Preliminary Notices: Common Avoidable But Fatal Mistakes
August 26, 2019 —
William L. Porter - Porter Law GroupIn the California building and construction industry, service of a “Preliminary Notice” is a prerequisite for Subcontractor and Supplier claims for payment through the Mechanics Lien, Stop Payment Notice and Payment Bond Claim process. Without proper drafting and service of a Preliminary Notice, these extremely valuable claims cannot be protected. Unfortunately, despite the vital importance of the Preliminary Notice, Subcontractors and Suppliers often make common self-defeating mistakes that make their Preliminary Notice efforts completely ineffective, resulting in loss of their claims rights. The purpose of this article is to list some of these common mistakes in the hope that the reader will avoid such mistakes, preserve the integrity of the Preliminary Notice, and protect the claims rights it makes available:
Not Sending out the Preliminary Notice Within 20 Days After Supplying Labor or Materials:
The protection of a Preliminary Notice begins 20 days before it sent out. This means that if a Subcontractor or Supplier claimant delivered $100,000 in materials on February 1, that same claimant must serve the Preliminary Notice on or before February 21 (the sooner the better), or the claimant will not be able to pursue an enforceable Mechanics Lien, Stop Payment Notice or Payment Bond claim for that $100,000. There are very few exceptions. Best practice: A Subcontractor or Supplier must send out the Preliminary Notice as soon as an agreement to provide work or materials to a California construction project is in place (See California Civil Code 8204).
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Sixth Circuit Finds No Coverage for Property Damage Caused by Faulty Workmanship
October 21, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Sixth Circuit affirmed the lower court's order granting summary judgment to the insurer who denied a defense for a construction defect claim. Steel Supply & Eng'g Co. v. Illinois Nat'. Ins. Co., 2015 U.S. App. LEXIS 14363 (6th Cir. Aug. 13, 2015).
Steel Supply contracted with the Carmel Redevelopment Corporation to fabricate and erect steel for a construction project in Carmel, Indiana. After the steel was erected, an iron worker at the site discovered defects in the steel. Subsequent investigations revealed additional defects.
Carmel filed suit against Steel Supply for breach of contract. The complaint alleged that a critical connection that Steel Supply designed was inadequate to handle the forces coming onto it. Carmel claimed that the immediate need to remediate the steel damaged Carmel directly, and that other contractors sought damages from Carmel for harm caused by the delays.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
A Court-Side Seat: A FACA Fight, a Carbon Pledge and Some Venue on the SCOTUS Menu
November 02, 2020 —
Anthony B. Cavender - Gravel2GavelIn this summary of recent developments in environmental and regulatory law, venues are challenged, standing is upheld, statutory exemption is disputed and more.
THE U.S. SUPREME COURT
Change Must Come from Within … Maryland?
As the new term begins, the Court has agreed to review BP PLC v. Mayor and City Council of Maryland, a decision of the U.S. Court of Appeals for the Fourth Circuit which held that a climate change damages case filed against many energy companies must be heard in the state courts of Maryland and not the federal courts. The petitioners argue that the federal office removal statute authorizes such removal, and the Fourth Circuit’s contrary decision conflicts with rulings from other circuit courts.
THE FEDERAL COURTS
Where Is the Fund in That?
On September 25,2020, in U.S. House of Representatives v. Mnuchin, et al., the U.S. Court of Appeals for the District of Columbia held that the lower court should not have dismissed a lawsuit filed by the U.S. House of Representatives challenging the Executive Branch’s transferal of appropriated funds to the Department of Defense to build a physical barrier along the southern border of the United State. The case is More than $8 billion is at stake, a sum that had been transferred from various federal accounts not involved with building the wall. The appeals court held that the lower court should not have dismissed this lawsuit because the House of Representatives had standing to bring this lawsuit even if the U.S. Senate was not involved with this litigation. Accordingly, the case was returned to the lower court for additional findings, with the appeals court noting that the Constitution’s Appropriation’s Clause serves as an important check on the Executive Branch.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Associated Builders and Contractors Northern California Chapter Announces New President/CEO
January 24, 2022 —
Associated Builders and Contractors, Northern California Chapter(January 19, 2022 – Livermore, CA) Associated Builders and Contractors, Northern California Chapter (ABC NorCal) Board of Directors launched an exhaustive, nationwide CEO search, and recently selected Deborah Maus as the next President/CEO. Deborah is a Certified Association Executive (CAE) with 25+ years of strategic and operational leadership. Prior to accepting the position, Deborah served as the chief executive officer of Plumbing Heating Cooling Contractors of California.
Mark Kirkes, President of MK Electric & Design Inc—and 2022 ABC NorCal Chair— said, "We believe Deborah will focus on strengthening organizational structure to meet new and expanding program needs, guide policy development and strategic innovations, bring increased value to members and continue to be the leading voice of the merit shop in Northern California. Her demonstrated knowledge of the industry and her support of all who desire to succeed in the construction industry made her an ideal choice to advance ABC's mission in Northern California."
Former ABC NorCal President/CEO Michele Daugherty is transitioning to the ABC Central Florida Chapter as President/CEO, continuing her 16+ years of service in ABC. ABC 2021 Chair, Josh Ward noted, "Michele has been working for ABC since 2006 and we are happy to see that she is staying in the ABC family—continuing to fight for the Merit Shop. The Executive Committee expresses its sincere appreciation for Michele and her remarkable services to the organization. Her enthusiasm and leadership will be deeply missed and difficult to replicate. However, we believe we have found the right person in Deborah Maus."
About ABC Northern California Chapter
ABC Northern California Chapter (ABC NorCal) is a trade association founded on the merit shop philosophy and dedicated to serving construction professionals from Fresno to the Oregon border. Our mission: To promote free enterprise by advancing the merit shop philosophy in the construction industry through education, advocacy and business services. To learn more visit www.abcnorcal.org
Read the court decisionRead the full story...Reprinted courtesy of
Architects Should Not Make Initial Decisions on Construction Disputes
July 05, 2023 —
Bill Wilson - Construction Law ZoneA common provision often deleted from the standard form AIA documents is the provision in the AIA A201 General Conditions requiring an Initial Decision Maker (IDM) for claims between the contractor and owner. In the A201, the contracting parties have the option of naming their own IDM for the project. If an IDM is not selected (which is typically the case) the architect serves this role by default. While it is in all parties’ best interests to resolve disputes quickly and efficiently, using the architect as the IDM is not the best way to achieve such a resolution.
Several reasons work against using the architect as the IDM. Contractors typically don’t trust architects to be impartial in resolving disputes because the architect is paid by the owner. Most architects don’t have the temperament or any training to facilitate dispute resolution. An architect’s “initial decision” could even drive the parties further apart and lead to further issues later in the project. The architect may also be perceived to be part of the problem that led to the dispute in the first place. Also, many architects simply prefer to avoid serving the thankless role of an IDM altogether. Lastly, inserting the architect into the dispute resolution process as a required IDM adds an additional unnecessary step to dispute resolution, which can delay the overall procedure.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
Hurdles with Triggering a Subcontractor Performance Bond
April 05, 2017 —
David Adelstein – Florida Construction Legal UpdatesThere have been a couple of decisions as of late, particularly in federal court, that have gone in favor of a performance bond surety and against a general contractor’s claim against a subcontractor’s performance bond. These decisions have been so unfavorable that they may be swaying certain internal decisions to move to subcontractor default insurance with, perhaps, subcontractors that pose less risk. From the general contractor’s perspective, if they have to stop the management of the job and progress to jump through hoops to trigger the performance bond’s obligations, rightfully or wrongfully, the bond may not provide them the value they need. Performance bonds are an appropriate product in many instances, but there should be more consistency regarding the actual trigger of a subcontractor’s performance bond obligations. Project teams need to absolutely understand what efforts they need to take, and how they need to take such efforts, in order to properly trigger a performance bond’s obligations. This is a must (and I have presented many seminars on this very issue). Or, the general contractor should move away from the traditional AIA /standard performance bond form, which is the direction I always go when I am involved in the drafting of a performance bond.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
New York Court of Appeals Finds a Proximate Cause Standard in Additional Insured Endorsements
June 15, 2017 —
Geoffrey Miller - Saxe Doernberger & Vita, P.C.In The Burlington Insurance Company v. NYC Transit Authority, et al., No. 2016-00096, the New York Court of Appeals issued a landmark decision with regard to the meaning of “caused, in whole or in part, by” in the additional insured context. In a split decision, the court rejected Burlington Insurance Company’s argument that the language implied a “negligence” standard, but held that coverage was provided to the additional insured only where the named insured’s acts or omissions were the proximate cause of the injury:
While we [the majority] agree with the dissent that interpreting the phrases differently does not compel the conclusion that the endorsement incorporates a negligence requirement, it does compel us to interpret ‘caused, in whole or in part’ to mean more than ‘but for’ causation. That interpretation, coupled with the endorsement’s application to acts or omissions that result in liability, supports our conclusion that proximate cause is required here.[1]
Read the court decisionRead the full story...Reprinted courtesy of
Geoffrey Miller, Saxe Doernberger & Vita, P.C.Mr. Miller may be contacted at
gjm@sdvlaw.com
Philadelphia Proposed Best Value Procurement Bill
December 08, 2016 —
Wally Zimolong – Supplemental ConditionsAn opinion piece in today’s Philadelphia Inquirer concerning proposed legislation that would change the way the City of Philadelphia awards public construction projects is causing quite a stir. The article concerns legislation that would allow the City to award public construction contracts based on a “best value” approach rather than the current requirement that the contract be awarded to the lowest responsible and responsive bidder. The author worries that by removing the current objective criteria and replacing it with subjective ones, contracts can be steered to politically favored contractors. The author cites the recent no-bid contract awarded to a law firm run by the friend of Mayor Jim Kenney as an example of the chaos would ensue if this bill was passed.
Considering that the Bill’s sponsor, Bobby Hennon, is under FBI investigation, and some of the Mayor’s biggest supporters are as well, the author has ever right to be concerned. However, article comes up short in explaining what the Bill says and what best value procurement, if adopted, would mean for public construction work in Philadelphia.
First, the Bill that Councilman Hennon is proposing is actually a Bill that would make the best value procurement question a ballot question next November. In other words, the Bill, if passed, would but to a City wide vote the question of whether the City should change it procurement practices to permit the best value approach to be used in addition to the low bid approach that is current used.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com