FEMA Fire Management Assistance Granted for the French Fire
July 08, 2024 —
The Federal Emergency Management AgencyOAKLAND, Calif. – The Federal Emergency Management Agency's (FEMA) Region 9 Administrator authorized the use of federal funds on July 4 at 11:37 p.m. PDT / 2:37 a.m. EDT to assist the state of California to combat the French Fire burning in Mariposa County.
On July 4, the state of California submitted a request for a Fire Management Assistance Grant (FMAG). At the time of the request, the fire threatened approximately 1,019 homes in and around Mariposa, CA, population 1,300. 95% of the threatened homes are primary residences and 5% are secondary residences.
The fire started on July 4, 2024 and had burned more than 790 acres of State and private land. The fire was 0% contained. There are five large fires burning uncontrolled within the State.
FMAGs provide federal funding for up to 75 percent of eligible firefighting costs. The Disaster Relief Fund provides allowances for FMAGs through FEMA to assist in fighting fires that threaten to become a greater incident.
Eligible costs covered by FMAGs can include expenses for field camps, equipment use, materials, supplies and mobilization, and demobilization activities attributed to fighting the fire.
For more information on FMAGs, visit https://www.fema.gov/assistance/public/fire-management-assistance.
Read the court decisionRead the full story...Reprinted courtesy of
New Jersey Appellate Court Reinstates Asbestos Action
March 05, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to the New Jersey Law Journal, an asbestos case involving “a long-time ship worker who died of mesothelioma was reinstated by a New Jersey appellate court on March 3.” A lower court judge had “dismissed the claims against them based on his view that the evidence presented by the plaintiff was insufficient to show that the ships on which he worked contained asbestos and that he was exposed to it.” However, the appeals judges disagreed.
“Although the summary judgment motion was decided on a very narrow ground, we conclude that the record as a whole establishes a triable issue as to whether plaintiff was exposed to asbestos or asbestos-containing products on defendant’s dredges,” judges Susan Maven and Henry Carroll stated, according to the New Jersey Law Journal.
Read the court decisionRead the full story...Reprinted courtesy of
Procedural Matters Matter!
December 10, 2024 —
Suzanne M. Nicholson - Wilke FleuryAs an appellate practitioner, I am keenly aware that sometimes, a procedural matter can doom what would otherwise be a meritorious issue for appeal. Trial attorneys are well-advised to check and double-check procedural rules and case law governing the issues in their cases. Here’s a few recent developments to be aware of.
The record on appeal: electronic recordings now available in Santa Clara County.
It should not be news to anyone that it is the appellant’s burden to produce an adequate record for appeal. That includes not just the written submissions to the trial court, but also reporter’s transcripts of all proceedings that could have a substantive impact on your case. If you do not have a court reporter present for your hearing, you will be struck trying your best to get an agreed statement or a settled statement should the case go up on appeal. Believe me, that can be a serious challenge. Any omissions or deficiencies are going to result in presumptions made against the appellant.
Read the court decisionRead the full story...Reprinted courtesy of
Suzanne M. Nicholson, Wilke FleuryMs. Nicholson may be contacted at
snicholson@wilkefleury.com
Contractor Side Deals Can Waive Rights
October 02, 2023 —
Christopher G. Hill - Construction Law MusingsHere at Construction Law Musings, we are quite fond of the Federal Miller Act and it’s Virginia counterpart, the “Little” Miller Act. Both of these statutes allow a subcontractor or supplier on a government construction project the security to perform their work with the knowledge that a bonding company will back their claim for payment. These acts are necessary because a construction company cannot file a mechanic’s lien on a government owned piece of property.
As a general rule the Miller Acts impose almost strict liability on a contractor and its surety to pay for work performed by a downstream supplier or subcontractor. However, as a recent case out of the Fourth Circuit Court of Appeals makes clear, this rule is not without exceptions.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
A License to Sue: Appellate Court Upholds Condition of Statute that a Contracting Party Must Hold a Valid Contractor’s License to Pursue Action for Recovery of Payment for Contracting Services
June 21, 2017 —
Omar Parra & Jesse M. Sullivan - Haight Brown & Bonesteel LLPCalifornia Business & Professions Code section 7031(a) requires a party to have contractor’s license in order to maintain an action for compensation for services performed for which a contractor’s license is needed. In Phoenix Mechanical Pipeline, Inc. v. Space Exploration Technologies Corp., No. B269186 (2017 WL 2544856) (Cal. Ct. App. June 13, 2017), the Court of Appeal for the Second Appellate District considered the scope of this statute in denying, in part, Phoenix Mechanical Pipeline, Inc.’s (“Phoenix Pipeline”) appeal of a trial court ruling granting Space Exploration Technologies Corporation’s (“SpaceX”) demurrer to Phoenix Pipeline’s second amended complaint, without leave to amend.
Phoenix Pipeline filed the underlying lawsuit for, among other claims, breach of contract and breach of the duty of good faith and fair dealing arising from an agreement with SpaceX for Phoenix Pipeline to perform various plumbing, concrete removal and electrical services. Phoenix Pipeline alleged SpaceX paid for such services from 2010 to October 2013, but failed to pay Phoenix for services performed from October 2013 to August 2014, totaling just over $1,000,000. According to Phoenix Pipeline, this work was performed pursuant to a series of invoices, which constituted individual agreements between SpaceX and Phoenix Pipeline.
Reprinted courtesy of
Omar Parra, Haight Brown & Bonesteel LLP and
Jesse M. Sullivan, Haight Brown & Bonesteel LLP
Mr. Parra may be contacted at oparra@hbblaw.com
Mr. Sullivan may be contacted at jsullivan@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
No Coverage for Collapse of Building
January 04, 2021 —
Tred R. Eyerly - Insurance Law HawaiiDamage to a building caused by the break of a water pipe was not a collapse under the policy. Naabani Twin Stars v. Travelers Cos., 2020 U.S. Dist. LEXIS 196443 (D. N. M. Oct. 22, 2020).
An underground water line ruptured on plaintiffs property This caused a collapse under the adjacent parking lot, which in turn caused land beneath the building go change positions and damage the building. A geotechnical consultant concluded that a material change in the site conditions occurred as a direct result of the rupture of the water pipe in the parking lot, and that those changes directly affected the settlement of the building.
Travelers denied coverage for the damage. Travelers concluded that the building settlement was the result of subsurface movement, which invoked the earth movement exclusion. Travelers inspection concluded that the building was not in a state of collapse. The policy defined collapse as "an abrupt falling down or caving in of a building or structure, or any part of a building or structure, with the result that the building, or part of the building, cannot be occupied for its intended purpose."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Requirement to Post Collateral Under General Agreement of Indemnity Is Real
May 16, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn prior postings, I have discussed the all-powerful General Agreement of Indemnity (click
here and
here). This is the document a bond-principal executes to obtain bonds (e.g., performance and payment bonds). Not only does the bond-principal execute this General Agreement of Indemnity, but typically, so do other indemnitors such as the company’s principals and their spouses, other related companies, etc. The objective is that the surety has financial comfort that if a claim is made against the bond, there are avenues where it will get reimbursed and indemnified for any cost it incurs, or payment it makes, relative to that claim against the bond. When a surety issues bonds, the objective is that all losses it incurs gets reimbursed because the bonds are NOT insurance policies.
One of the powerful tools the surety can exercise in the General Agreement of Indemnity is to demand the bond-principal and other indemnitors to post collateral in an amount the surety deems sufficient to cover any losses it may incur. This is a right in any General Agreement of Indemnity I have seen and is a right the surety can rightfully exercise.
A recent example is shown from the opinion in Philadelphia Indemnity Ins. Co. v. Quinco Electrical, Inc., 2022 WL 1230110 (M.D.Fla. 2022), which pertains to the surety’s motion for preliminary injunction.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction Managers, Are You Exposing Yourselves to Labor Law Liability?
February 22, 2021 —
Timothy P. Welch - Hurwitz & Fine, P.C.When dealing with construction site accidents, who a party is matters. Under Labor Law sections 200, 240(1) and 241(6) owners, contractors,
and their agents have a non-delegable duty to provide reasonable and adequate protection to workers from risks inherent at work sites, with a specific emphasis placed on elevation-related hazards. Given the near strict liability nature of Labor Law section 240(1), it is critical to identify whether a party is a proper Labor Law defendant from the get-go.
While identifying the owner (and usually the contractor) may be relatively straightforward, identifying “their agents” has proven to be a more complex undertaking. It should be noted that the requirements set forth in the Labor Law are non-delegable from the standpoint of the owner or contractor, however, the duties themselves can be assigned to “agents” of an owner or “agents” of a contractor. When such an assignment occurs, the same non-delegable duty held by the owner or contractor is imposed on the agents as well. Moreover, “once an entity becomes an agent under the Labor Law it cannot escape liability to an injured plaintiff by delegating the work to another entity.[1]”
An entity that often skirts the line between being an agent and not, is the Construction Manager. Traditionally, the Construction Manager has been found to be outside the purview of the Labor Law when its scope of work is narrowly focused on scheduling and general coordination of the construction process. However, when a Construction Manager’s scope expands, so does its risk that it may, in fact, become a proper Labor Law defendant.
Read the court decisionRead the full story...Reprinted courtesy of
Timothy P. Welch, Hurwitz & Fine, P.C.Mr. Welch may be contacted at
tpw@hurwitzfine.com