Select the Best Contract Model to Mitigate Risk and Achieve Energy Project Success
October 17, 2022 —
Gregory S. Seador - Construction ExecutivePower and energy projects are inherently complex and risky. Therefore, management and proper allocation of risk among project participants are essential to success.
Careful drafting of the engineering, procurement and construction (EPC) contract is a critical first step in managing risk. The standard contract format used for power and energy construction projects is the EPC contract. In its traditional form, the EPC contract makes the EPC contractor responsible for the entire project, including engineering (design of the power plant), procurement (purchase, installation and performance of all equipment) and construction (construction of the plant).
EPC contracts can, however, employ different contract models and pricing structures, each of which carries differing levels of risk for project participants. Selecting the appropriate contract model and pricing structure to meet the unique needs of the project is important.
Reprinted courtesy of
Gregory S. Seador, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Seader may be contacted at
seador@slslaw.com
New York Considering Legislation That Would Create Statute of Repose For Construction
April 05, 2021 —
Richard W. Brown & Anna M. Perry - Saxe Doernberger & Vita, P.C.New York is considering legislation, which, if enacted, would create a statute of repose limiting the number of years after completion of a construction project that legal action may be asserted against a contractor. New York currently remains the only state without a statute of repose for construction. Earlier this year, however, the New York State Legislature introduced Bills S04127 and A01706 (the “Bill”) , which would impose a 10-year period of repose in which an injured party may bring suit against a design professional and/or a contractor for bodily injury or property damage resulting from a construction defect.
Currently, contractors and design professionals have exposure to bodily injury and property damage claims resulting from construction defects for an unlimited number of years after completion of a project. If enacted, the Bill would limit the period of repose to 10 years after the project is completed, which is deemed to occur upon substantial completion or acceptance by the owner. An additional 1-year grace period is provided for an injured party to file suit where bodily injury or property damage occurs in the tenth year after completion. The Bill notably limits the applicability of the 10-year statute of repose to third-party actions and thereby preserves the existing 3-year and 6-year statutes of limitation applicable to actions asserted by an owner or client for professional malpractice and breach of contract, respectively.
Reprinted courtesy of
Richard W. Brown, Saxe Doernberger & Vita, P.C. and
Anna M. Perry, Saxe Doernberger & Vita, P.C.
Mr. Brown may be contacted at RBrown@sdvlaw.com
Ms. Perry may be contacted at APerry@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Estoppel Certificate? Estop and Check Your Lease
May 06, 2019 —
Lauren Podgorski - Snell & Wilmer Real Estate Litigation BlogIf you are leasing space in a building, there may come a time when you receive a request from your landlord to fill out and sign an estoppel certificate. Estoppel certificates are usually sent to tenants in connection with the sale or refinance of a building, and a third party may rely on the accuracy of the statements and information contained in the estoppel certificate in connection with that transaction. Estoppel certificates can range from a very simple, one-page document, to several pages.
I’ve received an estoppel certificate in the mail. What do I do now?
Consider the following:
Check your lease. Your lease may require you to deliver the signed estoppel certificate and may even give you a timeframe within which you are required to return it. A form of estoppel certificate may also be included in your lease as an exhibit. If you’ve previously agreed to a form of estoppel certificate in your lease, check to ensure the one you have received matches the form you previously agreed to and if it doesn’t make sure to review it carefully to make sure it is acceptable.
Review the estoppel certificate and confirm that all of the information is accurate. Be on the lookout for any terms or provisions that you did not agree to in your lease. If it seems like the landlord is trying to modify your lease, you likely do not need to consent to the change in this document. Cross off (or modify or delete, if you have an electronic copy) any information that is inaccurate. Fill in all blanks (if the blank is not applicable, write “N/A”), and if any exhibits are referenced in the body of the document, make sure they are actually attached.
Read the court decisionRead the full story...Reprinted courtesy of
Lauren Podgorski, Snell & WilmerMs. Podgorski may be contacted at
lpodgorski@swlaw.com
Builder Waits too Long to Dispute Contract in Construction Defect Claim
May 10, 2012 —
CDJ STAFFThe Louisiana Court of Appeals has affirmed the lower court’s judgment in the case of Richard v. Alleman. The Richards initiated this lawsuit under Louisiana’s New Home Warranty Act, claiming that they had entered into a construction contract with Mr. Alleman and that they quickly found that his materials and methods had been substandard. They sued for the cost of repairing the home and filing the lawsuit. Mr. Alleman countersued, claiming the Richards failed to pay for labor, materials, and services. By his claim, they owed him $12,838.80.
The trial court split the issues of liability and damages. In the first trial, the court concluded that there was a contact between Alleman and the Richards and that the New Home Warranty Act applied. Mr. Alleman did not appeal this trial.
The second trial was on the issue of damages. Under the New Home Warranty Act, the Richards were found to be entitled to $36,977.11 in damages. In a second judgment, the couple was awarded $18,355.59 in attorney’s fees. Mr. Alleman appealed both judgments.
In his appeal, Alleman contended that the trial court erred in determining that the Home Warranty Act applied. This was, however, not the subject of the trial, having been determined at the earlier trial. Nor did the court accept Alleman’s claim that the Richards failed to comply with the Act. The trial record made clear that the Richards provided Alleman with a list of problems with their home by certified mail.
The court did not establish whether the Richards told Alleman to never return to their home, or if Alleman said he would never return to the home, but one thing was clear: Alleman did not complete the repairs in the list.
A further repair was added after the original list. The Richards claimed that with a loud noise, a large crack appeared in their tile flooring. Mr. Alleman stated that he was not liable for this as he was not given a chance to repair the damage, the Richards hired the flooring subcontractors, and that the trial court rejected the claim that the slab was defective. The appeals court found no problem with the award. Alleman had already “refused to make any of the repairs.”
Finally Alleman made a claim on a retainage held by the Richards. Since Alleman did not bring forth proof at trial, the appeals court upheld the trial courts refusal to award a credit to Alleman.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
An Uncharted Frontier: Nevada First State to Prohibit Defense-Within-Limits Provisions
July 10, 2023 —
Geoffrey B. Fehling & Andrew S. Koelz - Hunton Insurance Recovery BlogNevada recently became the first state to prohibit defense-within-limits provisions in liability insurance policies. Defense-within-limits provisions—resulting in what’s called “eroding” or “wasting” policies—reduce the policy’s applicable limit of insurance by amounts the insurer pays to defend the policyholder against a claim or suit. These provisions are commonly included in errors and omissions (E&O), directors and officers (D&O) and other management liability policies. This is in contrast to other policies, most commonly commercial general liability policies, which provide defense “outside of limits” where defense costs do not reduce the policy’s limit.
Reprinted courtesy of
Geoffrey B. Fehling, Hunton Andrews Kurth and
Andrew S. Koelz, Hunton Andrews Kurth
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Mr. Koelz may be contacted at akoelz@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Federal District Rejects Another Construction Defect Claim
November 30, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe Federal District Court, District of Hawaii, continued it long line of cases finding no coverage for claims of faulty workmanship. Nautilus Ins. Co. v. Summary Judgment RMB Enters., 2020 U.S. Dist. LEXIS 200468 (D. Haw. Oct. 28, 2020).
Property owners entered a construction contract with RMB Enterprises to develop and construct residential structures and a pond. The pond walls enclosed residential spaces, providing structural foundations for the walls of the building. After completion of the project, the pond leaked into its pump room. RMB performed remedial work by injecting epoxy into cracks. Later, water from the pondleaked into the interior of a residence near a staircase. Water also leaked into the master bedroom area causing musty odor, mood growth, and increased humidity.
The owners sued RMB asserting breach of contract, breach of warranty, misrepresentation, and negligence claims. Nautilus denied coverage. The policy provided that faulty workmanship did not constitute an "occurrence." But when faulty workmanship caused property damage to property other than "your work," then such property damage would be considered caused by an occurrence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
BHA Has a Nice Swing: Firm Supports NCHV and Final Salute at 2017 WCC Seminar
May 03, 2017 —
CDJ STAFFBert L. Howe & Associates (BHA) is excited to announce the return of their very popular Sink a Putt for Charity at the 2017
West Coast Casualty Construction Defect Seminar. This year, participant’s efforts on the green will help benefit both the
National Coalition for Homeless Vets and
Final Salute. As in years past, sink a putt in the BHA golf challenge and win a $25 Amazon gift card, and for every successful putt made, BHA will make a $25 cash donation in the golfer’s name to be distributed equally between these two worthy organizations.
While at the booth, don’t forget to test out BHA’s industry leading data collection and inspection analysis systems. BHA has recently added video overviews to their data collection process, as well as next-day viewing of inspection data via their secured BHA Client Access Portal. Discover meaningful cost improvements that translate to reduced billing while providing superior accuracy and credibility. Also learn about BHA’s expanding market presence and full range of services in Texas, Florida, and across the Southeast United States.
Attendees can also enter to win Dodger baseball tickets or a new iPad Pro! Other BHA giveaways include USB charging blocks, pocket tape measures, multi-tools, LED flashlights, and foam stress balls.
For more information on the National Coalition for Homeless Vets, please visit: http://nchv.org/
To learn more about how Final Salute provides homeless women Veterans with safe and suitable housing, please visit: http://www.finalsaluteinc.org/
Read the court decisionRead the full story...Reprinted courtesy of
Look Out! Texas Building Shedding Marble Panels
November 13, 2013 —
CDJ STAFFThe streets around the Omni Building in Lubbock, Texas have been barricaded for an indefinite period, since the marble panels have been falling off the building. The panels weight about 300 pounds each.
The building’s owners attempted to remedy the problem by replacing the marble with stucco, but that too came loose in the wind and fell to the ground. The city issued a stop work order preventing the installation of any more stucco. The city “told them that all needed to come down, both the old and the new,” according to Steve O’Neil, the city’s chief building official.
The city has filed a lawsuit to compel the owners to fix the building. Glen Robertson, Lubbock’s mayor, sees another possible solution, “or demolish it because, as it stands right now, it is truly a health and safety hazard to our citizens.
Read the court decisionRead the full story...Reprinted courtesy of