Material Prices Climb…And Climb…Are You Considering A Material Escalation Provision?
May 31, 2021 —
David Adelstein - Florida Construction Legal UpdatesAs you may know, material prices have been climbing. And they continue to climb based on the volatility of the material market. On top of that, there are lead times in getting material due to supply chain and other related concerns. The question is, how are you addressing these risks? These are risks that need to be addressed in your contract.
As it relates to climbing material prices, one consideration is a material escalation provision. The objective of this provision is to address the volatility of the material market in economic climates, such as today’s climate, where the price of material continues to climb. Locking down a material price today will be different than locking down the same price months from today. This volatility and risk impacts pricing and budgets. Naturally, an owner and contractor would like to be in a position to lock down supplier prices as soon as possible—both to secure pricing and to account for items with long lead times or that recent data forecasts a long lead time due to supply chain concerns. However, this is not always possible or practical and can depend on numerous issues such as when the owner contracts with the contractor, when the owner issues the notice to proceed (and permits are issued), final construction documents and revisions to the construction documents, the type of material, whether there is staging or storage available for the materials, and the current status including climitazation of the project.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
August 06, 2019 —
William L. Porter - Porter Law GroupThe “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Non-Responsibility will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
We Knew Concrete Could Absorb Carbon—New Study Tells How Much
December 08, 2016 —
Thomas F. Armistead – Engineering News-RecordConcrete’s large carbon footprint—that is, the amount of carbon dioxide emitted during the cement manufacturing process—is estimated to be 5% of industrial CO2 emissions, a source of concern in the battle against human-caused climate change. But last month, an international research team reported that substantial quantities of CO2 are reabsorbed, or sequestered, by cement-based products over their life cycle.
Read the court decisionRead the full story...Reprinted courtesy of
Thomas F. Armistead, Engineering News-RecordENR may be contacted at
enr.com@bnpmedia.com
How to Build Climate Change-Resilient Infrastructure
July 20, 2020 —
Aarni Heiskanen - AEC BusinessOhio University has released a guide titled, An Engineer’s Guide to Building Climate Change-Resilient Infrastructure. It was created for engineers, environmentalists, climate change communities, and construction organizations who are looking to share information about the importance of building cities that are able to fight growing climate threats.
Aarni Heiskanen, AEC Business
Mr. Heiskanen may be contacted at aec-business@aepartners.fi
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Spearin Doctrine: Alive, Well and Thriving on its 100th Birthday
January 15, 2019 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCOn December 9, 2018, United States v. Spearin, [1] a landmark construction law case, will be 100 years old. The Spearin “doctrine”[2] provides that the owner impliedly warrants the information, plans and specifications which an owner provides to a general contractor. The contractor will not be liable to the owner for loss or damage which results from insufficiencies or defects in such information, plans and specifications.
Some construction lawyers questioned whether the Spearin doctrine was still viable in Washington after the Washington Court of Appeals decided the recent case of King County v. Vinci Constr. Grand Projets.[3] Some concerned contractor industry groups even considered a “statutory fix” in the wake of the Court of Appeals Vinci decision. It is our opinion that the facts in the Vinci case are distinguishable and the Spearin doctrine is alive and thriving in Washington.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
Waiver of Subrogation and Lack of Contractual Privity Bars Commercial Tenants’ Claims
May 08, 2023 —
Melissa Kenney - The Subrogation StrategistIn United States Automatic Sprinkler Corporation v. Erie Insurance Exchange, et al., No. 2SS-CT-264, 2023 Ind. LEXIS 105, the Supreme Court of Indiana (Supreme Court) reversed an order of the trial court that denied a motion for summary judgment filed by a sprinkler contractor. At issue was whether commercial tenants – one who contracted with the sprinkler contractor and others who did not – could recover for their respective property damages. The court held that under the contract’s subrogation waiver and agreement to insure, the contracting tenant waived its insurer’s rights to recover through subrogation. With respect to the non-contracting tenants, who sought to recover only property damages, the court held that the absence of contractual privity barred their recovery.
The case centered around a sprinkler system that malfunctioned and flooded the Sycamore Springs Office Complex (Landlord), causing extensive property damage to four commercial tenants. Surgery Center, one of the four tenants, requested permission from the Landlord to install a sprinkler system inside the building. Landlord agreed, in exchange for Surgery Center agreeing to be solely responsible for maintaining the sprinkler system. Surgery Center hired United States Automatic Sprinkler (Automatic Sprinkler) to both install and conduct periodic inspection and testing of the sprinkler system. The contract terms outlined the scope of work to be performed by Automatic Sprinkler and the work was limited to the inspection and testing of the sprinkler system. Although repairs and emergency services were excluded from the contract, each could be performed upon the request and authorization of Surgery Center for an additional cost. The contract also contained certain risk allocation provisions including a waiver of subrogation and an agreement to insure.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Kenney, White and Williams LLPMs. Kenney may be contacted at
kenneyme@whiteandwilliams.com
California Supreme Court Allows Claim Under Unfair Competition Statute To Proceed
October 16, 2013 —
Tred Eyerly — Insurance Law HawaiiThe California Supreme Court determined that insurance practices violating the state's Unfair Insurance Practices Act (UIPA) could support a claim under the state's unfair competition law (UCL). Zhang v. Superior Court, 57 Cal. 4th 353 (2013).
Zhang purchased a CGL policy from California Capital Insurance Company. She sued California Capital in a dispute over coverage for fire damage to her commercial property. The complaint included causes of action for breach of contract, breach of the implied covenant of good faith and fair dealing, and violation of the UCL. In her UCL claim, Zhang alleged that California Capital had "engaged in unfair, deceptive, untrue, and/or misleading advertising" by promising to provide timely coverage in the event of a compensable loss, when it had no intention of paying the true value of the insureds' covered claims.
Zhang specifically alleged unreasonable delays causing deterioration of her property; withholding of policy benefits; refusal to consider cost estimates; misinforming her as to the right to an appraisal; and falsely telling her mortgage holder that she did not intend to repair the property, resulting in foreclosure proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Insurer's Denial of Coverage to Additional Insured Constitutes Bad Faith
May 21, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe insurer's unreasonable denial of a defense and indemnity to a lessor/additional insured was found to be in bad faith. Seaway Props. v. Fireman's Fund Ins. Co., 2014 U.S. Dist. LEXIS 55998 (W.D. Wash. April 22, 2014).
Seaway leased restaurant space to Ciao Bella Food, LLC. In January 10, 2010, the underlying plaintiff was on her way to the restaurant when she attempted to step down from a concrete platform between the building parking lot and the entrance to the restaurant. Seaway's lease gave Ciao Bella the right to use the common areas, including the parking lot, but did not grant Ciao Bella exclusive control over the common areas. The plaintiff suffered injuries and claimed both Ciao Bella and Seaway were liable.
Seaway's lease required Ciao Bella to maintain a CGL policy and to name Seaway as an additional insured. Ciao Bella did so by securing a policy with Fireman's Fund. Fireman's Fund had notice of the plaintiff's claim by November 2010. Seaway demanded in March 2012 that Fireman's Fund indemnify and defend it. In September 2012, two years after it first learned of the plaintiff's injury, Fireman's Fund denied coverage, asserting that Seaway was not an insured under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at