Unlicensed Contractors Nabbed in Sting Operation
September 09, 2011 —
CDJ STAFFThe California State License Board charged sixteen people in the Fresno area with accepting contracting jobs without licenses. The Statewide Investigative Fraud Team of the CSLB set up a sting operation at a home in Clovis, California seeking bids on tree service, painting, and general contracting services. Those who bid for jobs at more than $500 are required under California law to be licensed. Unlicensed contractors can only work on jobs with a cost to the homeowner of less than $500 and must inform the homeowner that they are not licensed.
In addition to citing contractors for not possessing appropriate licenses, the CSLB also cited contractors for failure to carry workers compensation insurance and illegal advertising. Further, California law limits down payments to the lesser of ten percent or $1,000. Two contractors were cited for requesting excessive down payments.
One contractor, an unlicensed tree service contractor, had been cited previously in a sting operation. He failed to show up for his court date.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Washington Supreme Court Expands Contractor Notice Obligations
November 28, 2018 —
Brett M. Hill - Ahlers Cressman & Sleight BlogThe Washington State Supreme Court dealt another blow to public works contractors in Washington State. In a case recently issued by the court, Nova Contracting, Inc. v. City of Olympia, [1] the court expanded contractors’ obligations when providing notice on public works construction projects. The Nova Contracting case was the subject of a previous blog. The case involved Nova Contracting and the City of Olympia. Nova was the low bidder on the contract. Nova alleged that the City of Olympia did not want Nova to win the job and intentionally hindered Nova’s ability to perform the job. The facts alleged by Nova, which were covered in the previous blog, involved the City’s improper and apparently punitive rejection of submittals on the job and the City’s eventual wrongful termination of Nova. Of significance in the case is that Nova never actually began work on the job. All that Nova had done at the time of termination was begin mobilizing its equipment on site. The Court of Appeals found that Nova had alleged sufficient facts to establish that the City violated the duty of good faith and fair dealing by improperly rejecting Nova’s submissions and had breached the contract with Nova by improperly terminating.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers Cressman & Sleight PLLCMr. Hill may be contacted at
brett.hill@acslawyers.com
Washington Supreme Court Upholds King County Ordinance Requiring Utility Providers to Pay for Access to County’s Right-of-Way and Signals Approval for Other Counties to Follow Suit
March 02, 2020 —
Kristina Southwell - Ahlers Cressman & Sleight PLLCOn December 5, 2019, the Washington State Supreme Court released its opinion in King County v. King County Water Districts, et al.,[1] upholding King County’s Ordinance 18403, which requires utility companies who are franchise grantees to pay “franchise compensation” for their use of the County rights-of-way. Generally, utility companies must apply for and obtain from the County a franchise permitting it to do necessary work in the County rights-of-way. [2] Previously, King County only charged an administrative fee associated with issuing such a franchise. But with the new franchise compensation charges, King County estimates that it will raise approximately $10 million dollars per year for its general fund.
Ordinance 18403 passed in November 2016 and was the first of its kind in the state. The ordinance created a rule, set forth in RCW 6.27.080, requiring electric, gas, water, and sewer utilities who are granted a franchise by King County to pay “franchise compensation” in exchange for the right to use the County’s rights-of-way. The rule provides that franchise compensation is in the nature of an annual rent payment to the County for using the County roads. King County decides an initial estimate of the charge by considering various factors such as the value of the land used, the size of the area that will be used, and the density of the households served. But utility companies can negotiate with the County over the final amount of franchise compensation.
Read the court decisionRead the full story...Reprinted courtesy of
Kristina Southwell, Ahlers Cressman & Sleight PLLCMs. Southwell may be contacted at
kristina.southwell@acslawyers.com
Repair Cost Exceeding Actual Cash Value Does Not Establish “Total Loss” Under Fire Insurance Policy
June 05, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn California FAIR Plan Assn. v. Garnes (No. A143190, filed 5/26/17), a California appeals court ruled that “total loss” under Insurance Code section 2051 refers to physical damage or loss, not the economic fact that the cost of repair exceeds the actual cash value of a home. Thus, where the home is not physically destroyed, the insured is entitled to the actual cost of repair, minus depreciation, even if that amount exceeds the fair market value of the home.
In Garnes, the insured had a fire policy issued by the California FAIR Plan with limits of $425,000. It was agreed that the assessed value of the insured home was only $75,000. The insured suffered a kitchen fire with estimated repair costs of $320,000. The FAIR Plan declared the home a total loss because the cost of repair exceeded the home’s value, and offered to pay the actual cash value as provided by Insurance Code section 2051(b)(1).
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Not So Fast, My Friend: Pacing and Concurrent Delay
April 25, 2022 —
William E. Underwood - ConsensusDocsWhen critical path activities are delayed by the owner (or another party), contractors will sometimes “pace,” or slow down, other activities to match the owner-caused delay. After all, why should the contractor hurry up and wait? But paced activities can often appear as concurrent delays on a project’s overall schedule. And all too often, contractors fail to contemporaneously document their efforts to pace work. Not only can this create avoidable disputes with owners and other contractors, but it can also create future roadblocks to the recovery of delay damages. This article examines the interplay between pacing and concurrent delay[1] and what contractors should do to minimize risk and preserve their rights to obtain more than a simple time extension for project delays.
Pacing versus Concurrent Delay
As a basic matter, most contracts allocate responsibility/liability for a schedule delay to the party that caused the delay. For example, if an owner is contractually required to provide equipment for a contractor to install, then the owner likely bears responsibility for any delays caused if the equipment is delivered late. If, however, the contractor was also behind schedule on other activities during this time and the project would have been delayed regardless of the owner’s late deliveries, then the delay is probably concurrent. And the contractor will generally be entitled to only an extension of time, and no other monetary relief.
Read the court decisionRead the full story...Reprinted courtesy of
William E. Underwood, Jones Walker LLP (ConsensusDocs)Mr. Underwood may be contacted at
wunderwood@joneswalker.com
To Sea or Not to Sea: Fifth Circuit Applies Maritime Law to Offshore Service Contract, Spares Indemnity Provision from Louisiana Oilfield Indemnity Act
March 29, 2017 —
Richard W. Brown & Afua Akoto – Saxe Doernberger & Vita, P.C.Faced with the issue of whether maritime or state law should be applied to determine the validity of an indemnity clause in a Master Services Contract (MSC), the Fifth Circuit affirmed that where there is no historical treatment of the contract in question (1), it would consider six factors established in Davis (2).
In Doiron, the Apache Corporation and STS (3) entered a broad-form blanket MSC, under which STS agreed to perform flow-back services, a process designed to dislodge solid objects from inside a well, on Apache’s well located off shore of Louisiana. The MSC also contained an indemnification provision, which required STS to defend and indemnify Apache and its company groups against all claims of property injury or bodily injury. During the flow-back operation, Larry Doiron Inc. (LDI), one of the Apache Company groups, supplied a crane barge for use by STS employees. Subsequently, the crane knocked over an STS employee, causing him to suffer severe injuries. LDI then made a formal demand to STS for defense and indemnification. STS rejected the demand and argued that the Louisiana Oilfield Indemnity Act applied to the MSC instead of maritime law. Pursuant to the Act, indemnity clauses in agreements pertaining to wells for oil, gas or water are void as against public policy. But, under maritime law, the enforcement of such provisions is not barred. Therefore, if the MSC was construed under the Act, STS had no duty to defend or indemnify LDI.
Reprinted courtesy of
Richard W. Brown, Saxe Doernberger & Vita, P.C. and
Afua S. Akoto, Saxe Doernberger & Vita, P.C.
Mr. Brown may be contacted at rwb@sdvlaw.com
Ms. Akoto may be contacted at asa@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Can’t Get a Written Change Order? Document, Document, Document
August 29, 2018 —
Todd M. Heffner - Smith CurrieMost construction contracts require that any changes to the work be made formally, in writing, via a change order, work directive, or similar written document. Frequently, however, changes to the work or extra work are communicated orally by the architect, engineer, or owner’s representative, instead of in writing. What is the contractor to do in such a situation? The best option is follow the provisions of the contract and demand a written change order before performing changed work. Unfortunately, the realities of construction sometimes make it impossible to get the changes in the proper format in a timely manner. Savvy contractors will maintain schedule and produce written documentation of the change in lieu of a formal change order or directive. But many contractors will simply proceed with the changed work, relying on the owner, architect, or engineer to do the right thing and stand by their oral instructions.
Read the court decisionRead the full story...Reprinted courtesy of
Todd M. Heffner, Smith CurrieMr. Heffner may be contacted at
tmheffner@smithcurrie.com
Georgia Appellate Court Supports County Claim Against Surety Company’s Failure to Pay
August 30, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPIn 2015, Hall County (Georgia) brought legal action against Selective Insurance Company of America, Inc., the surety company for contractor Ruby Forrest. Hall County had contracted Ruby Forrest to complete and maintain sidewalk systems within three residential subdivisions that Ruby Forrest owned and was developing. Ruby Forrest did not complete the work as promised, and Hall County brought action against the contractor’s surety to recover under performance / maintenance bonds for uncompleted work and to assert bad faith claim for punitive damages and attorney fees.
Selective Insurance did not dispute that it had issued the bonds, that Ruby Forrest did not complete the sidewalk systems within the bond periods or their extensions, or that Hall County provided Selective Insurance with timely notice of Ruby Forrest’s failure to complete the work. Instead, Selective Insurance asserted that the original claim by Hall County was time-barred under a provision in the bonds that stated that “the Issuer will have no more liability after” the expiration date of the bond.