
David A. Harris & Jesse M. Sullivan – Haight Brown & Bonesteel LLPRetention clauses are almost always included in California construction contracts and permit an Owner to withhold a portion of what is owed to the General Contractor as security to ensure the proper completion of the work. General Contractors pass the withholding of retention down to the subcontractors. Thus, if the subcontractor fails to complete its work, or fails to correct deficiencies, the Owner/General Contractor can use the retention to pay the costs of completing or correcting the subcontractor’s work.
The contractor must release any retention it receives from the owner within ten days unless a “good faith dispute exists between the direct contractor and the subcontractor.” (Civil Code section 8814.) Where there is a good faith dispute, the contractor “may withhold from the retention to the subcontractor an amount not in excess of 150 percent of the estimated value of the disputed amount.” (Civil Code section 8814(c).) If the contractor wrongfully withholds retention, it must not only pay the retention but must also pay the subcontractor “a penalty of 2 percent per month on the amount wrongfully withheld.” The contractor must also pay the subcontractor’s costs and reasonable attorney’s fees incurred in collecting the retention. (Civil Code section 8818.)
Reprinted courtesy of
David A. Harris, Haight Brown & Bonesteel LLP and
Jesse M. Sullivan, Haight Brown & Bonesteel LLP
Mr. Harris may be contacted at dharris@hbblaw.com
Mr. Sullivan may be contacted at jsullivan@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
All Aboard! COVID-19 Securities Suit Sets Sail, Implicates D&O Insurance
April 27, 2020 —
Lorelie S. Masters, Michael S. Levine & Geoffrey B. Fehling - Hunton Insurance Recovery BlogIn a prior post, we predicted that novel coronavirus (COVID-19) risks could implicate D&O and similar management liability coverage arising from so-called “event-driven” litigation, a new kind of securities class action that relies on specific adverse events, rather than fraudulent financial disclosures or accounting issues, as the catalyst for targeting both companies and their directors and officers for the resulting drop in stock price. It appears that ship has sailed, so to speak, as Kevin LaCroix at D&O Diary reported over the weekend that a plaintiff shareholder had filed a securities class action lawsuit against Norwegian Cruise Line Holdings, Ltd. alleging that the company employed misleading sales tactics related to the outbreak.
The lawsuit alleges that the cruise line made false and misleading statements or failed to disclose in its securities filings sales tactics by the company that purported to provide customers with unproven or blatantly false statements about COVID-19 to entice customers to purchase cruises. Those allegations rely on two news articles reporting on the company sales practices in the wake of COVID-19: a March 11, 2020 Miami New Times article quoting leaked emails in which a cruise employee reportedly asked sales staff to lie to customers about COVID-19 to protect the company’s bookings; and a March 12, 2020 Washington Post article entitled, “Norwegian Cruise Line Managers Urged Salespeople to Spread Falsehoods about Coronavirus.” The lawsuit alleges that the company’s share price was cut nearly in half following these disclosures.
Reprinted courtesy of Hunton Andrews Kurth attorneys
Lorelie S. Masters,
Michael S. Levine and
Geoffrey B. Fehling
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Save a Legal Fee: Prevent Costly Lawsuits With Claim Limitation Clauses
April 25, 2012 —
Douglas Reiser, Builders Council BlogEver had that lingering problem with a contracting partner that went away for awhile and then came back to bite you ? years later? In Washington, construction contract claims can be raised for up to six years after substantial completion. Six years!? Why would I want to wait that long to find out if I have a problem? You don’t have to.
Over the past few years, I have discussed the notion of “contractual claim periods” on The Builders Counsel. For today’s Save a Legal Fee column, I cannot think of a better topic. These provisions are specifically intended to save you from unnecessary legal fees that might arise if a problem goes unnoticed for too long.
Contractual claim periods are simply a way to reduce the amount of time that a contracting party has to raise a claim against its contracting partner. For example, a subcontractor might require that a general contractor raise any claim that it might have ? for defective or incomplete work, injury, damages, etc ? within a particular amount of time or forever lose the ability to raise the claim in a legal proceeding.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Does the UCC Apply to the Contract for the Sale of Goods and Services
July 03, 2022 —
David Adelstein - Florida Construction Legal UpdatesWhat governs the transaction for the hybrid contract that includes both goods and services–the Uniform Commercial Code (UCC) or the common law? A question that is asked in numerous disputes. A good example is the recent case out of the Eleventh Circuit Court of Appeals, Wadley Crushed Stone Company, LLC v. Positive Step, Inc., 2022 WL 1639011 (11th Cir. 2022), dealing with Alabama law.
In this case, the plaintiff (buyer) wanted to build a granite plant in Alabama that would process 500 tons of granite per hour. The plaintiff reached out to a defendant company to start the process of building a granite plant. The defendant company engaged vendors and professionals in the due diligence process to determine the equipment the plaintiff would need. After this due diligence, plaintiff and defendant entered into a contract that included equipment and services. Thereafter, the parties modified the contract to reduce the amount for the erection, installation, and electrical work (about $1.5 Million) as plaintiff planned to independently hire the contractor to perform that work. The modified contract was worth $4,059,224.43 of which there were 25 lines items for equipment totaling $3,887,274.43 with the balance (less than 5% of the contract amount) for engineering (done by a third party), installation, setup, and calibration of scales.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Differences in Types of Damages Matter
June 22, 2016 —
Christopher G. Hill – Construction Law MusingsOver the last 7 and a half years (yes I have been doing this for that long), I have often “mused” on various contractual provisions and their application. Why? Because
the contract matters and will be enforced. Provisions like “no damages for delay” and “
pay if paid” litter construction contracts and will be enforced if properly drafted. These types of clauses affect whether and what types of damages you as a construction company can collect.
Of course, these clauses have their limitations. For instance, and as
pointed out by my pal Matt DeVries at his great Best Practices Construction Law blog, not all damages that a subcontractor or general contractor may attribute to coordination or other scheduling related issues are “delay damages” to which a “no damages for delay” clause may apply.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Mendocino Hospital Nearing Completion
December 04, 2013 —
CDJ STAFFThe Frank R. Howard Memorial Hospital is well underway on its plans to move to a larger facility. The new building in Willits, California, will be more than twice the size of the old building at 74,000 square feet. Construction has reached the halfway point after just over three months of construction. Despite that, plans are to put the facility into use in January 2015.
The general contractor for the project is HBE Corporation. Rick Bockmann, HBE’s chief executive officer, said that the hospital was “on schedule and on budget.”
Read the court decisionRead the full story...Reprinted courtesy of
Claim Against Broker for Failure to Procure Adequate Coverage Survives Summary Judgment
April 15, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe broker's motion for summary judgment, seeking to dismiss negligence claims for failure to obtain adequate coverage, was denied by the court in Voss v. The Netherlands Ins. Co., 2014 N.Y. LEXIS 384 (N.Y. Ct. App. Feb. 25, 2014).
The insured met with a representative of CH Insurance Brokerage Services Co., Inc. (CHI) to discuss coverage for the premises and her two companies. At CHI's request, the insured shared information on sales figures for calculating business interruption coverage. The broker represented that CHI would reassess and revisit the coverage needs as her business grew.
CHI recommended $75,000 per incident in coverage for business interruption losses. The insured questioned whether the $75,000 limit was adequate, but the broker assured her that it was sufficient. The insured then accepted the recommendation. Subsequently, the insured's business grew, but CHI renewed the policy with the same $75,000 business interruption limit.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Some Construction Contract Basics- Necessities and Pitfalls
January 03, 2022 —
Christopher G. Hill - Construction Law MusingsRecently, I’ve been on an “advising” kick here at Construction Law Musings. My last two posts have been about communication and trusting your gut when it comes to a smooth construction project. This post will be the third in the trilogy (and who knows maybe I’ll have a 4th and 5th like the Hitchhiker’s Guide to the Galaxy “trilogy”).
While all construction contractors should use their communication skills and instincts to assure a smooth and hopefully profitable project, all of the gut following and great communication will not help you if your contract is not up to snuff. In the spirit of giving you a few basics things to look at, here’s my list of three basics that you need in your contract and a three things to be on the lookout for in others’ contracts.
First, the good stuff that needs to be there:
- Attorney Fees Clause– without it, a Virginia court (and most other courts) will not award you a judgment for any attorney fees spent to protect your rights.
- Dispute Resolution– whether the specified resolution is through the litigation process, ADR or some combination, such a clause or paragraph will only help define the parameters of what happens with a claim.
- Detailed scope of work– Without the proper detail in the scope of work, the parties cannot properly set expectations and know what happens when things change.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at