#11 CDJ Topic: Cortez Blu Community Association, Inc. v. K. Hovnanian at Cortez Hill, LLC, et al.
December 30, 2015 —
Beverley BevenFlorez-CDJ STAFFScott Calkins and
Anthony Gaeta of
Collinsworth, Specht, Calkins & Giampaoli, LLP obtained a defense verdict in a breach of fiduciary duty action involving a high-rise condominium in downtown San Diego, California. The Association asked for excess of over $3 million, however, the jury returned with a 10-2 defense verdict in favor of K. Hovnanian.
“While it is now becoming ever more common for attorneys representing homeowners associations to allege a breach of fiduciary duty by the developer, there has been little actual litigation of the issues surrounding those claims which test the viability of the allegations or the defenses to them,” defense attorney Anthony Gaeta stated. “A breach of a fiduciary duty by a developer, which is demonstrated to damage the viability of an HOA either to perform regularly scheduled maintenance, or replace building components from its reserves, has the potential in economic terms to surpass the damages from purported construction defects.”
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
The Court of Appeals Holds That Indifference to Safety Satisfies the Standard for a Willful Violation Under WISHA
May 16, 2022 —
Cameron Sheldon - Ahlers Cressman & Sleight PLLCIn March 2022, the Washington State Court of Appeals, Division One, issued Marpac Constr., LLC v. Dep’t of Lab. & Indus., No. 82200-4-I, 2022 WL 896850, at *1 (Wash. Ct. App. Mar. 28, 2022) holding Marpac Construction, LLC (“Marpac”) liable for three willful Washington Industrial Safety and Health Act of 1973 (WISHA) violations pertaining to safe crane operation near energized power lines.
Marpac was the general contractor on an apartment complex construction project in West Seattle. The worksite had high voltage power lines running throughout the site. Seattle City Light had flagged some with a 10-foot offset, but none of the other power lines were flagged. Marpac’s superintendent assumed that the lines were between 26 kilovolts (kV) and 50 kV based on their connection to the lines flagged by Seattle City Light. The superintendent never called Seattle City Light to check the voltage of the lines and the lines remained above ground.
In September 2016, a subcontractor began work on the project’s structural foundation. The subcontractor expressed concerns about working around the power lines, but Marpac promised it was working on mitigation of the power line hazard and directed the subcontractor continue working. At one point, the subcontractor’s employees had to move the crane and concrete forms away from the power lines to allow a cement truck to park in its place. The crane’s line contacted the power lines, causing serious injuries to two of the subcontractor’s employees.
Read the court decisionRead the full story...Reprinted courtesy of
Cameron Sheldon, Ahlers Cressman & Sleight PLLCMs. Sheldon may be contacted at
cameron.sheldon@acslawyers.com
Managing Once-in-a-Generation Construction Problems – Part II
April 03, 2023 —
Jeffrey S. Wertman - Construction ExecutivePart I of this series discussed the benefits of construction participants using alternative project delivery methods and properly addressing change order issues, rising costs and payment structure issues to manage construction during these uncertain times. Part II below explores the possibility that higher prices and steady consumer demand could lead to an increase in unscrupulous contractor practices—and how owners can mitigate that risk, managing the challenges posed by the unforeseen labor shortage and turnover in the industry and evolving your construction team for short-term and long-term success.
Higher Prices and Steady Demand
With the demand for construction projects relatively stable, contractors remaining in high demand and a surge in prices for construction materials and components, owners are under great pressure to accept less favorable construction terms. This has presented unscrupulous contractors with perceived leverage over owners and new opportunities to engage in questionable business practices and fraud. Although some contractors may seek to stretch the boundaries of a construction contract, other contractors are more deliberate. Falsifying payment applications and invoices to inflate labor or materials costs, billing for work not yet performed or materials not yet delivered to the project site and manipulating change orders are examples of illicit and fraudulent practices by contractors.
Reprinted courtesy of
Jeffrey S. Wertman, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Effective Strategies for Reinforcing Safety Into Evolving Design Standards
July 02, 2024 —
Ethan Harris - Construction ExecutiveFrom design/build condos to built-to-suit warehouses, one factor remains the highest priority regardless of the project type—the approach to upholding the highest level of safety. Safety exists as a core value across all areas of the construction industry, but the increased risk of serious injuries or fatalities persists. Ranked fourth on the United States Bureau of Labor Statistics’ list of occupations with the most fatality rates, construction workers put their lives in danger each time they step onto the jobsite.
Considering this risk, it’s important for every team member—from subcontractors to superintendents—to take responsibility for safety compliance, empowering their workforce to take ownership of their own actions and hold others accountable for theirs. To help enhance safety efforts from start to completion, safety leaders are focusing on ways to implement safety standards within each component of a building’s design. Although this approach requires more comprehensive planning and strategizing on the front end, it is intended to reduce and mitigate hazards before they become larger issues. Keeping this idea in mind, here are a few actionable methods for managing projects designed around safety compliance.
ASSESS FIRST
No two jobsites are the same. From crowded pedestrian walkways to dangerous existing infrastructure, each project requires specific layouts, materials and processes to be fully functional both during and after construction. Given the unique nature of each site, a detailed risk assessment must be conducted before any other design and/or building activities begin. During this initial assessment, careful consideration should be placed on the overall flow as it relates to the people, processes and equipment located on or near the construction site.
Reprinted courtesy of
Ethan Harris, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Federal District Rejects Another Construction Defect Claim
November 30, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe Federal District Court, District of Hawaii, continued it long line of cases finding no coverage for claims of faulty workmanship. Nautilus Ins. Co. v. Summary Judgment RMB Enters., 2020 U.S. Dist. LEXIS 200468 (D. Haw. Oct. 28, 2020).
Property owners entered a construction contract with RMB Enterprises to develop and construct residential structures and a pond. The pond walls enclosed residential spaces, providing structural foundations for the walls of the building. After completion of the project, the pond leaked into its pump room. RMB performed remedial work by injecting epoxy into cracks. Later, water from the pondleaked into the interior of a residence near a staircase. Water also leaked into the master bedroom area causing musty odor, mood growth, and increased humidity.
The owners sued RMB asserting breach of contract, breach of warranty, misrepresentation, and negligence claims. Nautilus denied coverage. The policy provided that faulty workmanship did not constitute an "occurrence." But when faulty workmanship caused property damage to property other than "your work," then such property damage would be considered caused by an occurrence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Elon Musk's Boring Co. Is Feuding With Texas Over a Driveway
July 25, 2022 —
Sarah McBride - BloombergWhile Elon Musk is publicly making a big deal about moving to Texas and cozying up to the governor, behind the scenes his tunnel-building venture, Boring Co., is wrangling with local authorities in the state over a host of seemingly mundane permitting issues.
Since Boring bought land last May to create a research and development center in Bastrop, Texas, a rural area outside Austin, the company has put workers up on mobile homes at the site without authorized sewage facilities, failed to get air and stormwater permits and built a driveway without first getting official approval, according to documents obtained by Bloomberg News through a public records request.
The company’s dealings with Bastrop are yet another illustration of how Musk’s businesses often push the boundaries of or simply ignore regulations that bind other companies. In recent years his Tesla Inc. restarted production at its Fremont plant in defiance of pandemic rules to stay closed, Boring tried to build a tunnel in Los Angeles without going through an environmental review process and the US Securities and Exchange Commission is examining the disclosure of Musk’s stake in Twitter Inc.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah McBride, Bloomberg
Sales of New U.S. Homes Slump to Lowest Level Since November
October 28, 2015 —
Victoria Stilwell – BloombergPurchases of new U.S. homes slumped in September to a 10-month low, disrupting a trend of steady improvement this year in the industry.
Sales dropped 11.5 percent to a 468,000 annualized pace and the prior two months were revised lower, Commerce Department figures showed Monday. The September rate, which included a record percentage decline in the Northeast, was weaker than all economists’ forecasts in a Bloomberg survey.
Limited inventory of affordable homes and viable lots on which to build them may be holding back progress in housing, which has helped buffer the U.S. from slower growth abroad. Builders may need confirmation that fundamentals supporting the housing recovery -- job growth and cheap borrowing costs -- remain in place before investing in additional land and labor.
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, Bloomberg
How the Pandemic Pushed the Construction Industry Five Years Into the Future
September 06, 2021 —
Alexandra McManus & Hussein Cholkamy - Construction ExecutiveOn any given day, there are a multitude of variables playing out on construction jobsites, from maintaining daily logs to track hundreds of workers to creating daily schedules to keep projects on track. What made an industry that’s arguably about 20 years in the past get a dramatic technology boost five years into the future? A global pandemic that nobody saw coming.
When COVID-19 made its first appearance on construction sites in early 2020, the domino effect of project shutdowns and labor shortages created uncertainty along with budget and timeline nightmares. The pandemic shook up the industry, with many projects coming to a screeching halt. As general contractors scrambled to keep their projects moving and workers safe, technology proved to be the solution.
With jobsites shutting down, coupled with a nationwide labor shortage, real-time visibility over workforce variables, such as who was on-site, where they were and who they interacted with was more important than ever. Safe proximity tracking, virtual density and access control technologies helped construction companies gain more control, visibility and the ability to deal with the ever-changing regulations due to the global pandemic. More importantly, it helped keep their valuable workforce safe.
Reprinted courtesy of
Alexandra McManus & Hussein Cholkamy, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Cholkamy may be contacted at hussein@eyrus.com
Ms. McManus may be contacted at alex@eyrus.com
Read the court decisionRead the full story...Reprinted courtesy of