General Contractors Can Be Sued by a Subcontractor’s Injured Employee
November 05, 2014 —
Craig Martin - Construction Contractor AdvisorGeneral contractors that exercise control over the worksite can be sued by a subcontractor’s injured employee. The Nebraska Supreme Court’s recent opinion, Gaytan v. Wal-Mart, should serve as a reminder that general contractors may be responsible for the safety of all workers on a job site.
In this case, a roofing subcontractor’s employee died after falling through the roof of the under-construction Wal-Mart. The deceased employee’s estate sued Wal-Mart and Gram Construction, the general contractor, alleging that they were negligent in maintaining a safe worksite.
The court initially acknowledged that an owner, the employer of an independent contractor, does not typically owe a subcontractor’s employee a duty because the owner typically has no control over the manner in which the work is to be done by the contractor. This general rule, however, has exceptions, such as where the owner retains control over the contractor’s work. But, for the exception to apply, the owner must have (1) supervised the work that caused the injury, (2) actual or constructive knowledge of the danger that caused the injury, and (3) the opportunity to prevent the injury.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Wyncrest Commons: Commonly Used Progress Payments in Construction Contracts Do Not Render Them Installment Contracts
December 11, 2023 —
Benjamin J. Hochberg - Peckar & Abramson, P.C.In BIL-JIM Construction Company, Inc. v. Wyncrest Commons, LP, 2023 WL 7276637 (Unpublished, decided November 3, 2023), the New Jersey Appellate Division was asked to consider two issues regarding the interpretation and application of a construction contract that utilized the standard form American Institute of Architects owner/contractor agreement (AIA Document A101-2007) (the “AIA Contract”). Specifically, it was asked to consider: 1) whether a modified AIA Contract was an “installment contract,” whereby each progress payment was subject to its own statute of limitations; and 2) whether and when work had been approved in the context of New Jersey’s Municipal Land Use Law. While the decision is presently unpublished, it provides guidance as to how form contracts utilizing the same or similar terms will be treated by New Jersey’s courts and is a reminder that the potential for future claims must be considered during contract negotiations.
Discussion
The primary issue in Wyncrest was whether an AIA Contract was an “installment contract,” and the remaining issues turned on the resolution of this question. Wyncrest, the owner for the project at issue, did not dispute that its contractor, BIL-JIM Construction Company, Inc., had not been fully paid for work that it had performed in connection with a construction project located in Ocean County, New Jersey. Instead, Wyncrest argued that because its AIA Contract with BIL-JIM required that invoices be presented and paid monthly, it constituted an “installment contract.” As such, older payments would be treated as individual transactions and were time barred by the applicable statute of limitations. The trial court agreed with Wyncrest’s characterization of the AIA Contract as an “installment contract,” and found that BIL-JIM’s invoices were each subject to their own statute of limitations. However, the trial court disagreed with Wyncrest’s argument that BIL-JIM’s claim for retainage—which was submitted at the end of its work at the project—was time barred.
Read the court decisionRead the full story...Reprinted courtesy of
Benjamin J. Hochberg, Peckar & Abramson, P.C.Mr. Hochberg may be contacted at
bhochberg@pecklaw.com
Unjust Enrichment Claims When There Is No Binding Contract
December 04, 2023 —
David Adelstein - Florida Construction Legal UpdatesA recent appellate opinion starts off, “This is a typical South Florida construction dispute.” (See case citation at the bottom) Let’s see, is it? No. It’s a garden variety payment dispute where the parties did NOT have a binding contract. Why? That’s for a different day (because the smart practice is ALWAYS to have a contract!) but it touches on the equitable, unjust enrichment claim. And it touches on competing unjust enrichment claims and the apportionment of those claims. In other words, can both parties be right on their unjust enrichment claims?
An owner hired a general contractor for home renovations. Work started but the relationship soured and the general contractor did not complete the work. The general contractor filed a payment dispute against the owner based on unpaid invoices. It pled alternative theories of recovery against the owner: breach of contract and unjust enrichment. The owner filed a counterclaim against the general contractor for the same claims. During the non-jury trial, the general contractor presented unpaid invoices along with testimony that the invoices represented the value of services rendered. The owner presented evidence of the completion of work damages.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
NJ Supreme Court Declines to Review Decision that Exxon Has No Duty to Indemnify Insurers for Environmental Liability Under Prior Settlement Agreement
November 29, 2021 —
Patricia B. Santelle & Laura Rossi - White and WilliamsOn November 1, 2021, in a single-sentence Order, the Supreme Court of New Jersey denied a request for review of a decision that ExxonMobil Corporation (Exxon) did not have to indemnify certain of its insurers over environmental liabilities as required by a previous settlement agreement. The case, entitled Home Insurance Company v. Cornell-Dubilier Electronics Incorporated, et al., has a unique and convoluted procedural history but, in short, the denial of review leaves standing a holding by the intermediate appellate court that the insurers’ “untimely notice actually prejudiced Exxon, violated the no-prejudice rule, and breached the covenant of good faith and fair dealing.” The court declined to consider the question framed by the insurers: whether the importance of enforcing settlement agreements outweighs New Jersey’s entire controversy doctrine.
The matter dated back almost thirty years, when the New Jersey Department of Environmental Protection notified the Appearing London Market Insurers (ALMI) of the potential liability of Cornell-Dublier Electronics (CDE), a former indirect subsidiary of Exxon, for pollution at a site in New Jersey. Coverage litigation followed in New Jersey, which ALMI defended under policies issued to CDE. Exxon was not named in the CDE suit nor were the policies which ALMI issued to Exxon at issue in that case; Exxon instead had its own pollution coverage case pending in New York. In June 2000, Exxon and its insurers, including ALMI, entered into a settlement agreement which (a) required Exxon to indemnify the insurers for any environmental liability claims involving its subsidiaries, and (b) provided for application of New York substantive law and litigation in New York City court for any dispute between the parties under it.
Reprinted courtesy of
Patricia B. Santelle, White and Williams and
Laura Rossi, White and Williams
Ms. Santelle may be contacted at santellep@whiteandwilliams.com
Ms. Rossi may be contacted at rossil@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Client Advisory: The Power of the Bonded Stop Notice Extends to Expended Construction Funds
February 07, 2014 —
Steven M. Cvitanovic - Haight Brown & Bonesteel LLPCFO to CEO: “I have bad news, the developer on our biggest project has run out of money.” Frightening words for sure, but contractors should not overlook the bonded stop notice in situations where the construction lender seemingly has expended all construction funds. The recent case of Brewer Corporation v. Point Center Financial, Inc. 2014 WL 346636 illustrates this point.
Contractors have two options at their disposal to secure payment on private works of improvement. The first is the mechanics lien. However, construction loan trust deeds are normally recorded prior to the commencement of construction and therefore have priority over mechanics liens. Connolly Development, Inc. v. Superior Court (1976) 17 Cal.3d 803, 827. Enter the bonded stop notice. The bonded stop notice requires the lender to withhold unexpended funds and, if it fails to do so, it is personally liable to the claimant for the full amount of the claim. But the stop notice also has the power of “priority” over any assignment of construction loan funds, whether before or after a stop notice is served. Civil Code § 3166, now Civil Code § 8544.
Read the court decisionRead the full story...Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLPMr. Cvitanovic may be contacted at
scvitanovic@hbblaw.com
New Jersey Firm’s Fee Action Tossed for not Filing Substitution of Counsel
August 13, 2014 —
Beverley BevenFlorez-CDJ STAFFEven though their client had terminated their services by email, a “New Jersey appeals court has tossed out a firm’s fee action” finding that the firm had “remained counsel of record because it did not file a substitution of counsel until almost a year later,” the New Jersey Law Journal reported.
In Arturi, D’Argenio, Guagliardi & Meliti v. Sadej, Jesse and Carla Sadej had retained the firm, Arturi, D’Argenio, Guagliardi & Meliti, “to defend them in the underlying land use litigation brought in 2002 by the borough of Seaside Park, N.J.” The case had been dismissed, but was reinstated in 2009 by an appeals court.
At that time, Arturi D’Argenio told the Sadejs that they would need to sign a new retainer agreement in order to continue representation. On July 18, 2010, the Sadejs emailed the firm stating that they were “officially terminated,” according to the opinion as quoted by the New Jersey Law Journal.
The firm sued the Sadejs “for about $100,000 in fees it was allegedly owed from the Seaside Park case and other matters on behalf of Jesse Sadej.” However, a substitution of attorney wasn’t filed until months later.
The case went to the appeals court, which stated that the firm should have withdrawn immediately after receiving the email notification from their client: “Because it failed to do so, it remained counsel of record and therefore was precluded from initiating the collection action at that point,” the judges said, as quoted by the New Jersey Law Journal.
Read the court decisionRead the full story...Reprinted courtesy of
Texas School District Accepts Settlement Agreement in Construction Defect Case
October 08, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Pine Tree ISD Board of Trustees “voted to accept a mediated settlement agreement to end litigation concerning the District’s middle school and its construction issues,” according to KETK News. Pine Tree ISD, located in Longview, Texas, “sued a number of defendant companies for construction and design defects at that campus.”
The school district “will receive the total sum of $820,500,” which “will cover the District’s costs in remediating the campus to repair the construction problems, as well as implementing new systems designed to prevent future issues, both of which came out of the District’s general fund.”
Read the court decisionRead the full story...Reprinted courtesy of
Construction Case Alert: Appellate Court Confirms Engineer’s Duty to Defend Developer Arises Upon Tender of Indemnity Claim
January 27, 2010 —
Steven M. CvitanovicIn the recent case of UDC-Universal Development, L.P. v. CH2M Hill, 2010 Cal.App.LEXIS 47 (filed January 15, 2010), the Sixth District Court of Appeal provided a stunning illustration of the far-reaching effects of the California Supreme Court’s holding in Crawford v. Weather Shield Manufacturing Inc. (2008) 44 Cal.4th 541. In Crawford, the Court held the duty to defend under an indemnity agreement arose upon the mere tender of defense of a claim covered by the indemnity.
In the UDC case, CH2M Hill provided engineering and environmental planning services to developer UDC on a project that ultimately wound up in a construction defect lawsuit by the homeowners association ( HOA ). UDC tendered its defense to CH2M Hill, the tender was rejected, and UDC filed a cross-complaint for negligence, breach of contract and indemnity against CH2M Hill and others. After the HOA’s construction defect claims were settled, UDC proceeded to trial against CH2M Hill. The jury found in favor of CH2M Hill on the claims for negligence and breach of contract. At the request of the parties prior to trial, the trial court ruled on the application of the indemnity agreement in light of Crawford and, in so doing, found that the defense obligation arose upon the tender and that CH2M Hill breached that duty despite the jury finding in favor of CH2M Hill.
The Court of Appeal affirmed, noting that the defense obligation arose as soon as the defense was tendered and did not depend on the outcome of the litigation, and that the HOA’s general description of the defects along with an allegation that Doe engineers were negligent triggered the duty to defend.
Although this case did not expand the crushing impact of Crawford’s holding, it is
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of