Insurer Unable to Declare its Coverage Excess In Construction Defect Case
January 06, 2012 —
CDJ STAFFThe Ninth Circuit Court of Appeals has upheld a summary judgment in the case of American Family Mutual Insurance Co. v. National Fire & Marine Insurance Co. Several other insurance companies were party to this case. In the earlier case, the US District Court of Appeals for Arizona had granted a summary judgment to Ohio Casualty Group and National Fire & Marine Insurance Company. At the heart of it, is a dispute over construction defect coverage.
The general contractor for Astragal Luxury Villas, GFTDC, contracted with American Family to provide it with a commercial liability policy. Coverage was issued to various subcontractors by Ohio Casualty and National Fire. These policies included blanket additional insured endorsements that provided coverage to GFTDC. The subcontractor policies had provisions making their coverage excess over other policies available to GFTDC.
The need for insurance was triggered when the Astragal Condominium Unit Owners Association filed a construction defect claim in the Arizona Superior Court. CFTDC filed a third-party claim against several subcontractors. The case was settled with American Family paying the settlement, after which it filed seeking reimbursement from the subcontractor’s insurers. The court instead granted summary judgment in favor of Ohio Casualty and National Fire.
American Family appealed to the Ninth Circuit for a review of the summary judgment, arguing that the “other insurance” clauses were “mutually repugnant and unenforceable.” The Ninth Circuit cited a case from the Arizona Court of Appeals that held that “where two policies cover the same occurrence and both contain ‘other insurance’ clauses, the excess insurance provisions are mutually repugnant and must be disregarded. Each insurer is then liable for a pro rate share of the settlement or judgment.”
The court noted that unlike other “other insurance” cases, the American Family policy “states that it provides primary CGL coverage for CFTDC and is rendered excess only if there is ‘any other primary insurance’ available to GFTDC as an additional insured.” They note that “the American Family policy purports to convert from primary to excess coverage only if CFTDC has access to other primary insurance as an additional insured.”
In comparison, the court noted that “the ‘other insurance’ language in Ohio Casualty’s additional insured endorsement cannot reasonably be read to contradict, or otherwise be inconsistent with, the ‘other primary insurance’ provision in the American Family policy.” They find other reasons why National Fire’s coverage did not supersede American Family’s. In this case, the policy is “written explicitly to apply in excess.”
Finally, the Astragal settlement did not exhaust American Family’s coverage, so they were obligated to pay out the full amount. The court upheld the summary dismissal of American Family’s claims.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
California Court Holds No Coverage Under Pollution Policy for Structural Improvements
October 02, 2018 —
Brian Margolies - TLSS Insurance Law BlogIn its recent decision in Essex Walnut Owner L.P. v. Aspen Specialty Ins. Co., 2018 U.S. Dist. LEXIS 138276 (N.D. Cal. Aug. 15, 2018), the United States District Court for the Northern District of California had occasion to consider the issue of a pollution liability insurer’s obligation to pay for the redesign of a structural support system necessitated by the alleged presence of soil contamination.
Aspen’s insured, Essex, owned a parcel of property it was in the process of redeveloping for commercial and residential purposes. The project required excavation activities in order to construct an underground parking lot, and as part of this process, Essex designed a temporary shoring system comprising tied-in retaining walls in order to stabilize the area outside of the excavation. During the excavation work, construction debris was encountered requiring removal. Aspen agreed to pay for a portion of the costs to remove and dispose the debris under the pollution liability policy it issued to Essex.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Margolies, Traub Lieberman Straus & Shrewsberry LLPMr. Margolies may be contacted at
bmargolies@tlsslaw.com
At $350 Million, Beverly Hillbillies Mansion Is Most Expensive in U.S.
August 10, 2017 —
Matt Gross - BloombergThe story of Jed Clampett is, by now, a legend. A poor mountaineer, he could barely feed his family of four, but one day, while he was out hunting for food, he fired his rifle into the swamp behind his shack—and struck oil. The sale of the resource-rich land, in 1962, would eventually net him between $25 million and $100 million, and he did what anyone with sudden riches would do: He packed up his truck and moved his clan to Beverly Hills, where their adventures would be the subject of nine seasons of the Beverly Hillbillies.
Now the Bel Air estate featured in the (fictional) show’s opening credits is up for sale—and as befits a wealthy, cultured oilman like Jed Clampett, it’s the most expensive listing in the country at $350 million.
“Chartwell”—10.3 acres of land centering on a 25,000-square-foot mansion inspired by French Neoclassical design—went on the market this week, besting its closest competitor, a Beverly Hills spec house, by $100 million.
Read the court decisionRead the full story...Reprinted courtesy of
Matt Gross, Bloomberg
Indictments Issued in Las Vegas HOA Scam
January 22, 2013 —
CDJ STAFFA federal grand jury has indicted eleven individuals involved in the Las Vegas homeowners association scam. Leon Benzer, Keith Gregory, and Barry Levinson were all indicted for their roles in the scam, where conspirators took over homeowners associations in order to profit from construction defect suits. According to the Las Vegas Review Journal, all eleven were charged with conspiracy to commit mail and wire fraud. Mr. Levinson's license to practice law has been suspended due to an investigation that he misappropriated client funds. Mr. Benzer has been described as the "mastermind" of the scam.
Twenty-eight defendants have plead guilty, with all but one agreeing to cooperate with investigators. The report quotes William C. Woerner, the acting special agent in charge of the FBI in Las Vegas, as saying that "today's indictment demonstrates the continued commitment of the FBI and its law enforcement partners to identify and root out public corruption at all levels."
Read the court decisionRead the full story...Reprinted courtesy of
Substitute Materials — What Are Your Duties? What Are Your Risks? (Law Note)
June 27, 2022 —
Melissa Dewey Brumback - Construction Law in North CarolinaIn managing a project as the design professional, you are called upon to wear many hats. One of those hats is that of material specifier and, at times, substitute material approver. What are your duties in looking at substitute materials?
As always, the legal answer is “it depends”. In part, it will depend on your role on the project and what, specifically, the contract says. However, at its most basic, you can be sued for accepting an out of spec substitute material. This is so even if you believed the spec met requirements based on information that the contractor gave you. So, tread carefully in this area.
Do not assume any information that the contractor presents to you– take the time to research for yourself, call the manufacturer, and otherwise ensure that the product will work.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
Constructive Changes – A Primer
October 02, 2018 —
Jonathan R. Mayo - Smith CurrieA “constructive change” occurs when an owner action or omission not formally acknowledged by the owner to be a change in the contact’s scope of work forces the contractor to perform additional work. Constructive changes are not formal change orders, but informal changes that could have been ordered under a contract’s changes clause if the change had been recognized by the owner. The constructive change doctrine recognizes that being informally required to do extra work is similar to a formal change order and should be governed by similar principles. Thus, if it is found that a constructive change order did occur, the contractor may be entitled to payment for additional costs incurred, and an extension to the contract performance period.
Constructive changes most often arise where there is a dispute regarding contract interpretation, defective plans and specifications, acceleration or suspension of work, interference or failure to cooperate with the contractor, misrepresentation or nondisclosure of superior knowledge or technical information, over inspection, or a delay in providing requested information crucial to the contractor’s ability to continue work.
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan R. Mayo, Smith CurrieMr. Mayo may be contacted at
jrmayo@smithcurrie.com
Brown and Caldwell Team with AECOM for Landmark Pure Water Southern California Program
May 15, 2023 —
Brown and CaldwellLOS ANGELES, May 09, 2023 — A joint venture of AECOM and Brown and Caldwell (AECOM-BC Team) has been chosen to provide program and project management support and engineering design services for the
Pure Water Southern California program, one of the largest water reuse programs in the world.
The innovative program, being developed by the Metropolitan Water District of Southern California (Metropolitan) in partnership with the Los Angeles County Sanitation Districts (Sanitation Districts), will produce up to 150 million gallons of high-quality, purified water per day for up to 15 million people.
Anticipated for water delivery by 2032 and potentially earlier, the program will reuse the largest untapped wastewater source in the region that currently flows to the ocean to increase water resiliency, enhance water quality, and fuel economic growth. It will lower Southern California’s reliance on imported water supplies from the Colorado River and Sierra Nevada and replenish groundwater basins while leveraging cutting-edge research and development to increase regional water reuse.
About Brown and Caldwell
Headquartered in Walnut Creek, California, Brown and Caldwell is a full-service environmental engineering and construction services firm with 52 offices and over 1,900 professionals across North America and the Pacific. For more than 75 years, our creative solutions have helped municipalities, private industry, and government agencies successfully overcome their most challenging water and environmental obstacles. As an employee-owned company, Brown and Caldwell is passionate about exceeding our clients’ expectations and making a difference for our employees, our communities, and our environment. For more information, visit www.brownandcaldwell.com
Read the court decisionRead the full story...Reprinted courtesy of
City and Contractor Disclaim Responsibility for Construction Error that Lead to Blast
November 13, 2013 —
CDJ STAFFThe city of Grand Junction, Colorado and their contractor, Aperion Utility Construction, LLC, have both denied any wrongdoing in the construction accident that lead to the destruction of two homes. Aperion was drilling in order to repair traffic signals. Their drill damaged a gas line. In the subsequent explosion, three people were injured and two homes destroyed. Homes for 10 blocks were subsequently evacuated.
The three men who were injured have filed a lawsuit claiming negligence on the part of the contractor and the city. The city has released a report from their insurers that concluded that the city was not responsible.
Read the court decisionRead the full story...Reprinted courtesy of