The Independent Tort Doctrine (And Its Importance)
October 24, 2022 —
David Adelstein - Florida Construction Legal UpdatesA non-construction raises an important legal principle. Here it is because it applies to construction disputes. It actually applies to many business-type disputes. It is based on what is widely referred to as the independent tort doctrine:
Florida law does not allow a party damaged by a breach of contract to recover exactly the same contract damages via a tort claim. “It is a fundamental, long-standing common law principle that a plaintiff may not recover in tort for a contract dispute unless the tort is independent of any breach of contract. A plaintiff bringing both a breach of contract and a tort claim must allege, in addition to the breach of contract, “some other conduct amounting to an independent tort.”
Bedoyan v. Samra, 47 Fla.L.Weekly D1955a (Fla. 3d 2022) (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
3 Common Cash Flow Issues That Plague The Construction Industry
August 20, 2019 —
Patrick Hogan, HandleThe construction industry has its fair share of serious cash flow problems. The nature of the industry with long periods between billing and collection, the unpredictability of some business factors, and even the day-to-day decisions of stakeholders have a huge effect on cash reserves.
So how can you protect your business from these cash flow problems? Having a greater awareness of the most common cash flow problems is the key to maintaining your financial stability. Here are some of the top cash flow issues that construction companies need to watch out for.
1. Uncontrolled business growth
The growth of a business as a cash flow problem sounds unintuitive. It is supposed to be a positive thing. So how could it hurt your construction business? When it goes out of control.
During the growth phase, the company will need to expand its operations to meet the increasing demand. This means renting a larger office space, hiring more staff, and buying more inventory, all of which can burn through the company’s cash quickly. The more substantial the level of your growth is, the more your cash flow is affected.
Growth is a good thing, but it is important to be aware of the pitfalls that you could encounter that can lead to cash flow problems. If you are dealing with a volatile growth instead of a stable one, you have to think twice before expanding your operations. A quarter with a large number of construction project deals does not guarantee the same happening in a subsequent quarter.
2. Change of scope or scope creep
The scope, or the statement of work, is the foundation that guides a construction project from start to finish. It specifies all the deliverables needed by the project as agreed by all stakeholders. When the existing requirements are altered, new features are added, or project goals are changed uncontrollably, what happens is scope creep and it can hurt a company’s cash flow.
Construction projects can take a long time before they are finished. A lot of factors can result in changes in the scope. There may be changes in the market strategy, market demand, and other unpredictable variables that make changes in the project requirements a necessity. These changes build up and the project may shift away from what was intended, causing delays, loss of quality, and the rise of planned costs.
One way to prevent scope creep from affecting cash flow significantly is charging a fee for variations of the scope of work. However, having a solid and clear scope baseline is still the best way to combat scope creep. Reminding clients of what you signed up for by referring to the baseline is a good strategy to deal with pushy clients.
3. Payment delays and nonpayment
As previously mentioned, the construction industry tends to have a lengthy period between sending an invoice and collecting payments. And if you are too passive in your collection, clients are more likely to extend pay periods and delay paying you.
Unexpected delays in payment and other payment issues can have a devastating effect on companies that have little to no cash reserves. Without a cash cushion to fall back on, payment issues can threaten the existence of the business itself. If you are unable to manage your receivables, you will not have enough cash to pay the bills, pay employees, and fund your growth.
Payment delays and nonpayment can happen for several reasons. They can be simple like mistakes in the invoicing or the person needed to approve the invoice is unavailable. More serious reasons like a client unsatisfied with your service or, worse, trying to scam you are also possibilities. For these reasons, it is crucial to communicate with clients properly and see if you can agree with a payment structure or pursue legal action.
The construction industry operates slightly differently from other industries. Different projects produce different cash flow issues and require different strategies. By being aware of the top cash flow problems that can hurt your construction business, you will be better equipped in dealing with them in case they happen.
About the Author:
Patrick Hogan is the CEO of Handle, where they build software that helps contractors, subcontractors, and material suppliers secure their lien rights and get paid faster by automating the collection process for unpaid construction invoices. Read the court decisionRead the full story...Reprinted courtesy of
Patrick Hogan, CEO, Handle
Health Care Construction Requires Compassion, Attention to Detail and Flexibility
July 01, 2019 —
Coker Barton - Construction ExecutiveWhen it comes to renovating and expanding hospitals, there is one principle that everyone can agree on: patients, family and hospital staff must be placed at the forefront of every stage of the job, ultimately dictating the project’s timeline. For a health care project to be a success, a general contractor needs to have industry-specific experience, must emphasize communication and scheduling and—most importantly—have a passion for the industry.
Capably and safely work in a health care environment
Health care requires a level of detail and understanding of the industry that is not found in other construction sectors. Builders must focus on infection control and interim life safety measures to protect patients, visitors and staff. There is accountability involved that goes beyond completing a project right on schedule.
For example, the expansion of The Studer Family Children’s Hospital at Sacred Heart in Pensacola, Fla., included a new 175,000-square-foot tower in addition to building out space above the Neonatal Intensive Care Unit. Anytime the contractor is building next to or over patients, especially those who are most vulnerable, it is on alert. It sets up containment areas, which help maintain the negative pressure in the construction area by pulling air in versus blowing dirty air out, as well as keep dust and other contaminants inside the construction area. There is no room for mistakes, which is why these techniques require more training and experience to properly execute.
Reprinted courtesy of
Coker Barton, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
How to Remove a Mechanics Lien from Your Property
March 21, 2022 —
Hannah Kreuser - Porter Law GroupIt sometimes happens that a contractor or material supplier records a mechanics lien on your property that becomes expired. Other times, the mechanics lien may be wrong, invalid and unenforceable for some reason, serving no legitimate purpose. The contractor or material supplier may be reasonable and release the mechanics lien once these issues are brought to its attention, but the contractor or material supplier may very well refuse to release the mechanics lien when requested. When this happens, what are your options?
In California, there are various ways to bring this type of mechanics lien to a court’s attention in the hopes that the court will cause it to be released. Three of the more common methods are: (1) a petition under California Civil Code (“CCC”) § 8480; (2) a petition under California Code of Civil Procedure (“CCP”) § 765.010; or (3) a Lambert motion. This article will briefly discuss each of these methods.
Read the court decisionRead the full story...Reprinted courtesy of
Hannah Kreuser, Porter Law GroupMs. Kreuser may be contacted at
hkreuser@porterlaw.com
Employee Handbooks—Your First Line of Defense
April 15, 2015 —
Craig Martin – Construction Contractor AdvisorThis spring has been busy with questions about employee handbooks. Perhaps it is because the NLRB just issued a directive on the legality of various clauses usually contained in handbooks. Or perhaps it’s because employers, including construction companies, are realizing the importance that handbooks play in defending against claims of harassment.
Employee Handbooks Are Important
Employee handbooks are an employer’s first line of defense in claims of harassment. A key provision to any employee handbook is an anti-harassment provision that includes:
- A definition of harassment;
- The process to complain about harassment;
- A commitment to investigate all claims of harassment; and
- An assurance that no one will be retaliated against for reporting harassment.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Blindly Relying on Public Adjuster or Loss Consultant’s False Estimate Can Play Out Badly
May 03, 2021 —
David Adelstein - Florida Construction Legal UpdatesInsurance policies, particularly property insurance policies, have a concealment or fraud provision that, in essence, gives the insurer an out if the insured submits a fraudulent claim, a false claim, or conceals material facts. Unlike a traditional fraud claim where a party needs to prove intent, the provision is broad enough that it does not require any intent behind making a false statement. See Mezadieu v. Safepoint Ins. Co., 46 Fla.L.Weekly D691c (Fla. 4th DCA 2021). For this reason, and as exemplified below, do NOT blindly rely on a public adjuster or loss consultant’s estimate that contains false statements because those false statements, particularly if you know they are false, can play out badly for you! Review the estimate and ask questions about it to make sure you understand what is being included in the loss or damages estimate.
In Mezadieu, a homeowner submitted a claim to her property insurance carrier due to a second-floor water leak emanating from her bathroom. She submitted an estimate from her public adjuster that included damages for her kitchen cabinets directly below the second-floor bathroom, as well as other items on her first-floor. Her carrier denied coverage based on the exclusion that the policy excludes damage caused by “[c]onstant or repeated seepage of water or steam…which occurs over a period of time.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Florida Enacts Property Insurance Overhaul for Benefit of Policyholders
July 05, 2023 —
Laura Farrant & Bradley S. Fischer - Lewis BrisboisFort Lauderdale, Fla. (June 13, 2023) – On June 1, 2023, Governor Ron DeSantis signed into law CS/SB 7052 (the Act), increasing consumer protection and insurer accountability in Florida. The newly enacted and amended statutes under CS/SB 7052 bolster policyholder protections and impose greater insurer oversight, including heightened penalties for insurer misdeeds in the state under a new law that will take effect on July 1, 2023 (this legal alert does not address all of the statutory revisions associated with the Act). As House Speaker Paul Renner noted, “The insurance legislation signed by Governor DeSantis today . . . not only empowers homeowners, but also cultivates market-driven competition, ultimately leading to lower costs.”
Statutory Revisions Regarding Insurance Coverage
The Act prohibits authorized insurers from cancelling or nonrenewing a property insurance policy for a residential property or dwelling that was damaged by any covered peril until the earlier of: (a) when the property has been repaired; or (b) one year after the insurer issues the final claim payment. The Act also expands current law prohibiting authorized insurers from cancelling or nonrenewing a residential property insurance policy until 90 days after repairs are completed for damages resulting from a hurricane or wind loss that is the subject of a state of emergency declared by the Governor and for which the Office of Insurance Regulation (OIR) has issued an emergency order. See Fla. Stat. §627.4133(2)(d)(1)(a) and (b) (Notice of cancellation, nonrenewal, or renewal premium).
Reprinted courtesy of
Laura Farrant, Lewis Brisbois and
Bradley S. Fischer, Lewis Brisbois
Ms. Farrant may be contacted at Laura.Farrant@lewisbrisbois.com
Mr. Fischer may be contacted at Bradley.Fischer@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defects in Home a Breach of Contract
September 09, 2011 —
CDJ STAFFThe Supreme Court of North Dakota has ruled in Leno v. K & L Homes, affirming the verdict of the lower court. K & L Homes argued that district court had erred in several ways, including by refusing to instruct the jury on comparative fault, denying a request for inspection, and not allowing a defendant to testify on his observations during jury viewing.
The Lenos purchased a home constructed by K & L Homes, after which they alleged they found cracks, unevenness, and shifting, which they attributed to improper construction. They claimed negligence on the part of K & L Homes. K & L Homes responded that the Lenos were responsible for damage to the home. The Lenos dropped their negligence claim, arguing breach of contract and implied warranties.
Before the trial, after the discovery period had passed, K & L Homes requested to inspect the home. This was rejected by the court. Kelly Moldenhauer, the owner of K & L Homes sought to testify about his observations during the jury’s viewing of the house. The court denied this too. The jury found that K & L was in breach of contract and awarded damages to the Lenos.
The North Dakota Supreme Court noted that K & L Homes gave “warranties that the home had been built according to local building codes and laws, and that the house was fit for its particular purpose as a residence.” The court found that a defective home breached this warranty. Further, the home violated an implied warranty of fitness.
The district court had denied K & L’s request to inspect the home, as the discovery period had ended and it would not give the Lenos time to do further discovery of their own. At the time of the request, there was only twenty-two days before the trial. The Supreme Court ruled that this was not an abuse of discretion of the part of the district court.
The Lenos had requested that Moldenhauer’s testimony not be permitted, as it would “have the same effect as if the court had granted K & L Homes’ pretrial request for inspection.” K & L Homes agreed to this in court, replying, “okay.”
The decision affirms the judgment of the district court and the damages awarded to the Lenos by the jury.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of