What to do about California’s Defect-Ridden Board of Equalization Building
October 01, 2014 —
Beverley BevenFlorez-CDJ STAFFJerry Brown recently signed into law a bill requiring the state of California “to assess its properties in the Sacramento area and develop long-term plans for renovating, replacing or selling the most troublesome buildings,” according to SF Gate. Some say the Board of Equalization building, which was built for $80 million and then repaired for $60 million has construction defects, is “jeopardizing the health and safety of public employees.”
Current problems include “[f]looding, mold, falling windows and free-falling elevators,” reported SF Gate. Furthermore, recently, “three employees filed a $75 million lawsuit against the state, alleging toxic mold in the building is causing extreme fatigue, skin rashes, persistent flu-like symptoms, respiratory illnesses, frequent headaches, memory lapses and fears of cancer.”
“This is a disaster,” Assemblyman Roger Dickinson, D-Sacramento, who authored the bill regarding assessing state capitol buildings, told SF Gate. “It endangers the health and safety of employees and the public alike. And it is costing state taxpayers tens of millions of dollars.”
Read the court decisionRead the full story...Reprinted courtesy of
Using the Prevention Doctrine
April 22, 2019 —
David Erhart - Gordon & Rees Construction Law BlogThe following scenario happens regularly in the construction industry. A contractor on a project reaches out to a subcontractor to perform work. Excited about the prospect of performing the work, the subcontractor signs a contract and puts it nose to the grindstone. After dutifully completing the work the subcontractor turns to the contractor and asks to be paid. But, the contractor refuses saying that there is a provision in the subcontract that says the contractor is only obligated to pay the subcontractor if the contractor receives payment from the owner. So the contractor has completed the work, but has no money to show for it.
One potential remedy for a subcontractor in this situation is the use of the prevention doctrine. “Under the prevention doctrine, ‘if a promisor prevents or hinders fulfillment of a condition to his performance, the condition may be waived or excused.’” Cox v. SNAP, Inc., 859 F.3d 304, 308 (4th Cir. 2017) (quoting Moore Bros. Co. v. Brown & Root, Inc., 207 F.3d 7171, 725 (4th Cir. 2000)). “Put simply, ‘where a party to a contract is the cause of the failure of the performance of the obligation due him or her, that party cannot in any way take advantage of that failure.’” Haddon Hous Assocs v. United States, 711 F.3d 1330, 1338 (Fed. Cir. 2013) (quoting Restatement (Second) of Contracts § 245; Williston, § 39:4).
Read the court decisionRead the full story...Reprinted courtesy of
David Erhart, Gordon & Rees Scully MansukhaniMr. Erhart may be contacted at
derhart@grsm.com
Bert L. Howe & Associates Celebrates 21-Year Success Story
July 31, 2014 —
Beverley BevenFlorez-CDJ STAFFJuly 31, 2014 marks the 21st anniversary of Bert L. Howe & Associates, Inc. (BHA). The company commenced operations on this date 21 years ago today. During the last two decades, the landscape of the construction defect industry as a whole has shifted significantly. In the early nineties, the industry consisted substantially of multi-family residential projects, and construction defect litigation was a regional concern focused primarily on Southern California.
In the intervening 21 years, the construction defect industry has become a nationwide concern with the majority of states adopting builders’ right to repair legislation. To mark the 21st anniversary of BHA, we spoke with some of the key personnel to get some insights and impressions of how the industry and the company have evolved throughout the years.
On July 31st, 1993, Bert formed the company after a long career as a general contractor. He had become involved in the construction forensics field in 1988, providing general construction investigation and expert support services to legal professionals handling multifamily residential cases.
James Howe, the firm's current President and Chief Operating Officer, joined the company in November 1993. Previously, he had been recruited by The New York Times and served as operations manager for their Orange County, Los Angeles, and Inland Empire operations.
In January of 1994, operations were relocated to a small, 1,100-square foot, two-story walk-up in Anaheim Hills, California. James stated that they purchased furniture from Plummers, and he and Bert carted all of the furniture up the stairs and assembled it themselves over the weekend.
Immediately, they hired the first employee, Matthew J. Nardella, an architect and graduate from Cal Poly University, who also came to the firm with substantial construction and design experience.
Matt was scheduled to begin work on January 17th, 1994, the day of the Northridge earthquake. “I remember calling Bert,” Matt said. “‘Bert, is everything okay down there? Do you want me to come in?’ All of the news said freeways collapsed. I didn’t know what was going on with the roads,” Matt continued. “Bert’s like, ‘Yeah, nothing happened here, get over here.’ I said, ‘Okay, I’ll be there.’” Matt chuckled at the memory.
Even back in early 1994, Bert was in high demand as an expert witness. “He was everyone’s go-to-guy,” Matt Nardella stated. “The day a case was filed they would call him first.”
“He had a real desire,” Susan Howe, BHA’s Chief Executive Officer, said. “The primary way Bert worked on growing the business was by showing up, being prepared, and being full of ideas. If there was a problem or an issue, he would come up with a solution on how to handle it in the scope of what we were doing. He identified solutions and provided additional benefits to his clients. That’s how he grew the business, really. He grew each individual relationship.”
During that period, the type and scope of projects began to shift into a more diversified mix, including hotels, resorts, warehouses, storage facilities, restaurants, and more, though, at the time, BHA mainly provided expert witness support in construction defect cases involving attached housing developments, such as condominiums and townhomes.
Many of the other current key employees within the firm were hired during the mid-90s and continue with the firm today. Don MacGregor, John B. A. Mancini, and Jorge Porter were hired during this period. “The business was growing quickly and constantly from the moment I walked in the door,” Don MacGregor said, speaking of his early days with BHA. “Within just a few months of me being hired, the firm added six additional architects, engineers, and design professionals to meet client demands.”
Between 1995 and 1996, the company moved to a larger office (about 2,000 square feet), then added an additional 1,000 square feet of office space by adding on an adjoining unit. However, by 1997, James started looking for new, bigger office space. It was during this time that the firm’s current Chief Executive Officer joined the company.
Susan G. Howe left an executive position at a Newport Beach based business bank to focus her energy full time on the company's financial affairs and regulatory compliance issues.
When James walked in to what is now the firm’s Corporate Headquarters at 5415 E. La Palma in Anaheim Hills, it seemed enormous. At 5,500 square feet, it was twice the size of the modest current office. The space had previously been built out by American Express Travel Related Services.
In 1998, shortly after moving operations to Anaheim Hills, another key person in the BHA story joined the firm, Mark Chapman. "I remember interviewing Mark and feeling strongly that he was destined to become a recognized presence within this industry,” James Howe stated. “I was particularly intrigued with his dual credentials. Being a licensed professional engineer and a licensed general contractor provided the credibility he needed to speak to both civil engineering issues and general contracting or cost issues. This seemed like a win-win for the client. He was also a very strong negotiator coming in, and I respected that," James mused.
Mark recalled the recruitment process and his early discussions with James. "The job at BHA was different and intriguing enough to get me to make what ultimately turned out to be the right decision,” Mark stated. “I had been concerned with design for most of my career, but was interested in this highly specialized niche industry. I knew the industry existed, but it was still highly specialized at the time. I had no idea that I could make a career out of it. Nor did I realize that my skill set as an engineer and contractor was the perfect fit to handle the multi-faceted analysis that is sometimes required. The combination of design analysis, field work, meetings, and mediations turned out to be a refreshing career change.
"Working with Bert was a learning experience I will always remember and cherish,” Mark said. “He always said his door was open anytime I needed anything. When I did have a question, he would always take whatever time was needed to listen, think about it, and give me an answer. I was always impressed because not only did he always have an answer, it was always the right answer. Bert made me feel like family. I knew I had made it and gained his confidence when I walked into his office one day and asked his opinion and he simply said ‘You can handle it, I trust you.’ The past 16 years of my life have been the most rewarding personally and professionally. I owe it mostly to my experience at BHA, the Howe family's generosity, and my associates. It takes a great team to be successful. No one can do it by themselves.”
Soon enough, the once cavernous space was too small. The company was still growing, and arrangements were made to lease the adjoining unit, 5413, doubling the corporate office's footprint to a little over 12,000 square feet. James wondered if the firm would once again fill the new space: “Again, it seemed big at the time,” James said. “Somehow we filled it up, and now we’re busting out of it.”
John Springman joined BHA in June of 2000. John had worked with Bert throughout the years on several cases, John as the architectural expert and Bert as the general contracting/cost designee. They had worked so well together, that Bert spent a year or two recruiting him to join BHA.
By this time, Bert, Susan, and James had expanded their vision from only Bert as an expert witness, to BHA becoming a ‘multi-disciplinary’ firm with experts in differing fields. “At first, [Bert’s] primary form of testimony was cost estimating and standard of care for general contracting practices,” Susan said, “but he soon realized the value in developing a construction experts group comprising licensed architects, engineers, roofing and waterproofing experts, and building envelope specialists."
Susan explained how innovative the one-stop shop philosophy was back then. “[Bert] had not only to recruit John Springman and people like him, but we had to communicate the synergies, cost and productivity benefits to our existing client base, because it was innovative and different.”
However, it didn’t take long for BHA’s clients to reap the great benefits having access to a multi-disciplinary integrated support solution offered: “We were able to provide cost savings to our clients, because we were collecting the data and sharing it to all of the different disciplines within our own organization,” Susan said.
In the early 2000s, the projects began changing from condominium developer cases to single-family home cases. According to John, “The insurance industry started to write in exclusions for condominiums. Forced to go elsewhere for business, it went to single family homes.”
Also around this time, the Aas court decision changed the construction defect industry in California. The court ruled that you have to have damage to have a claim. “Just because a code wasn’t followed didn’t matter unless damage occurred from it,” John said. “It is under breach of contract and other things, but not negligence. Insurance covered negligence, so it took away insurance coverage. Then SB 800 [California’s Right to Repair Act] came about and took a lot of those things and brought them back in.”
While continuing to grow its California market, in 1999 BHA extended its reach into other regions beginning with Nevada and Arizona. By 2003, their reach extended to the east coast with satellite offices in Ohio, Kentucky, and South Carolina.
The types of projects BHA handled also diversified. BHA continued their work with production housing and condominiums and other attached housing, and they supplemented this work with cases involving high-rise and mid-rise buildings, hospitals, hotels, schools and universities, religious institutions, sprawling custom homes, retail complexes, as well as handling delay claims, premises liability, trip-and-fall cases, worker compensation files, and others.
Susan recalled one of BHA’s first international cases that involved a mining operation in Chile. “The core of it was construction defect, but our main job was design analysis and estimating on a really huge scale,” Susan said. The firm was engaged directly through AIG. “An adjuster there contacted Bert at the West Coast Casualty seminar, a few weeks later Bert and half of the office were in Santiago. It was a very memorable assignment; I remember the litigation part of the case was handled largely in the capital city of Santiago. But the mining operations were quite remote. Each of our employees had to undergo altitude testing prior to being performing site investigations at the mining and processing facilities.”
By 2010, BHA had grown to a staff of over forty associates, with satellite offices across the country to support the growing regional businesses. However, in September of 2011, BHA’s beloved founder and President Bert Howe passed away after suffering a heart attack.
While Bert’s presence is still missed by the associates and, most especially, his wife and son, the company was well-positioned to continue on. Susan explained that James for about five years before Bert’s death had been slowly deleveraging Bert from the business. “He was helping his father to be able to work less,” Susan stated. “And as a result of that, we had all these great people like Matt Nardella, John Springman, Mark Chapman, Brad Hughes, John Tolman, Charlie Miller, Jerry Miles, and others who had significant tenure with the firm. They had all worked very closely with Bert, and had really matured, and now they had a few extra gray hairs."
So what’s next for Bert L. Howe & Associates, Inc.? Susan sees greater technological changes, as well as diversification in the types of projects, and the ability to offer additional value added services to their clients.
James stated that BHA has the capability to competitively enter new markets providing a superior credibility, cost, and customer service proposition. “Leveraging from our smart office techniques, proprietary construction forensics technologies, and mature business processes, we could effectively go into any regional market as efficiently as any other company, more efficiently than most, and bring a great deal of value to clients with minimal capital investment in these various markets.”
James also sees more opportunities for career BHA employees who are ready to take on new responsibilities. “I would like to see, and I’m trying to create, new opportunities and challenges for people to continue to be upwardly mobile,” James said. “I am energized by the prospect of delivering additional value to clients, and providing additional opportunities for key people here to grow and improve their lives economically through the growth of the company."
BHA currently is comprised of sixty employees, serving clients throughout the U.S. with offices in Anaheim Hills, California; Sacramento, California; San Diego, California; Las Vegas, Nevada; Salt Lake City, Utah; Denver, Colorado; Phoenix, Arizona; Miami, Florida; Houston, Texas; and San Antonio, Texas.
Read the court decisionRead the full story...Reprinted courtesy of
Nevada’s Construction Defect Law
March 05, 2015 —
Beverley BevenFlorez-CDJ STAFFConstructive Dive reported on the effects of Nevada’s new construction defect law, which is a revision of the original 1995 Homeowners Protection Act: “The new rules more tightly define ‘defect,’ strike the requirement for the losing party to pay the other’s legal fees, and require homeowners to be much more specific about the defects they claim.” Furthermore, it reduces “the length of time a homeowner has to make a construction-defects claim at six years, down from the 10-year statute of limitations in the original law.”
Arizona, Colorado, Florida, and Washington legislators are debating revising their current construction defect laws, according to Construction Dive. “If the Colorado measure passes, homeowners will have to go through arbitration before they’ll be allowed to sue their builders. The proposal in Washington would require the owner making the claim to have a third-party professional inspect the defect before filing a suit,” Construction Dive reported.
Read the court decisionRead the full story...Reprinted courtesy of
Nevada Supreme Court Clarifies the Litigation Waiver of the One-Action Rule
September 07, 2017 —
Bob L. Olson - Snell & Wilmer Real Estate Litigation BlogNevada has a one-action rule which, with limited exceptions, requires a creditor seeking to recover a debt secured by real property to proceed against the security first prior to seeking recovery from the debtor personally. In the event that a law suit is filed in violation of the one-action rule, final judgment may be entered in favor of the creditor but that judgment “releases and discharges the mortgage or other lien.” NRS 40.455(3). Nevada law further provides that, with the exception of certain guaranties, any provision in an agreement relating to the sale of real property which contains a waiver of Nevada’s anti-deficiency laws may not be enforced by a court because doing so violates Nevada’s public policy. NRS 40.453.
Nevada law also addresses when the one-action rule may be waived in litigation. In the author’s view, the governing statute, NRS 40.435 is ambiguous. Section 2 of that statute states that if the one-action rule is timely interposed as an affirmative defense, the action must either be dismissed without prejudice or continued to allow the creditor to file amended pleadings to convert the action into one which does not violate the one-action rule. This suggests that the one-action rule must be asserted as an affirmative defense in the debtor’s answer to the complaint or it is waived by the debtor. The first sentence of section 3 of the statute, however, seems to suggest that the debtor has up until the entry of a final judgment to waive the one-action rule by stating: “[t]he failure to interpose, before the entry of a final judgment, the provisions of NRS 40.430 [the one-action rule] as an affirmative defense in such a proceeding waives the defense in that proceeding.”
Read the court decisionRead the full story...Reprinted courtesy of
Bob L. Olson, Snell & WilmerMr. Olson may be contacted at
bolson@swlaw.com
The American Rescue Plan Act: What Restaurants Need to Act on NOW
March 22, 2021 —
Michael Krueger - Newmeyer DillionThe American Rescue Plan Act (“Act”) was passed by the Senate over the weekend and passed by the House today. President Biden is set to sign the Act into law on Friday, March 12th. The Act has $1.9 Trillion in relief funds with $28.6 Billion set aside for the restaurant industry in the Restaurant Revitalization Fund (“Fund”). The Fund has apportioned funds into two funding groups; $5 Billion for restaurants with annual gross revenue under $500,000 and $23.6 Billion for restaurants over $500,000 in annual gross revenue.
Differences from the Paycheck Protection Program (“PPP”)
This is a grant program with no loan documents or forgiveness applications. Instead, each restaurant entity can apply for and receive up to $10M in grant funds through the Act. The amount a restaurant receives is based on the sum of the restaurant’s gross revenue in 2019 minus the gross revenue in 2020 minus PPP and EIDL money received. For example, Restaurant A made $7M gross revenue in 2019, made $3M gross revenue in 2020 and received $1M in PPP and EIDL combined. ($7M - $3M -$1M =$3M) The restaurant will receive $3M in grant funds directly from the SBA (as long as funds are available).
Read the court decisionRead the full story...Reprinted courtesy of
Michael Krueger, Newmeyer DillionMr. Krueger may be contacted at
michael.krueger@ndlf.com
Sensors for Smarter Construction – Interview with Laura Kassovic of MbientLab
November 17, 2016 —
Aarni Heiskanen – AEC BusinessI had the pleasure of interviewing Laura Kassovic, CEO and Co-founder at MbientLab Inc. We discuss how wearable technology and smart sensors can help on the construction site.
MbientLab is a technology company headquartered in San Francisco, California. It was started about four years ago by a team of engineers who are experts in sensors and machine learning. MbientLab develops wearable technology and also does manufacturing in the USA and Asia.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aarni@aepartners.fi
Insurer's Attempt to Strike Experts in Collapse Case Fails
February 03, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's efforts to exclude two of the insured's experts in a collapse case were unsuccessful. Hudon Specialty Ins. Co. v. Talex Enterprises, LLC, 2019 U.S. Dist. LEXIS 150148 (S.D. Miss. Sept. 4, 2019).
The insureds' building collapsed. The remaining portions of the building required immediate stabilization. The insureds hired Mr. Laird, an engineer, to prevent further property destruction. The insured designated Mr. Laird as a non-retained expert for trial. Mr. Laird's report claimed that the collapse was caused because the building had been re-roofed many times without removal of the degraded underlying roofing materials, thereby adding additional weight to the roof structure.
The insureds also designated Steve Cox as a non-retained expert. Mr. Cox was an architect who owned property neighboring the building that collapsed. He opined that the building collapsed because of the condition of very old mortar and not because of water standing on the building roof or because of roof repairs.
Hudson sought to strike these two experts because their opinions were inconsistent with the admitted facts. A document produced by the insureds stated that a large amount of rainwater had collected on the roof and the weight of the rainfall was the proximate cause of the collapse. Hudson claimed that this statement qualified as a judicial admission, removing the question of causation from contention. The court disagreed that the statement was a judicial admission because it did not form any part of the pleadings. The statement may have been an evidentiary admission that could be controverted or explained by the parties.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com