Another Reminder that Your Construction Contract Language Matters
June 06, 2018 —
Christopher G. Hill - Construction Law MusingsHere at Musings, I have often (some might say too often) discussed the fact that in Virginia (as well as other places), your construction contract language will be strictly enforced. I have also discussed the need for attorney fees provisions as well as other language in order to mitigate your risk as a contractor. A recent case from the City of Roanoke Circuit Court discussed both of these principals and their intersection.
In LAM Enterprises, LLC v. Roofing Solutions, Inc., the Roanoke Court looked at a contract between LAM and Roofing Solutions, Inc. that contained two provisions of the construction contract between the parties. The first provision limited the liability of Roofing Solutions to the contract price. The second provision is a relatively typical “prevailing party” attorney fees provision in which the winner of any lawsuit would be entitled to collect its attorney fees. For the specific language of these provisions, I commend the opinion linked above for your reading.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Expansion of Statutes of Limitations and Repose in K-12 and Municipal Construction Contracts
March 27, 2019 —
Henry Bangert - Colorado Construction LitigationThe purpose of this whitepaper is to bring attention to a trend in K-12 and municipal construction contracts, which expands the time periods for law suits against construction professionals.
Introduction and Background
Under Colorado statute, the period of time within which a legal action for construction defects may be brought against a construction professional in Colorado is two years from when the claimant (or its predecessor in interest) discovers or in the exercise of reasonable diligence should have discovered the physical manifestations of a defect (the “Statute of Limitations”), but in no case may an action be brought more than six years after substantial completion of the improvement, unless the claim arises in the fifth or sixth year after substantial completion, in which event the action may be brought within two years of such date, i.e., up to eight years after substantial completion (the “Statute of Repose”). See C.R.S. § 13-80-104. While the triggering events differ for the Statute of Limitations and Statue of Repose, the periods are intended to run concurrently to limit the period of time an action may be brought against construction professionals for construction defects to, at most, eight years after substantial completion. Importantly, these limitations periods may be expanded by agreement.
Prior to 1986, Colorado law provided for a 10-year Statute of Repose. However, in 1986, Colorado’s legislature shortened the Statute of Repose time limit to the current six (or up to eight) year period. In 1986, Colorado also redefined the date the claim arises from the date the defect was discovered or should have been discovered to the date the physical manifestation of a defect was discovered or should have been discovered. Therefore, after 1986, the two-year limitations period could begin to run when a claimant should have discovered the manifestation of a defect, even if the claimant did not recognize that a defect existed.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
New York Office Secures Appellate Win in Labor Law 240(1) Fall in Basement Accident Case
March 20, 2023 —
Nicholas P. Hurzeler & Gregory S. Katz - Lewis BrisboisNew York, N.Y. (March 14, 2023) – New York Appellate Partner Nicholas P. Hurzeler and Managing Partner Gregory S. Katz recently prevailed when the New York Appellate Division, Second Department affirmed the dismissal of a Labor Law 240(1) claim involving an accident that occurred in the basement of a house under construction. Balfe v. Graham, ___ AD3d ___ (2d Dept. 2023), decided March 8, 2023.
In this matter, the plaintiff was installing ductwork in the basement of a house that had been stripped down to its foundation when he stepped backwards into an open hole that had been dug out of a concrete floor to accommodate the installation of an ejector pump. The lower court dismissed the plaintiff’s claim based on Labor Law 240(1), and he appealed. The plaintiff argued that he fell into an unprotected opening that should have been covered or barricaded. He further claimed the accident qualifies as a typical “falling worker” case within the scope of Labor Law 240(1), citing the depth of the hole needed to accommodate the ejector pump, and the size of the pump. Under the case law, a worker who falls into an uncovered opening on a construction site will typically be covered by Labor Law 240(1).
Reprinted courtesy of
Nicholas P. Hurzeler, Lewis Brisbois and
Gregory S. Katz, Lewis Brisbois
Mr. Katz may be contacted at Greg.Katz@lewisbrisbois.com
Mr. Hurzeler may be contacted at Nicholas.Hurzeler@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
More on the VCPA and Construction
February 01, 2023 —
Christopher G. Hill - Construction Law MusingsI have posted before regarding the intersection between the Virginia Consumer Protection Act (VCPA) and construction contracting in regard to residential construction projects. A case out of the Eastern District of Virginia District Court further discusses this intersection as it relates to design contracts that also include the procurement and installation of certain design elements post-design. The basic facts of Marcus v Dennis are as follows:
In October of 2018, Defendant Marlene Dennis, the owner of Marlene Dennis Design, LLC (“MDD”), operating out of Virginia, entered into a contract to provide design services and the procurement and installation of certain design elements for the Plaintiffs, Gregory and Jamie Marcus, at their Maryland home. The Marcuses agreed to $175 per hour to Dennis with a cap of a total of $100,000.00 for design consultation and furniture selection and procurement. The Marcuses also agreed that they would pay no more than $250,000.00 for furnishings, rugs, artwork, decorative lighting, and accessories. In November 2020, Dennis sent an invoice for $68,000.00 and informed the Plaintiffs that the total contract fees would be more than the $100,000.00 cap. After paying $124,722.41 in design fees, the Plaintiffs received an invoice for $255,5560.72 in January of 2021. Despite the cap of $250,000.00, the Plaintiffs wired $255,000.00 to Dennis while requesting the backup invoices for the material charges. After much effort and a threat of litigation, the Plaintiffs received documents from Dennis showing that Dennis inflated the costs of the materials prior to passing the costs along to the Marcuses. The Plaintiffs’ home was unfurnished and empty as of April 10, 2021, and the Marcuses had to hire and pay another design team over $85,000.00 to finish Dennis’ work. Needless to say, the Marcuses sued both Dennis and her firm for breach of contract, breach of fiduciary duty, and for violation of the VCPA. Dennis moved to dismiss the Complaint.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Construction Client Advisory: The Power of the Bonded Stop Notice Extends to Expended Construction Funds
February 07, 2014 —
Steven M. Cvitanovic - Haight Brown & Bonesteel LLPCFO to CEO: “I have bad news, the developer on our biggest project has run out of money.” Frightening words for sure, but contractors should not overlook the bonded stop notice in situations where the construction lender seemingly has expended all construction funds. The recent case of Brewer Corporation v. Point Center Financial, Inc. 2014 WL 346636 illustrates this point.
Contractors have two options at their disposal to secure payment on private works of improvement. The first is the mechanics lien. However, construction loan trust deeds are normally recorded prior to the commencement of construction and therefore have priority over mechanics liens. Connolly Development, Inc. v. Superior Court (1976) 17 Cal.3d 803, 827. Enter the bonded stop notice. The bonded stop notice requires the lender to withhold unexpended funds and, if it fails to do so, it is personally liable to the claimant for the full amount of the claim. But the stop notice also has the power of “priority” over any assignment of construction loan funds, whether before or after a stop notice is served. Civil Code § 3166, now Civil Code § 8544.
Read the court decisionRead the full story...Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLPMr. Cvitanovic may be contacted at
scvitanovic@hbblaw.com
Development in CBF Green Building Case in Maryland
August 19, 2015 —
Christopher G. Hill – Construction Law MusingsRemember that case I discussed a while back relating to the Chesapeake Bay Foundation (CBF) building in Annapolis, Maryland? Remember how it was a lawsuit over parallams and failure of those parallams? Do you even remember what a parallam is?
Well, that case was initially dismissed upon the Defendant’s Motion for Summary Judgment because the trial court determined that CBF did not file its lawsuit within the proper time frame after notice of the potential failure of the building materials. Of course, CBF appealed to the Fourth Circuit Court of Appeals under the caption The Chesapeake Bay Foundation, Inc., et. al. v. Weyerhaeuser Company (4th Circuit).
After a great review of the facts of the case, the engineering inspections and reports at issue and the trial court’s ruling, the Fourth Circuit vacated the dismissal and remanded the case for further proceedings. The Court of Appeals reasoned that the district court jumped the gun in dismissing the lawsuit so early in the process because:
a genuine dispute exists as to whether knowledge of the water infiltration problem would have put a reasonable person on notice that the Parallams were susceptible to premature deterioration and that their PolyClear 2000 treatment would not preserve them.
In short, the court ruled that the engineering reports relating to moisture issues would have put CBF on notice of the particular issue of deterioration that was at issue in the litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Insurer Must Defend Insured Against Construction Defect Claims
November 14, 2018 —
Tred R. Eyerly - Insurance Law HawaiiFinding various exclusions inapplicable, the Federal District Court ruled that the insurer owed a defense to the general contractor based upon Texas law. Mt. Hawley Ins. Co. v. Slay Engineering, 2018 U.S. Dist. LEXIS 139363 (W.D. Texas Aug. 15, 2018).
Huser Construction had a CGL policy issued by Mt. Hawley Insurance Company. Huser contracted to design and construct a municipal sports complex with the City of Jourdanton. The project consisted of four baseball fields, a softball field, parking lots and swimming pool. Huser subcontracted with Cody Pools, Inc. to design and build the swimming pool. Huser also subcontracted with Q-Haul, Inc. to perform earth work, grading and storm drainage work at the site.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Montana Theater Threatened by Closure due to Building Safety
January 14, 2015 —
Beverley BevenFlorez-CDJ STAFFPhil Henderson, owner of Stevensville Hardware which is adjacent to the theater, has sued the Stevensville Playhouse, alleging that one of the theater building’s walls leans over into his property, according to the Bitterroot Star. Henderson stated that the leaning wall is interfering with construction plan, and he also alleges that the building is not safe and should be condemned.
A building inspector hired by Henderson declared that “…it seems necessary to notify the Stevensville Playhouse that their structure is to be immediately considered unsafe for entry, occupancy, etc.” However, another engineering firm presented a different view on the situation: “The playhouse has withstood many snow storms and earthquakes during its life and will likely continue to function well into the future. We do not mean to downplay the need to perform the recommended repairs, but we do not feel that the building needs to be condemned at this point.”
Read the court decisionRead the full story...Reprinted courtesy of