Unjust Enrichment and Express Contract Don’t Mix
August 23, 2021 —
Christopher G. Hill - Construction Law MusingsI am a huge fan of clearly written construction contracts. Virginia state and federal courts will interpret contract provisions as written and will seek to enforce all of those terms where possible. Where the contract is ambiguous, we construction attorneys make money and the courts are forced to make decisions that the parties may not like.
A recent case out of the Eastern District of Virginia federal court highlights the ways in which a clear contract affects the claims that can be brought and limits the scope of possible litigation. In First Call Environmental LLC v. Murphy Oil USA LLC, the Court looked at a relatively typical Owner, Contractor, Subcontractor set of agreements. In this matter, Murphy Oil entered a contract with National Rapid Response, Inc. (“NRR”) whereby NRR would provide emergency and environmental management and waste disposal services to Murphy Oil. NRR then subcontracted with the Plaintiff First Call to perform the services for Murphy Oil. First Call filed suit against Murphy Oil alleging two counts: breach of contract (based on a third-party beneficiary theory), and unjust enrichment.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Congratulations to Arezoo Jamshidi & Michael Parme Selected to the 2022 San Diego Super Lawyers Rising Stars List
April 04, 2022 —
Arezoo Jamshidi & Michael C. Parme - Haight Brown & Bonesteel LLPCongratulations to Arezoo Jamshidi and Michael Parme who were selected for the 2022 San Diego Super Lawyers Rising Stars list. The 2022 San Diego Rising Stars list is an honor reserved for lawyers who exhibit excellence in practice. Only 2.5% of attorneys in San Diego receive this distinction.
Reprinted courtesy of
Arezoo Jamshidi, Haight Brown & Bonesteel, LLP and
Michael C. Parme, Haight Brown & Bonesteel, LLP
Ms. Jamshidi may be contacted at ajamshidi@hbblaw.com
Mr. Parme may be contacted at mparme@hbblaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
DC Circuit Issues Two Important Clean Air Act and Administrative Law Decisions
December 16, 2019 —
Anthony B. Cavender - Gravel2GavelThe U.S. Court of Appeals or the District of Columbia has recently issued two important rulings on the Clean Air Act in particular and administrative law in general: California Communities Against Toxics, et al., v. EPA and Murray Energy Corporation v. EPA.
The Battle of the Memos: Seitz Makes Way for Wehrum
In the California Communities case, decided on August 20, 2019, the court held, in a 2 to 1 decision, that a petition to review a change in EPA policy announced in an agency memorandum which reversed an agency policy announced nearly 25 years ago in another agency memo must be rejected because the memo at issue was not a “final agency action” subject to the Administrative Procedure Act (APA). In 1995, the “Seitz Memo,” which interpreted Section 112 of the Clean Air Act and addresses the regulation and control of hazardous air pollutants from stationary sources, stated that once a source of toxic emissions is classified as “major,” the facility remains subject to regulation as a major source even if the facility makes changes to the facility to limit its potential to emit such toxics below the major source threshold. Then, in 2018 under a new administration, the “Wehrum Memorandum” was issued which reversed this policy and its interpretation of the law. (Both memos were issued without any kind of advance notice or opportunity to comment.) If a source takes steps to limit its potential to emit, then it may be regulated as an area source, and subject to less rigid regulation. The court majority held that the Wehrum Memo was not a final agency action and was not subject to judicial review when it was measured against both prongs of the “finality test” devised by the Supreme Court in the cases of Bennet v. Spear, 520 US 154 (1997) and US Army Corps of Engineers v. Hawkes, 136 S. Ct. 1807 (2016). While the memo undoubtedly represented the consummation of the agency’s decision-making process, the memo had no direct and appreciable legal consequences, and not therefore being a final action, the case must be dismissed. Judge Rogers filed a strong dissenting opinion.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Court of Appeal Puts the “Equity” in Equitable Subrogation
October 05, 2020 —
Garret Murai - California Construction Law BlogSubrogation as a concept is well understood in insurance circles. According to the Institute of Risk Management Institute’s glossary of insurance terms subrogation is “the assignment to an insurer by the terms of [a] policy or by law, after payment of a loss, of the rights fo the insured to recover the amount of the loss from one legally liable for it.” In other words, if an insurer comes out of pocket for something someone else broke, the insurer can turn to that responsible party for reimbursement of its out of pocket costs.
Typically, subrogation is, as stated in IRMI’s glossary of insurance terms, a matter of contract and the rights and responsibilities of parties are set forth within the terms of a policy. However, subrogation may, as stated in IRMI’s glossary, also be matter of law. And this is where equitable subrogation comes in.
“Equitable subrogation,” according to IRMI, is “the right of subrogation granted under common law when one party has made a payment on behalf of another and becomes entitled to whatever recovery rights the other party has against a responsible third party.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Providing Your Insurer Prompt Notice
May 20, 2024 —
David Adelstein - Florida Construction Legal UpdatesSometimes, when it comes to insurance, you may hear the argument that you breached your insurance policy by failing to provide your insurer with prompt notice as the insurance policy requires. Well, this is not such an absolute issue. With that said, you should absolutely provide your insurer with prompt notice of a claim or loss. No legitimate reason not to. But, if you don’t, it is not an absolute get out of jail free card for your insurer, but it does give them a good argument, which you don’t really want to deal with.
In Gulfpoint Construction Co., Inc. v. Westfield Ins. Co., 2024 WL 1759228 (11th Cir. 2024), an insured appealed a trial court’s ruling that found it did not provide prompt notice to its property insurer as the policy required. In this case, notice was provided two years after a loss from a hurricane. The insurer denied coverage and, in doing so, relied on the insured’s failure to provide prompt notice. Although the trial court agreed, the appellate court found this was a genuine issue of material fact.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
The Top 10 Changes to the AIA A201: What You Need to Know
May 24, 2018 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome back Melissa Dewey Brumback. Melissa is a construction law attorney with Ragsdale Liggett in Raleigh, North Carolina. Aside from the fact that she is a UNC grad and fan, she’s okay!
In 2017, as it does every ten years, the American Institute of Architects (AIA) updated most of its standard form contract documents, including the A201 General Conditions. This cycle, the contract changes are evolutionary in nature, not revolutionary. Even so, it is crucial to know the changes to avoid making a fatal mistake that could cost you money on a construction project. In reverse order, the top 10 changes you need to know include:
# 10: Differing Site Conditions
Prior editions of the A201 provided that upon encountering differing site conditions, the Contractor was to promptly provide notice to the Owner and Architect, before the conditions are disturbed, and in no event later than 21 days after the conditions were first observed. A201–2017 shortens the time for notice from 21 to 14 days.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Flying Solo: How it Helps My Construction Clients
February 18, 2015 —
Christopher G. Hill – Construction Law MusingsTwo and a half years ago, on July 1, 2010, I opened my solo practice. At the time, I really had no insight into how big this change would be from a positive, customer service, perspective.
When I made the decision to go solo with my construction law practice, I knew I wanted to have flexibility to serve my client base of contractors and subcontractors in Virginia. I started some flat rate billing and had the ability to take cases that were below the dollar value of those that my old firm was willing to take. I also knew that I would be a master of my own destiny for better or worse (and it has been much more of the former than the latter).
What I did not realize is the impact that owning my own business would have on my perspective. I have always believed that, in most cases where construction disputes occur, mediation is a great option. However mediation only occurs with conflict. For any business, whether construction or otherwise, conflict creates expenses that were not likely to have been anticipated or built in to the budget. Litigation is not something that most businesses can, or should, build into their operating budgets.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Pennsylvania Supreme Court Adopts New Rule in Breach-of-the-Consent-to-Settle-Clause Cases
August 19, 2015 —
Sean Mahoney – White and Williams LLPIn Babcock & Wilcox Company, et al. v. America Nuclear Insurers, et al., the Pennsylvania Supreme Court recently held that where a liability insurer has agreed to provide a defense to its insured in an underlying tort action subject to a reservation of rights but refuses to consent to a settlement in that action, the insured may nevertheless accept the settlement over the insurer’s objection where the settlement is “fair, reasonable, and non-collusive” from the perspective of a reasonably prudent person in the insured’s position in light of the totality of the circumstances and is covered. Babcock & Wilcox Company v. America Nuclear Insurers, No. 2 WAP 2014, 2015 WL 4430352 (Pa. Jul. 21, 2015). This decision fills an important gap in Pennsylvania precedent addressing the rules applicable when an insurer refuses to consent to an insured’s settlement of a lawsuit.
In Babcock, the underlying plaintiffs sued Babcock & Wilcox Company and Atlantic Richfield Company (“the Insureds”) alleging that the Insured’s nuclear facilities caused bodily injury and property damage. The Insureds’ liability insurers agreed to defend the Insureds subject to a reservation of rights. The insurers later refused to consent to an offer to settle the underlying action for a total of $80 million because they believed the Insureds were likely to succeed on the merits. Nevertheless, in 2009, the Insureds accepted that offer and settled the underlying action for $80 million, notwithstanding the insurer’s refusal. The Insureds then sought reimbursement of the $80 million settlement from their insurers, who rejected that request on the ground that the Insureds had breached the consent-to-settlement/cooperation provisions of the implicated policies.
Read the court decisionRead the full story...Reprinted courtesy of
Sean Mahoney, White and Williams LLPMr. Mahoney may be contacted at